EXPLORING CRITICAL SUCCESS FACTORS FOR STAKEHOLDER MANAGEMENT IN CONSTRUCTION PROJECTS

Open access
Yang, Jing, Shen, Geoffrey Qiping, Ho, Manfong, Drew, Derek S., Chan, Albert P. C.·2009·JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT

Abstract

With a focus on different aspects of stakeholder management, various sets of critical success factors (CSFs) have been suggested in the literature. It is crucial to explore the relative importance and groupings of these factors. This paper aims to identify CSFs associated with stakeholder management in construction projects, and explore their ranking and underlying relationship. 15 CSFs were identified through a literature review, and consolidated by interviews and pilot studies with professionals in construction industry. A questionnaire instrument containing these 15 CSFs was sent out to project managers in Hong Kong, and 183 completed questionnaires were retrieved. The top three ranked factors for stakeholder management were “managing stakeholders with social responsibilities”, “assessing the stakeholders’ needs and constraints to the project”, and “communicating with stakeholders properly and frequently”. Using factor analysis and considering the high importance of the factor “managing stakeholders with social responsibilities”, the 15 CSFs were grouped into five dimensions namely, precondition factor, stakeholder estimation, information inputs, decision making, and sustainable support. All these five groupings and their relationship were included in a framework for successful stakeholder management in construction projects. These findings help to clarify what the high prioritized factors are, and could also be used as an assessment tool to evaluate the performance of stakeholder management and thus help to identify areas for improvement. Santrauka Atsižvelgiant į skirtingus suinteresuotųjų šalių valdymo aspektus, literatūroje siūlomi įvairūs kritinių sėkmės veiksnių (KSV) kompleksai. Svarbiausia yra sugrupuoti šiuos veiksnius ir nustatyti jų santykinį reikšmingumą. Šio straipsnio tikslas – nustatyti KSV, susijusius su suinteresuotųjų šalių valdymu statybos projektuose, išnagrinėti jų prioritetus ir pagrindinius tarpusavio ryšius. 15 KSV buvo nustatyta remiantis literatūros analize, statybos šakos profesionalų apklausomis ir eksperimentinėmis studijomis. Projektų valdytojams Honkonge išsiųstas klausimynas ir gauti 183 atsakymai. Trys aukščiausiai įvertinti veiksniai: projektų dalyvių socialinė atsakomybė, suinteresuotųjų šalių poreikių ir apribojimų įvertinimas, tinkamas ir dažnas bendradarbiavimas su suinteresuotomis šalimis. Naudojantis veiksnių analize ir atsižvelgiant į tai, kad socialinės atsakomybės rodiklis vertinamas kaip labai reikšmingas, 15 KSV suskirstyti į 5 grupes: išankstinių veiksnių, suinteresuotųjų grupių nustatymo, informacijos rinkimo, sprendimų priėmimo ir subalansuotos paramos. Visos šios grupės bei jų ryšiai buvo įtraukti į sistemą, skirtą sėkmingam suinteresuotųjų šalių valdymui statybos projektuose. Šie duomenys padeda paaiškinti, kokiems veiksniams suteikiamas prioritetas ir gali būti naudojami suinteresuotųjų šalių valdymo įgyvendinimui įvertinti bei tobulintinoms sritims nustatyti.

Overview

The claims and statistics of this paper haven’t been checked yet.

Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.3846/1392-3730.2009.15.337-348

Cites

62 of 62 references verified0 citation errors · 0 not checkable

Statistics

Verification

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.

A few free checks a day · papers already verified open instantly · results are public

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

Citations

Cites

Show all 62 references

Research works printed but not linked: 24

  1. 10.1016/S0377-2217(00)00037-0 · doi:10.1016/s0377-2217(00)00037-0
  2. 10.1061/(ASCE)0733-9364(2004)130:2(188) · doi:10.1061/(asce)0733-9364(2004)130:2(188
  3. Cleland D. I., 2002, Project Management: Strategic Design and Implementation
  4. Crow D. A., 2008, The Social Science Journal, 1
  5. 10.1080/02630259908970271 · doi:10.1080/02630259908970271
  6. El‐Sawah H. M., 2006, Journal of Engineering and Applied Science, 53, 195
  7. Hartmann F. T., 2002, Frontiers of Project Management Research, 225
  8. Jergeas G. F., 2000, AACE International Transactions, 12, 1
  9. Kocak N. A., 2003, RUC Option Development Framework and Tools
  10. Landin A., 2000, Impact of Quality Management in the Swedish Construction process
  11. 10.1080/01446190500041537 · doi:10.1080/01446190500041537
  12. 10.1080/01446190801965368 · doi:10.1080/01446190801965368
  13. Newcombe R., 2003, Construction Management and Economics, 22, 762
  14. Nunnally J. O., 1978, Psychometric Theory
  15. Olander S., 2006, External Stakeholder Management
  16. 10.1080/01446190701821810 · doi:10.1080/01446190701821810
  17. Pallant J., 2001, SPSS Survival Manual
  18. 10.1080/01446190802071182 · doi:10.1080/01446190802071182
  19. Schwager H. P., 2004, Organizational strategies to address stakeholder relationships: A customer portal perspective
  20. Schermerhorn J. R., 2003, Organizational Behaviour,
  21. Walker D. H. T., 2008, Stakeholder and The Supply Chain Procurement Systems:A Cross‐industry Project Management Perspective
  22. Wang S. Q., 1999, Journal of Project Finance, 4, 56
  23. 10.1080/096132100368993 · doi:10.1080/096132100368993
  24. Yang J., 2008, International Conference on Construction and Real Estate Management 2008, 109

Cited by

See all 264

Metadata

Authors
Yang, J., Shen, G. Q., Ho, M., Drew, D. S., & Chan, A. P. C.
Venue
JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT
Published
2009-12-31
Volume
15
Issue
4
Pages
337-348
ISSN
  • 1392-3730 (ISSN-L)
  • 1822-3605
OpenAlex
W2027745689
Cited by
264
References
62
FWCI
8.57
Type
journal article
Language
en
Open access
gold

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review

How to cite

Cite CoChat for the checks on this page, and the paper for its own findings.

This page
CoChat. (2026). Citation check: EXPLORING CRITICAL SUCCESS FACTORS FOR STAKEHOLDER MANAGEMENT IN CONSTRUCTION PROJECTS. https://app.cochat.ai/papers/10.3846/1392-3730.2009.15.337-348
The paper
Yang, J., Shen, G. Q., Ho, M., Drew, D. S., & Chan, A. P. C. (2009). EXPLORING CRITICAL SUCCESS FACTORS FOR STAKEHOLDER MANAGEMENT IN CONSTRUCTION PROJECTS. JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT. https://doi.org/10.3846/1392-3730.2009.15.337-348

Data sources

Bibliographic data: Semantic Scholar, OpenAlex, Crossref.

Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).

Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.