Causes of delays on construction projects: a comprehensive list
Open accessThe DOI matches its Crossref record; 92 of the 92 references it cites were found in a registry or an index.
Abstract
Purpose: The purpose of this paper is to present a systematic review of studies on CPD published between 1985 and 2018. Design/methodology/approach: Before identifying common CPD, research trends were examined in terms of the number of publications in selected journals, as well as the contributions made by countries, institutions and researchers. Findings: The findings reveal that researchers from developing countries have contributed the most to identifying the causes of CPD. A total of 149 causes of CPD were identified in a thorough review of 97 selected studies. Weather/climate conditions, poor communication, lack of coordination and conflicts between stakeholders, ineffective or improper planning, material shortages, financial problems, payment delays, equipment/plant shortage, lack of experience/qualification/competence among project stakeholders, labour shortages and poor site management were identified as the ten most common CPDs. Originality/value: Being the first study of its type, this study provides insight into the research output related to this area and identifies a common set of CPDs, which may provide a better understanding of the key areas requiring attention where steps should be taken to minimise or control factors causing delays in construction projects.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Comparison of PubMed, Scopus, Web of Science, and Google Scholar: strengths and weaknesses
Falagas, M. E., Pitsouni, E. I., Malietzis, G. A., & Pappas, G. (2008) · The FASEB Journal · doi:10.1096/fj.07-9492lsf · Cited by 5,039
Causes of delay in large construction projects
Assaf, S. A., & Al-Hejji, S. (2006) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.11.010 · Cited by 1,705
Causes and effects of delays in Malaysian construction industry
Sambasivan, M., & Soon, Y. W. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.11.007 · Cited by 1,422
The project benefits of Building Information Modelling (BIM)
Bryde, D., Broquetas, M., & Volm, J. M. (2013) · International Journal of Project Management · doi:10.1016/j.ijproman.2012.12.001 · Cited by 1,268
A comparative study of causes of time overruns in Hong Kong construction projects
Chan, D. W., & Kumaraswamy, M. M. (1997) · International Journal of Project Management · doi:10.1016/s0263-7863(96)00039-7 · Cited by 831
Causes of construction delay: traditional contracts
Odeh, A. M., & Battaineh, H. T. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00037-5 · Cited by 810
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00055-8 · Cited by 796
Analysing factors affecting delays in Indian construction projects
Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012) · International Journal of Project Management · doi:10.1016/j.ijproman.2011.10.004 · Cited by 745
Factors influencing construction time and cost overruns on high-rise projects in Indonesia
Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997) · Construction Management and Economics · doi:10.1080/014461997373132 · Cited by 698
Cost escalation and schedule delays in road construction projects in Zambia
Kaliba, C., Muya, M., & Mumba, K. (2009) · International Journal of Project Management · doi:10.1016/j.ijproman.2008.07.003 · Cited by 596
Cited by
Hamledari, H., & Fischer, M. (2021) · Automation in Construction · doi:10.1016/j.autcon.2021.103926 · Cited by 237
Role of Blockchain-Enabled Smart Contracts in Automating Construction Progress Payments
Hamledari, H., & Fischer, M. (2021) · Journal of Legal Affairs and Dispute Resolution in Engineering and Construction · doi:10.1061/(asce)la.1943-4170.0000442 · Cited by 172
Manzoor, B., Othman, I., Durdyev, S., Ismail, S., & Wahab, M. (2021) · Applied System Innovation · doi:10.3390/asi4030052 · Cited by 118
“A suitable example is how a graphical representation of the building structures and systems will provide a complete overview during the construction process [65,66].”
BackgroundSelf-citationMomade, M., Durdyev, S., Estrella, D., & Ismail, S. (2021) · Frontiers in Engineering and Built Environment · doi:10.1108/febe-07-2021-0036 · Cited by 45
Self-citation
Metadata
- Authors
- Durdyev, S., & Hosseini, M. R.
- Venue
- International Journal of Managing Projects in Business
- Publisher
- Emerald
- Published
- 2019-04-12
- Volume
- 13
- Issue
- 1
- Pages
- 20-46
- ISSN
- 1753-8378 (ISSN-L)
- OpenAlex
- W2946135269
- Cited by
- 245
- References
- 92
- FWCI
- 14.13
- Type
- journal article
- Language
- en
- Open access
- green
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.