Integrated Earned Value Gantt Chart (EV-Gantt) Tool for Project Portfolio Planning and Monitoring Optimization
The DOI matches its Crossref record; 58 of the 60 references it cites were found in a registry or an index.
Abstract
Project portfolio management (PPM), as a way to manage multiple projects, is becoming a key managerial skill needed by most organizations, especially those engaged in multiple projects concurrently. These multiple projects usually have different characteristics and functions, yet most existing project portfolio theories do not provide an efficient planning and monitoring tool at the operational level. This research aims to integrate the two most efficient planning and monitoring tools—namely, earned value analysis and the Gantt chart to develop a new PPM tool named earned value Gantt chart (EV-Gantt) for portfolio planning and monitoring. EV-Gantt was tested through scenario analysis and a pilot run using a portfolio of real cases. Results show that EV-Gantt performed satisfactorily in resource allocation, systematic reporting, and monitoring enhancement. A standard operating procedure was developed to facilitate implementation of the EV-Gantt tool by engineering managers.
Overview
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
Citations
Cites
Managing Innovation: Integrating Technological, Market and Organizational Change
Tidd, J., Bessant, J., & Pavitt, K. (1997) · University of Maribor digital library (University of Maribor) · Cited by 4,437
A Guide to the project management body of knowledge
(1996) · Choice Reviews Online · doi:10.5860/choice.34-1636 · Cited by 4,339
A guide to the project management body of knowledge (PMBOK guide)
Pmbok (2004) · Cited by 4,316
Managing Innovation: Integrating Technological, Market and Organizational Change
Hayward, G. (1998) · Technovation · doi:10.1016/s0166-4972(98)80033-3 · Cited by 1,856
Causes and effects of delays in Malaysian construction industry
Sambasivan, M., & Soon, Y. W. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.11.007 · Cited by 1,422
Project Success: A Multidimensional Strategic Concept
Shenhar, A. J., Dvir, D., Levy, O., & Maltz, A. C. (2001) · Long Range Planning · doi:10.1016/s0024-6301(01)00097-8 · Cited by 1,222 · cited 2×
“A resource allocation plan is prepared to ensure all concurrent projects have enough resources to be completed successfully according to the portfolio strategy (PMI, 2006; Qin, Grasman, Long, Lin, & Thomas, 2012; Shenhar et al., 2001).”
BackgroundAn integrated framework for project portfolio selection
Archer, N. P., & Ghasemzadeh, F. (1999) · International Journal of Project Management · doi:10.1016/s0263-7863(98)00032-5 · Cited by 856
Current practice in project management — an empirical study
White, D., & Fortune, J. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00029-6 · Cited by 705
Portfolio management for new product development: results of an industry practices study
Cooper, R., Edgett, S., & Kleinschmidt, E. (2001) · R&D Management · doi:10.1111/1467-9310.00225 · Cited by 702
Project Management: The Managerial Process
Gray, C. F., & Larson, E. W. (1999) · Cited by 536
Project management: the managerial process
(2010) · International Journal of Managing Projects in Business · doi:10.1108/17538371011076145 · Cited by 478
(1986) · European Management Journal · doi:10.1016/s0263-2373(86)80049-4 · Cited by 435
Meskendahl, S. (2010) · International Journal of Project Management · doi:10.1016/j.ijproman.2010.06.007 · Cited by 423
Earned Value Project Management Method and Extensions
Anbari, F. T. (2003) · Project Management Journal · doi:10.1177/875697280303400403 · Cited by 392
Project portfolio selection through decision support
Ghasemzadeh, F., & Archer, N. P. (2000) · Decision Support Systems · doi:10.1016/s0167-9236(00)00065-8 · Cited by 380
The impact of project portfolio management on information technology projects
Reyck, B. D., Grushka-Cockayne, Y., Lockett, M., Calderini, S. R., Moura, M., & Sloper, A. (2005) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.02.003 · Cited by 316
Project portfolio management – There’s more to it than what management enacts
Blichfeldt, B. S., & Eskerod, P. (2008) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.06.004 · Cited by 303
Technology portfolio management: optimizing interdependent projects over multiple time periods
Dickinson, M. W., Thornton, A. C., & Graves, S. (2001) · IEEE Transactions on Engineering Management · doi:10.1109/17.969428 · Cited by 296
Lipke, W., Zwikael, O., Henderson, K., & Anbari, F. (2009) · International Journal of Project Management · doi:10.1016/j.ijproman.2008.02.009 · Cited by 292
Project portfolio management in practice and in context
Martinsuo, M. (2013) · International Journal of Project Management · doi:10.1016/j.ijproman.2012.10.013 · Cited by 287
Gantt charts: A centenary appreciation
Wilson, J. M. (2003) · European Journal of Operational Research · doi:10.1016/s0377-2217(02)00769-5 · Cited by 246
Jonas, D. (2010) · International Journal of Project Management · doi:10.1016/j.ijproman.2010.07.002 · Cited by 220
Maylor, H. (2001) · European Management Journal · doi:10.1016/s0263-2373(00)00074-8 · Cited by 207
Formalization of project portfolio management: The moderating role of project portfolio complexity
Teller, J., Unger, B. N., Kock, A., & Gemünden, H. G. (2012) · International Journal of Project Management · doi:10.1016/j.ijproman.2012.01.020 · Cited by 198
A typology of project management: emergence and evolution of new forms
Evaristo, R., & van Fenema, P. C. (1999) · International Journal of Project Management · doi:10.1016/s0263-7863(98)00041-6 · Cited by 194
Project management and business development: integrating strategy, structure, processes and projects
Merwe, A. P. V. D. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(01)00012-6 · Cited by 182
The integration of ideation and project portfolio management — A key factor for sustainable success
Heising, W. (2012) · International Journal of Project Management · doi:10.1016/j.ijproman.2012.01.014 · Cited by 182
A model for effective implementation of Earned Value Management methodology
Kim, E., Wells, W. G., & Duffey, M. R. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00049-2 · Cited by 177
Ziegler, R. J., & Buffa, E. S. (1962) · Journal of the American Statistical Association · doi:10.2307/2282474 · Cited by 173
Pajares, J., & López-Paredes, A. (2011) · International Journal of Project Management · doi:10.1016/j.ijproman.2010.04.005 · Cited by 162
Young, R., Young, M., Jordan, E., & O'Connor, P. E. (2012) · International Journal of Project Management · doi:10.1016/j.ijproman.2012.03.003 · Cited by 160
A fuzzy approach for the earned value management
Naeni, L. M., Shadrokh, S., & Salehipour, A. (2010) · International Journal of Project Management · doi:10.1016/j.ijproman.2010.07.012 · Cited by 151
Dynamic capability through project portfolio management in service and manufacturing industries
Killen, C. P., & Hunt, R. (2010) · International Journal of Managing Projects in Business · doi:10.1108/17538371011014062 · Cited by 140
Understanding stakeholders' perspective of cost estimation in project management
Doloi, H. K. (2010) · International Journal of Project Management · doi:10.1016/j.ijproman.2010.06.001 · Cited by 138
Project Management in Construction: Software Use and Research Directions
Liberatore, M. J., Pollack‐Johnson, B., & Smith, C. A. (2001) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2001)127:2(101 · Cited by 135
Lee, S. H., Pena-Mora, F. A., & Park, M. (2005) · Automation in Construction · doi:10.1016/j.autcon.2005.02.008 · Cited by 134
A competency model for effectiveness in managing multiple projects
Patanakul, P., & Milosevic, D. Z. (2008) · The Journal of High Technology Management Research · doi:10.1016/j.hitech.2007.12.006 · Cited by 109
Anderson, D. K., & Merna, T. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00087-x · Cited by 90
Young, M., & Conboy, K. (2013) · International Journal of Project Management · doi:10.1016/j.ijproman.2013.03.005 · Cited by 76
Motivation by Project and Functional Managers in Matrix Organizations
Dunn, S. C. (2001) · Engineering Management Journal · doi:10.1080/10429247.2001.11415110 · Cited by 66
Bakker, R. M., Knoben, J., de Vries, N., & Oerlemans, L. A. G. (2010) · International Journal of Project Management · doi:10.1016/j.ijproman.2010.04.006 · Cited by 66
Application of multiagent systems in project management
Yan, Y., Kuphal, T., & Bode, J. (2000) · International Journal of Production Economics · doi:10.1016/s0925-5273(00)00082-7 · Cited by 63
Acebes, F., Pajares, J., Galán, J. M., & López-Paredes, A. (2013) · Procedia - Social and Behavioral Sciences · doi:10.1016/j.sbspro.2013.03.027 · Cited by 62
Multi-objective optimization model for multi-project scheduling on critical chain
Wang, W., Wang, X., Ge, X., et al. (2013) · Advances in Engineering Software · doi:10.1016/j.advengsoft.2013.11.004 · Cited by 58
A time-dependent earned value model for software projects
Warburton, R. D. H. (2011) · International Journal of Project Management · doi:10.1016/j.ijproman.2011.02.008 · Cited by 54
Long, S. K., & Spurlock, D. G. (2008) · Engineering Management Journal · doi:10.1080/10429247.2008.11431764 · Cited by 46
Trabold, F. W., & Clark, W. (1947) · Cited by 38
Strategic Decisions in Complex Stakeholder Environments: A Theory of Generalized Exchange
Cameron, B. G., Crawley, E. F., Feng, W., & Lin, M. (2011) · Engineering Management Journal · doi:10.1080/10429247.2011.11431907 · Cited by 33
International Journal of Latest Trends in Finance and Economic Sciences
Filipe, J., & Portela, S. (2011) · International journal of latest trends in finance and economic sciences · Cited by 33
Abdul‐Rahman, H., Chen, W., & Muhammad, N. B. (2011) · Journal of Civil Engineering and Management · doi:10.3846/13923730.2011.598331 · Cited by 29
Self-citationAlvarado, C. M., Silverman, R. P., & Wilson, D. S. (2004) · Journal of Facilities Management · doi:10.1108/14725960510808419 · Cited by 26
Evidence-Based Scope for Reducing “Fire-Fighting” in Project Management
Wearne, S. (2014) · Project Management Journal · doi:10.1002/pmj.21395 · Cited by 17
Waters, N., & Beruvides, M. G. (2012) · Engineering Management Journal · doi:10.1080/10429247.2012.11431936 · Cited by 15
A Framework of Cost-Effectiveness Analysis for Alternative Energy Strategies
Qin, R., Grasman, S. E., Long, S. K., et al. (2012) · Engineering Management Journal · doi:10.1080/10429247.2012.11431953 · Cited by 13
Toomey, J. W. (2000) · Materials management/logistics series · doi:10.1007/978-1-4615-4363-3_12 · Cited by 11
A New, Competency‐based, On‐the‐job Programme for Developing Professional Excellence in Engineering
Cobb, J., & Gibbs, J. M. (1990) · Journal of Management Development · doi:10.1108/eum0000000001372 · Cited by 10
Alford, L. P. (1924) · Medical Entomology and Zoology · Cited by 4
An approach to earned value analysis (EVA): an application to a practical case
Pedro, M. I., Pereira, J. B. L., Filipe, J., & Ferreira, M. (2011) · OAR@UM (University of Malta) · doi:10.35808/ijfirm/8 · Cited by 2
Research works printed but not linked: 13
- Abba W. F., 1997, Program Manager, 26, 58
- Association for Project Management, 2008, Earned value analysis: APM guidelines
- Bauer N., 2004, Project Management Network, 18, 29
- Cooper R. G., 2002, Portfolio management: Fundamental to new product success: The PDMA toolbook for new product development
- Department of Defense, 2012, Earned value analysis system (EVAS) program analysis pamphlet (PAP)
- Fleming Q. W., 1998, The Journal of Defense Software Engineering, July, 19
- Gantt H. L., 1903, ASME Transactions, 24, 1322
- Kim E. H., 2003, International Journal of Project Management, 21, 375, 10.1016/S0263-7863(02)00049-2 · DOI · Paper page
- National Society of Professional Engineers (NSPE), 2013, Engineering body of knowledge
- PM Network, 1995, PM Network July, 1995, 35
- Project Management Institute (PMI), 2005, Practice standard for earned value management
- Project Management Institute (PMI), 2006, The Standard for Portfolio Management
- Taylor F. W., 1903, ASME Transactions, 24, 1337
Cited by
Song, J., Martens, A., & Vanhoucke, M. (2021) · European Journal of Operational Research · doi:10.1016/j.ejor.2021.05.036 · Cited by 49
Measuring the Impact of Scope Changes on Project Plan Using EVM
Tariq, S., Ahmad, N., Ashraf, M. U., Alghamdi, A. M., & Alfakeeh, A. S. (2020) · IEEE Access · doi:10.1109/access.2020.3018169 · Cited by 41
“In article [28], the author has integrated monitoring and planning techniques (EVA and Gantt chart) by developing a tool named EV-Gantt.”
MethodEshghi, A., Mousavi, S. M., & Mohagheghi, V. (2019) · Neural Computing and Applications · doi:10.1007/s00521-018-04002-x · Cited by 27
Wu, Z., & Ma, G. (2022) · Engineering Construction & Architectural Management · doi:10.1108/ecam-12-2021-1105 · Cited by 22
The impact of a limited budget on the corrective action taking process
Song, J., Martens, A., & Vanhoucke, M. (2020) · European Journal of Operational Research · doi:10.1016/j.ejor.2020.03.069 · Cited by 21
Metadata
- Authors
- Ong, H. Y., Wang, C., & Zainon, N.
- Affiliations
- University of Malaya (MY)
- Corresponding author
- Ong, Hong Yeow
- ORCID
- Zainon, Nurshuhada
- Venue
- Engineering Management Journal
- Publisher
- Informa UK Limited
- Published
- 2016-01-02
- Volume
- 28
- Issue
- 1
- Pages
- 39-53
- ISSN
- 1042-9247 (ISSN-L)
- 2377-0643
- OpenAlex
- W2298189222
- Cited by
- 22
- References
- 60
- Citations by year
- 2025: 1 · 2024: 3 · 2023: 1 · 2022: 4 · 2021: 5 · 2020: 2 · 2019: 2 · 2018: 3 · 2017: 1
- FWCI
- 2.19
- Type
- journal article
- Language
- en
- Open access
- closed
- Locations
- Engineering Management Journal (publishedVersion)
- Topics
- Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
- Social Sciences › Decision Sciences › Management Science and Operations Research › Resource-Constrained Project Scheduling
- Social Sciences › Economics, Econometrics and Finance › Finance › Capital Investment and Risk Analysis
- Keywords
- earned value analysis, Gantt chart, project portfolio management, project planning, project monitoring, resource allocation, multiple projects, standard operating procedures
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.