Why a Critical Path by Any Other Name Would Smell Less Sweet?: Towards a Holistic Approach to PERT/CPM
The DOI matches its Crossref record; 37 of the 37 references it cites were found in a registry or an index.
Abstract
To maximize the potential of Critical Chain (CC) to enrich project management practice, I discuss Eliyahu Goldratt's work in the context of his entrepreneurial career. I show that PERT/CPM had been an instance of Goldratt's “Theory of Constraints” (TOC) before Goldratt had articulated it. I also highlight errors and questionable recommendations he made. Nonetheless, CC provides a more holistic approach than the typical practice before. I (1) discuss CC and TOC, including strengths and weaknesses, in the relevant context; (2) provide earlier sources for the major so-called Goldratt innovations; (3) identify opportunities for immediate improvement and future research highlighted by Goldratt's work.
Overview
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
Citations
Cites
Deming, W. E. (1982) · Medical Entomology and Zoology · Cited by 7,297
A guide to the project management body of knowledge (PMBOK guide)
Pmbok (2004) · Cited by 4,316
International Journal of Project Management
Turner, J. R. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(03)00062-0 · Cited by 1,176
(2002) · International Series in Operations Research & Management Science · doi:10.1007/b101924 · Cited by 709
Activity networks: Project planning and control by network models
Elmaghraby, S. E. (1977) · Medical Entomology and Zoology · Cited by 582
Dave, U. (1995) · Journal of the Operational Research Society · doi:10.1057/jors.1995.75 · Cited by 517
Heuristic scheduling systems with applications to production systems and project management
(1995) · European Journal of Operational Research · doi:10.1016/0377-2217(95)90067-5 · Cited by 356
On the merits and pitfalls of critical chain scheduling
Herroelen, W., & Leus, R. (2001) · Journal of Operations Management · doi:10.1016/s0272-6963(01)00054-7 · Cited by 350
Computerized shop floor scheduling
GOLDRATT, E. M. (1988) · International Journal of Production Research · doi:10.1080/00207548808947875 · Cited by 277
Non-Stock Production: The Shingo System for Continuous Improvement
新郷, 重. (1988) · Productivity Press eBooks · Cited by 266
Research works printed but not linked: 12
- Cabanis-Brewin J., 1999, PM Network, 13, 49
- Globerson S., 2000, PM Network, 14, 63
- Goldratt E.M., 1997, Critical chain.
- Goldratt E.M., 1984, The goal.
- Goldratt E.M., 1986, The Race.
- Hopp W.J., 2001, Factory physics.
- Nahmias S., 1989, Operations analysis.
- Pervozvansky A.A., 1975, Mathematical models in production management
- Portougal V.M., 1972, Ekonomika i Mathematicheskie Metody, 9, 761
- Trietsch D., 2004, Proceedings of the ORSNZ Conference, 35
- Trietsch D., Human Systems Management.
- Wilkins B., 1984, Computerworld, 2
Cited by
Modeling activity times by the Parkinson distribution with a lognormal core: Theory and validation
Trietsch, D., Mazmanyan, L., Gevorgyan, L., & Baker, K. R. (2011) · European Journal of Operational Research · doi:10.1016/j.ejor.2011.07.054 · Cited by 119
“Advantages of the Lognormal Distribution Baker & Trietsch (2009a) present four arguments why the lognormal distribution is attractive for modeling stochastic activity times: (1) it is strictly positive, (2) its cv is not restricted, (3) it can approximate sums of positive random variables, and (4) it can represent the…”
BackgroundSelf-citationPERT 21: Fitting PERT/CPM for use in the 21st century
Trietsch, D., & Baker, K. R. (2011) · International Journal of Project Management · doi:10.1016/j.ijproman.2011.09.004 · Cited by 115
“Trietsch (2005b) critiques numerous issues about CCPM as presented by Goldratt (1997).”
BackgroundSelf-citationProject Scheduling: Improved Approach to Incorporate Uncertainty Using Bayesian Networks
Khodakarami, V., Fenton, N., & Neil, M. (2007) · Project Management Journal · doi:10.1177/875697280703800205 · Cited by 89
“…(Herroelen & Leus, 2001), and a sound estimation of project and activity duration (and consequently the buffer size) is still essential (Trietsch, 2005 The earliest start and finish times of each activity are determined by working forward through the network and determining the…”
BackgroundThe Theory of Constraints and the Make‐or‐Buy Decision: An Update and Review
Balakrishnan, J., & Cheng, C. H. (2005) · Journal of Supply Chain Management · doi:10.1111/j.1745-493x.2005.tb00183.x · Cited by 54
Current status and future potential of the research on Critical Chain Project Management
Ghaffari, M., & Emsley, M. W. (2015) · Surveys in Operations Research and Management Science · doi:10.1016/j.sorms.2015.10.001 · Cited by 71
“Trietsch (2005a) continues his critique by citing some of the concepts similar to the principles of CCPM that already existed in the literature at the time of CCPM introduction.”
BackgroundMethodInfluentialTying the pieces together: A normative framework for integrating sales and project operations
Cooper, M. J., & Budd, C. S. (2006) · Industrial Marketing Management · doi:10.1016/j.indmarman.2006.03.005 · Cited by 72
Carden, L. L., & Egan, T. M. (2008) · Project Management Journal · doi:10.1002/pmj.20068 · Cited by 63
Multi-project Time-cost Optimization in Critical Chain with Resource Constraints
Amiri, M. J. T., Haghighi, F., Eshtehardian, E., & Abessi, O. (2018) · KSCE Journal of Civil Engineering · doi:10.1007/s12205-017-0691-x · Cited by 38
The effect of systemic errors on optimal project buffers
Trietsch, D. (2005) · International Journal of Project Management · doi:10.1016/j.ijproman.2004.12.004 · Cited by 35
Self-citationE‐GOVERNMENT SERVICE INNOVATION IN THE SCOTTISH CRIMINAL JUSTICE INFORMATION SYSTEM
Kinder, T. (2010) · Financial Accountability and Management · doi:10.1111/j.1468-0408.2009.00489.x · Cited by 34
CRITICAL CHAIN PROJECT MANAGEMENT THEORY AND PRACTICE
Stratton, R. (2009) · Nottingham Trent University's Institutional Repository (Nottingham Trent Repository) · Cited by 31
Teaching Critical Chain Project Management: The Academic Debate and Illustrative Examples
Millhiser, W. P., & Szmerekovsky, J. G. (2012) · INFORMS Transactions on Education · doi:10.1287/ited.1110.0083 · Cited by 24
“In fact, in the project management literature, the idea of a feeding buffer can be traced back to the 1980s (see Trietsch 2005, p. 32, for references).”
BackgroundMethodResultInfluentialNasseri, H. A., Widén, K., & Aulin, R. (2016) · Journal of Engineering Design and Technology · doi:10.1108/jedt-11-2013-0078 · Cited by 19
Applying critical chain buffer management theory in location-based management
Büchmann-Slorup, R. (2013) · Construction Management and Economics · doi:10.1080/01446193.2013.797094 · Cited by 18
“Trietsch (2005) also stated that the assumptions have simply not been proved fatal yet, so it is important to consider whether the assumptions are likely to apply.”
BackgroundFrom feeding-back to feeding-forward: managerial feedback as a trigger of change in SMEs
Psychogios, A. G., Blakçori, F., Szamosi, L. T., & O’Regan, N. (2018) · Journal of Small Business and Enterprise Development · doi:10.1108/jsbed-01-2018-0034 · Cited by 22
Enablers and Barriers to Project Planning and Scheduling Based on Construction Projects in Oman
Nasseri, H. A., & Aulin, R. (2016) · Journal of Construction in Developing Countries · doi:10.21315/jcdc2016.21.2.1 · Cited by 25
“According to Abeyasinghe, Greenwoo and Johansen (2001) and Trietsch (2005), the lack of proper understanding of activity criticality and related resources in project planning can result in "aggressive" schedules with high levels of uncertainty.”
BackgroundFrom Management by Constraints (MBC) to Management By Criticalities (MBC II)
Trietsch, D. (2005) · Human Systems Management · doi:10.3233/hsm-2005-24109 · Cited by 13
“This paper, although it is not focused on project management, has the same mission as [20]: To put 5FS in perspective, highlight the inconsistencies, and build positively on the legitimate contributions.”
BackgroundInfluentialSelf-citationGrey, J. (2007) · Journal of International Crisis and Risk Communication Research · Cited by 12
The Theory of Constraints in Academia: It's Evolution, Influence, Controversies, and Lessons
Balakrishnan, J., Cheng, C. H., & Trietsch, D. (2008) · Libraries and Cultural Resources (University of Calgary) · doi:10.11575/prism/33938 · Cited by 10
Self-citationBuilding Chan Chan: A Project Management Perspective
Smailes, R. L. (2011) · Latin American Antiquity · doi:10.7183/1045-6635.22.1.37 · Cited by 10
Recent Trends in Theory Use and Application within the Project Management Discipline
Johnson, N., Creasy, T., & Fan, Y. (2016) · Journal of Engineering Project and Production Management · doi:10.32738/jeppm.201601.0004 · Cited by 22
“Additionally, Trietsch (2005) declared that TOC should be thought of, not as a theory, but more “management by constraints”.”
BackgroundThe use of the critical path and critical chain methods in the South African construction industry
Deacon, H., & van der Lingen, E. (2015) · Acta Structilia · doi:10.38140/as.v22i1.160 · Cited by 8
Mukherjee, S., & Chatterjee, A. (2006) · Cited by 7
A Theory of Constraints Service Systems Improvement Method: Case of the Airline Turnaround Problem
Ellis, S. (2011) · doi:10.25148/etd.fi11051601 · Cited by 7
Process improvement capability: a study of the development of practice(s)
Jones, O., Gold, J., & Claxton, J. (2019) · Business Process Management Journal · doi:10.1108/bpmj-11-2017-0299 · Cited by 6
Buffer Sizing in CCPM Portfolios with Different Resource Capacities
Ghaffari, M., & Emsley, M. W. (2017) · International Journal of Information Technology Project Management · doi:10.4018/ijitpm.2017070103 · Cited by 5
“…principlesandliterature:e.g.Leach(1999,2003,2014),Lechler,Ronen&Stohr,(2005),Herroelen &Leus(2001),Ghaffari&Emsley(2015),Trietsch(2005),Raz,Barnes&Dvir,(2003),Steyn(2001, 2002),Anantatmula&Webb(2014).”
A Conflict Resolution Tool for Project Managers: Evaporating Cloud
Gupta, M. C., & Kerrick, S. A. (2014) · Journal of international technology and information management · doi:10.58729/1941-6679.1076 · Cited by 4
“…books such as Newbold (1998), Leach (1999), and Hutchin (2001) and critically reviewed with results and practical implications documented in scientific journal articless such as Herroelen, Leus, and Demeulemeester (2002); Raz (2003); Trietsch (2005); and Blackstone, Cox, and Schleier (2009).”
BackgroundImproved methods for task estimation and project tracking
Burns, J. R., & Janamanchi, B. (2007) · International Journal of Information Systems and Change Management · doi:10.1504/ijiscm.2007.015118 · Cited by 3
The Toyota Production System and Lean Manufacturing
Roser, C. (2016) · CRC Press eBooks · doi:10.1201/9781315367941-17 · Cited by 3
Project Management Traditional Principles
Marle, F., & Vidal, L. (2015) · Springer eBooks · doi:10.1007/978-1-4471-6787-7_1 · Cited by 4
Critical Chain Method in Traditional Project and Portfolio Management Situations
Anantatmula, V. S., & Webb, J. B. (2014) · International Journal of Information Technology Project Management · doi:10.4018/ijitpm.2014070104 · Cited by 3
Applying theory of constraints in administrative process: An experiment from the U.S. government
Knaggs, C., Pollard, S. K., & Wang, W. (2012) · International Conference on Management Science and Engineering (ICMSE) · doi:10.1109/icmse.2012.6414447 · Cited by 3
“- 2016 - Fig.3 USSS procurement “doom loop” Years of experimentation with tools such as LSS, TQM, JIT, and MRP had often resulted in short-term improvements, but disappointing long-term results.”
BackgroundInfluentialApplying manufacturing flow theory to construction management
Stratton, R., Koskela, L., Alsehaimi, A., et al. (2010) · Nottingham Trent University's Institutional Repository (Nottingham Trent Repository) · Cited by 3
Holistic Mine Management By Identification Of Real-Time And Historical Production Bottlenecks
Kahraman, M. M. (2015) · UA Campus Repository (The University of Arizona) · Cited by 3
From the Flawed "Theory of Constraints" to Hierarchically Balanced Criticalities (HBC) 1
Trietsch, D. (2004) · Cited by 2
Self-citationThe Role of the Knowledge Intermediary in Evangelical Project and Production Management Theories
Balakrishnan, J., & Cheng, C. H. (2019) · Journal of Engineering Project and Production Management · doi:10.2478/jeppm-2019-0006 · Cited by 2
“Recent updated reviews of TOC/CCPM are provided in Raz et al. (2003), Trietsch (2005), Gupta and Boyd (2008).”
BackgroundMethodInfluentialHuang, C., Li, R.-K., Tsai, C., et al. (2014) · International Journal of Academic Research in Accounting Finance and Management Sciences · doi:10.6007/ijarafms/v4-i1/505 · Cited by 1
“Concerning the second critic, Duncan (1999); Trietsch (2005) have argued that although CCPM presents some good ideas as new insights, these ideas are not new.”
Optimal Crashing and Buffering of Stochastic Serial Projects
Trietsch, D. (2010) · International Journal of Information Technology Project Management · doi:10.4018/jitpm.2010100203 · Cited by 1
“To address this issue, Trietsch (2005) presents the systemic error model, which employs a multiplicative stochastic error that is constant for each project but varies across projects.”
BackgroundSelf-citationProgramação de parada de plataforma marítima utilizando o método da corrente crítica.
Finocchio, J. (2009) · doi:10.11606/d.3.2009.tde-26012009-133737 · Cited by 1
University of Latvia, & Professional Association of Project Managers (Latvia) (2015) · E-resource repository of the University of Latvia (University of Latvia) · doi:10.22364/pmdpp.2015 · Cited by 1
Togun, O. F., Sobowale, O. S., Udom, J. A., et al. (2024) · SSRN Electronic Journal · doi:10.2139/ssrn.4759219 · Cited by 1
Notice of Retraction: The Study on Setting Method of Project Buffers in a Critical Chain
Gong, C., & Qing, S. (2010) · International Conference on E-Business and E-Government · doi:10.1109/icee.2010.720
“It is necessary and useful at this time to re-plan the project and re-identify the critical chain timely ([7,8]).”
BackgroundAya, M. A. S., Plazas, A. A. R., & Afanador, S. D. P. F. (2009) · Repositorio Institucional E-DocUR (Universidad Del Rosario) · doi:10.48713/10336_1259
Baker, K. R., & Trietsch, D. (2009) · doi:10.1002/9780470451793.ch18
Self-citationThe Concurrent Development Scheduling Problem (CDSP)
Paul, L. W. (2005) · Digital Commons - University of South Florida (University of South Florida)
Robust Project Scheduling and Control
Trietsch, D. (2005)
Self-citationModeling Agility Evaluation in Critical Chain Project management (Approach of Dynamic Systems)
Firouzabadi, K. J., Ghalehbin, M. N., Ahmad, S., et al. (2013)
Essentials of Operations Research - Chapter 10: Network Techniques (PERT & CPM)Preprint
Mahto, D. G. (2016) · SSRN Electronic Journal · doi:10.2139/ssrn.2887249
Optimizing The Global Performance Of Build-to-order Supply Chains
Shaalan, T. (2006) · STARS (University of Central Florida)
Adapting Critical Chain Project Management to Army Engineer Construction Projects
Rohr, E. E. (2017) · TopSCHOLAR (Western Kentucky University)
Critical Chain Method in Traditional Project and Portfolio Management Situations
Anantatmula, V. S., & Webb, J. B. (2016) · IGI Global eBooks · doi:10.4018/978-1-5225-0196-1.ch049
Optimal Crashing and Buffering of Stochastic Serial Projects
Trietsch, D. (2012) · IGI Global eBooks · doi:10.4018/978-1-61350-456-7.ch219
Self-citationOptimal Crashing and Buffering of Stochastic Serial Projects
Trietsch, D. (2012) · IGI Global eBooks · doi:10.4018/978-1-4666-0930-3.ch002
Self-citationBaker, K. R., & Trietsch, D. (2018) · doi:10.1002/9781119262602.ch19
Self-citationBonatsos, S. (2019) · theses.fr (ABES) · doi:10.70675/718a0b90z30f6z4a09z8e1ez2dcc4de99874 · Cited by 3
Metadata
- Authors
- Trietsch, D.
- Affiliations
- University of Auckland (NZ)
- Corresponding author
- Trietsch, Dan
- Venue
- Project Management Journal
- Publisher
- SAGE Publications
- Published
- 2005-03
- Volume
- 36
- Issue
- 1
- Pages
- 27-36
- ISSN
- 1938-9507 (ISSN-L)
- 8756-9728
- OpenAlex
- W2182246258
- Cited by
- 57
- References
- 37
- Citations by year
- 2024: 1 · 2019: 3 · 2018: 4 · 2017: 2 · 2016: 7 · 2015: 5 · 2014: 3 · 2013: 2 · 2012: 4
- FWCI
- 6.89
- Type
- journal article
- Language
- en
- Open access
- closed
- Licence
- journals.sagepub.com/page/policies/text-and-data-mining-license (tdm)
- Locations
- Project Management Journal (publishedVersion)
- Topics
- Social Sciences › Decision Sciences › Management Science and Operations Research › Operations Management Techniques
- Social Sciences › Decision Sciences › Management Science and Operations Research › Resource-Constrained Project Scheduling
- Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
- Keywords
- critical chain project management, theory of constraints, PERT/CPM, history of project management, critical path, project scheduling, entrepreneurial careers
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.