Causes of delays on construction projects: a comprehensive list
Open accessThe DOI matches its Crossref record; 92 of the 92 references it cites were found in a registry or an index.
Abstract
Purpose: The purpose of this paper is to present a systematic review of studies on CPD published between 1985 and 2018. Design/methodology/approach: Before identifying common CPD, research trends were examined in terms of the number of publications in selected journals, as well as the contributions made by countries, institutions and researchers. Findings: The findings reveal that researchers from developing countries have contributed the most to identifying the causes of CPD. A total of 149 causes of CPD were identified in a thorough review of 97 selected studies. Weather/climate conditions, poor communication, lack of coordination and conflicts between stakeholders, ineffective or improper planning, material shortages, financial problems, payment delays, equipment/plant shortage, lack of experience/qualification/competence among project stakeholders, labour shortages and poor site management were identified as the ten most common CPDs. Originality/value: Being the first study of its type, this study provides insight into the research output related to this area and identifies a common set of CPDs, which may provide a better understanding of the key areas requiring attention where steps should be taken to minimise or control factors causing delays in construction projects.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Comparison of PubMed, Scopus, Web of Science, and Google Scholar: strengths and weaknesses
Falagas, M. E., Pitsouni, E. I., Malietzis, G. A., & Pappas, G. (2008) · The FASEB Journal · doi:10.1096/fj.07-9492lsf · Cited by 5,039
Causes of delay in large construction projects
Assaf, S. A., & Al-Hejji, S. (2006) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.11.010 · Cited by 1,705
Causes and effects of delays in Malaysian construction industry
Sambasivan, M., & Soon, Y. W. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.11.007 · Cited by 1,422
The project benefits of Building Information Modelling (BIM)
Bryde, D., Broquetas, M., & Volm, J. M. (2013) · International Journal of Project Management · doi:10.1016/j.ijproman.2012.12.001 · Cited by 1,268
A comparative study of causes of time overruns in Hong Kong construction projects
Chan, D. W., & Kumaraswamy, M. M. (1997) · International Journal of Project Management · doi:10.1016/s0263-7863(96)00039-7 · Cited by 831
Causes of construction delay: traditional contracts
Odeh, A. M., & Battaineh, H. T. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00037-5 · Cited by 810
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00055-8 · Cited by 796
Analysing factors affecting delays in Indian construction projects
Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012) · International Journal of Project Management · doi:10.1016/j.ijproman.2011.10.004 · Cited by 745
Factors influencing construction time and cost overruns on high-rise projects in Indonesia
Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997) · Construction Management and Economics · doi:10.1080/014461997373132 · Cited by 698
Cost escalation and schedule delays in road construction projects in Zambia
Kaliba, C., Muya, M., & Mumba, K. (2009) · International Journal of Project Management · doi:10.1016/j.ijproman.2008.07.003 · Cited by 596
Gündüz, M., Nielsen, Y., & Özdemir, M. (2012) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000129 · Cited by 583
Trend of the research on construction and demolition waste management
Yuan, H., & Shen, L. (2011) · Waste Management · doi:10.1016/j.wasman.2010.10.030 · Cited by 574
Critical review of the research on the management of prefabricated construction
Li, C. Z., Shen, Q., & Xue, X. (2014) · Habitat International · doi:10.1016/j.habitatint.2014.04.001 · Cited by 565
Construction delay: a quantitative analysis
Al-Momani, A. H. (2000) · International Journal of Project Management · doi:10.1016/s0263-7863(98)00060-x · Cited by 553
Significant factors causing delay in the UAE construction industry
Faridi, A. S., & El‐Sayegh, S. M. (2006) · Construction Management and Economics · doi:10.1080/01446190600827033 · Cited by 551
Causes of Delay in Large Building Construction Projects
Assaf, S. A., Al-Khalil, M., & Al-Hazmi, M. (1995) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(1995)11:2(45 · Cited by 544
Delays in construction projects: The case of Jordan
Sweis, G., Sweis, R., Abu Hammad, A., & Shboul, A. (2008) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.09.009 · Cited by 534
The significant factors causing delay of building construction projects in Malaysia
Alaghbari, W., Razali A. Kadir, M., Salim, A., & Ernawati (2007) · Engineering, Construction and Architectural Management · doi:10.1108/09699980710731308 · Cited by 489
Causes of Delay in Building Construction Projects in Egypt
Abd El-Razek, M. E., Bassioni, H. A., & Mobarak, A. M. (2008) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2008)134:11(831 · Cited by 463
Causes of delay and cost overruns in Nigerian construction projects
Mansfield, N., Ugwu, O., & Doran, T. (1994) · International Journal of Project Management · doi:10.1016/0263-7863(94)90050-7 · Cited by 457
Delays and cost increases in the construction of private residential projects in Kuwait
Koushki, P. A., Al‐Rashid, K., & Kartam, N. (2005) · Construction Management and Economics · doi:10.1080/0144619042000326710 · Cited by 456
Scientific collaboration and endorsement: Network analysis of coauthorship and citation networks
Ding, Y. (2011) · Journal of Informetrics · doi:10.1016/j.joi.2010.10.008 · Cited by 438
Construction delays in a fast-growing economy: Comparing Thailand with other economies
Ogunlana, S. O., Promkuntong, K., & Jearkjirm, V. (1996) · International Journal of Project Management · doi:10.1016/0263-7863(95)00052-6 · Cited by 390
Lee, M., Wu, Y., & Tsai, C. (2009) · International Journal of Science Education · doi:10.1080/09500690802314876 · Cited by 378
Analysis of cost and schedule performance of international development projects
Ahsan, K., & Gunawan, I. (2010) · International Journal of Project Management · doi:10.1016/j.ijproman.2009.03.005 · Cited by 375
Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects
Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2016) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000391 · Cited by 365
Construction Delays and Their Causative Factors in Nigeria
Aibinu, A. A., & Odeyinka, H. A. (2006) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2006)132:7(667 · Cited by 348
Causes of Delay in Road Construction Projects
Mahamid, I., Bruland, A., & Dmaidi, N. (2011) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000096 · Cited by 345
Causes of delays in Saudi Arabian public sector construction projects
Al‐Kharashi, A., & Skitmore, M. (2009) · Construction Management and Economics · doi:10.1080/01446190802541457 · Cited by 327
Delay Mitigation in the Malaysian Construction Industry
Abdul‐Rahman, H., Berawi, M. A., Berawi, A. R. B., Mohamed, O., Othman, M., & Yahya, I. A. (2006) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2006)132:2(125 · Cited by 326
Tsai, C., & Lydia Wen, M. (2005) · International Journal of Science Education · doi:10.1080/0950069042000243727 · Cited by 307
Problems causing delays in major construction projects in Thailand
Toor, S.-U.-R., & Ogunlana, S. (2008) · Construction Management and Economics · doi:10.1080/01446190801905406 · Cited by 307
The top 10 universal delay factors in construction projects
Zidane, Y. J.-T., & Andersen, B. S. (2018) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-05-2017-0052 · Cited by 294
Delays and cost overruns in the construction projects in the Gaza Strip
Enshassi, A., Al‐Najjar, J., & Kumaraswamy, M. (2009) · Journal of Financial Management of Property and Construction · doi:10.1108/13664380910977592 · Cited by 278
Howard, G. S., Cole, D. A., & Maxwell, S. E. (1987) · American Psychologist · doi:10.1037//0003-066x.42.11.975 · Cited by 277
Alinaitwe, H. M., & Apolot, R. E. (2013) · Cited by 267
Critical Factors Affecting Schedule Performance: Evidence from Indian Construction Projects
Iyer, K. C., & Jha, K. N. (2006) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2006)132:8(871 · Cited by 244
Contributors to construction delays
Kumaraswamy, M. M., & Chan, D. W. M. (1998) · Construction Management and Economics · doi:10.1080/014461998372556 · Cited by 239
CAUSES OF DELAYS IN CONSTRUCTION PROJECTS IN TURKEY
Kazaz, A., Ulubeyli, S., & Tuncbilekli, N. A. (2012) · Journal of Civil Engineering and Management · doi:10.3846/13923730.2012.698913 · Cited by 234
Effect of organizational culture on delay in construction
Arditi, D., Nayak, S., & Damcı, A. (2016) · International Journal of Project Management · doi:10.1016/j.ijproman.2016.10.018 · Cited by 230
Extending citation analysis to non-source items
Butler, L., & Visser, M. S. (2006) · Scientometrics · doi:10.1007/s11192-006-0024-1 · Cited by 214
Durdyev, S., & Mbachu, J. (2011) · Construction Economics and Building · doi:10.5130/ajceb.v11i3.2120 · Cited by 211
Self-citationAnalysing delay causes and effects in Ghanaian state housing construction projects
Amoatey, C. T., Ameyaw, Y. A., Adaku, E., & Famiyeh, S. (2015) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-04-2014-0035 · Cited by 209
Causes of delays in the construction industry in Lebanon
Mezher, T. M., & Tawil, W. (1998) · Engineering Construction and Architectural Management · doi:10.1046/j.1365-232x.1998.00049.x · Cited by 201
Reasons for delays in public projects in Turkey
Arditi, D., Akan, G. T., & Gurdamar, S. (1985) · Construction Management and Economics · doi:10.1080/01446198500000013 · Cited by 198
The ranking of construction management journals
Wing, C. K. (1997) · Construction Management and Economics · doi:10.1080/014461997372953 · Cited by 198
Ruqaishi, M., & Bashir, H. A. (2013) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000248 · Cited by 196
Need for Alternative Research Approaches in Construction Management: Case of Delay Studies
Alsehaimi, A., Koskela, L., & Tzortzopoulos, P. (2012) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000148 · Cited by 193
Analyzing Delays of Road Construction Projects in Cambodia: Causes and Effects
Santoso, D. S., & Soeng, S. (2016) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000467 · Cited by 178
Structural equation model for investigating factors affecting delay in Indian construction projects
Doloi, H. K., Sawhney, A., & Iyer, K. C. (2012) · Construction Management and Economics · doi:10.1080/01446193.2012.717705 · Cited by 170
Factors contributing to project time and hence cost overrun in the Malaysian construction industry
Shehu, Z., Endut, I. R., & Akintoye, A. (2014) · Journal of Financial Management of Property and Construction · doi:10.1108/jfmpc-04-2013-0009 · Cited by 164
Risk matrix for factors affecting time delay in road construction projects: owners' perspective
Mahamid, I. (2011) · Engineering Construction & Architectural Management · doi:10.1108/09699981111180917 · Cited by 163
Bagaya, O., & Song, J. (2016) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000443 · Cited by 163
Causes of delay in residential construction projects in Cambodia
Durdyev, S., Omarov, M., & Ismail, S. (2017) · Cogent Engineering · doi:10.1080/23311916.2017.1291117 · Cited by 158
Self-citationAnalysis of Citation Networks in Building Information Modeling Research
Hosseini, M. R., Maghrebi, M., Akbarnezhad, A., Martek, I., & Arashpour, M. (2018) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001492 · Cited by 156
Self-citationFuzzy Assessment Model to Estimate the Probability of Delay in Turkish Construction Projects
Gündüz, M., Nielsen, Y., & Özdemir, M. (2013) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000261 · Cited by 152
Material and equipment procurement delays in highway projects in Nepal
Manavazhi, M. R., & Adhikari, D. K. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00027-3 · Cited by 152
A review of enabling factors in construction industry productivity in an Australian environment
Hughes, R., & Thorpe, D. (2014) · Construction Innovation · doi:10.1108/ci-03-2013-0016 · Cited by 152
The professionals’ perspective on the causes of project delay in the construction industry
Agyekum‐Mensah, G., & Knight, A. (2017) · Engineering Construction & Architectural Management · doi:10.1108/ecam-03-2016-0085 · Cited by 144
Studying the Reasons for Delay and Cost Overrun in Construction Projects: The Case of Iran
Samarghandi, H., Tabatabaei, S. M. M., Taabayan, P., Hashemi, A. M., & Willoughby, K. A. (2016) · Journal of Construction in Developing Countries · doi:10.21315/jcdc2016.21.1.4 · Cited by 144
Aggregation of factors causing cost overruns and time delays in large public construction projects
Adam, A., Josephson, P., & Lindahl, G. (2017) · Engineering Construction & Architectural Management · doi:10.1108/ecam-09-2015-0135 · Cited by 142
Sambasivan, M., Deepak, T. J., Salim, A. N., & Venishri, P. (2017) · Engineering Construction & Architectural Management · doi:10.1108/ecam-09-2015-0145 · Cited by 138
Reasons for Cost and Schedule Increase for Engineering Design Projects
Chang, A. S.-T. (2002) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(2002)18:1(29 · Cited by 133
A survey of constraints on Iranian construction operatives' productivity
Zakeri, M., Olomolaiye, P. O., Holt, G. D., & HARRIS, F. C. (1996) · Construction Management and Economics · doi:10.1080/014461996373287 · Cited by 130
Understanding time delay disputes in construction contracts
Iyer, K. C., Chaphalkar, N. B., & Joshi, G. A. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.05.002 · Cited by 121
Three-Stage Least-Squares Analysis of Time and Cost Overruns in Construction Contracts
Bhargava, A., Anastasopoulos, P. C., Labi, S., Sinha, K. C., & Mannering, F. (2010) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000225 · Cited by 118
Yang, J.-B., Yang, C.-C., & Kao, C.-K. (2009) · International Journal of Project Management · doi:10.1016/j.ijproman.2009.10.005 · Cited by 118
Importance and ranking evaluation of delay factors for development construction projects in Benin
Akogbe, R., Feng, X., & Zhou, J. (2013) · KSCE Journal of Civil Engineering · doi:10.1007/s12205-013-0446-2 · Cited by 114
Yang, J.-B., & Ou, S.-F. (2008) · Canadian Journal of Civil Engineering · doi:10.1139/l07-101 · Cited by 111
Exploring critical road project delay factors in Ghana
Amoatey, C. T., & Ankrah, A. N. O. (2017) · Journal of Facilities Management · doi:10.1108/jfm-09-2016-0036 · Cited by 111
Reasons for overrun in public sector construction projects in Nigeria
Dlakwa, M. M., & Culpin, M. F. (1990) · International Journal of Project Management · doi:10.1016/0263-7863(90)90032-7 · Cited by 109
Financial-related causes contributing to project delays
Abdul‐Rahman, H., Takim, R., & Min, W. S. (2009) · Journal of Retail & Leisure Property · doi:10.1057/rlp.2009.11 · Cited by 104
Investigating the causes of delay in grain bin construction projects: the case of China
Chen, G., Shan, M., Chan, A. P. C., Liu, X., & Zhao, Y. (2017) · International Journal of Construction Management · doi:10.1080/15623599.2017.1354514 · Cited by 97
Enshassi, A., Kumaraswamy, M. M., & Al‐Najjar, J. (2010) · International Journal of Construction Management · doi:10.1080/15623599.2010.10773137 · Cited by 97
Analysis of non-excusable delay factors influencing contractors' performance in Lagos State, Nigeria
Ibironke, O. T., Oladinrin, O. T., Adeniyi, O., & Eboreime, I. V. (2013) · Journal of Construction in Developing Countries · Cited by 97
Empirical Assessment of the Likelihood and Duration of Highway Project Time Delays
Anastasopoulos, P. C., Labi, S., Bhargava, A., & Mannering, F. (2011) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000437 · Cited by 88
Guarini, M. R., Battisti, F., & Chiovitti, A. (2017) · Buildings · doi:10.3390/buildings8010001 · Cited by 87
Understanding the Dynamics of Construction Decision Making and the Impact on Work Health and Safety
Pirzadeh, P., & Lingard, H. C. (2017) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000532 · Cited by 85
Critical Delaying Factors: Public Sector Building Projects in Gilgit-Baltistan, Pakistan
Hussain, S., Zhu, F., Ali, Z., Aslam, H. D., & Hussain, A. (2018) · Buildings · doi:10.3390/buildings8010006 · Cited by 78
The causes, impacts and mitigations of delay in megaprojects in the Sultanate of Oman
Oyegoke, A. S., & Kiyumi, N. A. (2017) · Journal of Financial Management of Property and Construction · doi:10.1108/jfmpc-11-2016-0052 · Cited by 76
Mahamid, I. (2013) · Construction Economics and Building · doi:10.5130/ajceb.v13i2.3194 · Cited by 73
Understanding delays in housing construction: evidence from Northern Ireland
McCord, J., McCord, M. J., Davis, P. T., Haran, M. E., & Rodgers, W. J. (2015) · Journal of Financial Management of Property and Construction · doi:10.1108/jfmpc-07-2015-0028 · Cited by 66
Kavishe, N., Jefferson, I., & Chileshe, N. (2018) · International Journal of Construction Management · doi:10.1080/15623599.2018.1435154 · Cited by 64
Approaches of Implementing ICT Technologies within the Construction Industry
Hosseini, M. R., Chileshe, N., Zou, J. X., & Baroudi, B. (2013) · Australasian Journal of Construction Economics and Building - Conference Series · doi:10.5130/ajceb-cs.v1i2.3161 · Cited by 60
Self-citationModeling schedule overrun and cost escalation percentages of highway projects using fuzzy approach
El-Maaty, A. E. A., El-Kholy, A. M., & Akal, A. Y. (2017) · Engineering Construction & Architectural Management · doi:10.1108/ecam-03-2016-0084 · Cited by 52
Time Delay and Cost Overrun of Road over Bridge (ROB) Construction Projects in India
Venkateswaran, C. B., & Murugasan, R. (2017) · Journal of Construction in Developing Countries · doi:10.21315/jcdc2017.22.supp1.5 · Cited by 44
Wang, W., Lin, C.-L., Wang, S.-H., Liu, J.-J., & Lee, M. (2014) · Journal of Civil Engineering and Management · doi:10.3846/13923730.2013.801922 · Cited by 44
Vu, H. A., Cu, V. H., Min, L., & Wang, J. Q. (2017) · Engineering Construction & Architectural Management · doi:10.1108/ecam-06-2016-0138 · Cited by 43
Mahamid, I. (2017) · Journal of Financial Management of Property and Construction · doi:10.1108/jfmpc-07-2016-0031 · Cited by 40
4P delays in project management
Ansah, R. H., & Sorooshian, S. (2018) · Engineering Construction & Architectural Management · doi:10.1108/ecam-09-2016-0199 · Cited by 37
Where is intentionality in studying project delays?
Eizakshiri, F., Chan, P., & Emsley, M. W. (2015) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-05-2014-0048 · Cited by 28
Durdyev, S., & Ihtiyar, A. (2018) · Journal of Professional Issues in Engineering Education and Practice · doi:10.1061/(asce)ei.1943-5541.0000402 · Cited by 18
Self-citation
Cited by
Hamledari, H., & Fischer, M. (2021) · Automation in Construction · doi:10.1016/j.autcon.2021.103926 · Cited by 237
Manzoor, B., Othman, I., Durdyev, S., Ismail, S., & Wahab, M. (2021) · Applied System Innovation · doi:10.3390/asi4030052 · Cited by 118
“A suitable example is how a graphical representation of the building structures and systems will provide a complete overview during the construction process [65,66].”
BackgroundSelf-citationMomade, M., Durdyev, S., Estrella, D., & Ismail, S. (2021) · Frontiers in Engineering and Built Environment · doi:10.1108/febe-07-2021-0036 · Cited by 45
Self-citation
Metadata
- Authors
- Durdyev, S., & Hosseini, M. R.
- Venue
- International Journal of Managing Projects in Business
- Publisher
- Emerald
- Published
- 2019-04-12
- Volume
- 13
- Issue
- 1
- Pages
- 20-46
- ISSN
- 1753-8378 (ISSN-L)
- OpenAlex
- W2946135269
- Cited by
- 245
- References
- 92
- FWCI
- 14.13
- Type
- journal article
- Language
- en
- Open access
- green
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.