CAUSES OF DELAYS IN CONSTRUCTION PROJECTS IN TURKEY
Open accessAbstract
In both developing and industrialized countries, deviation from a planned time schedule is one of the most frequently encountered problems in construction investments. Various factors faced with during construction period prevent systematic flow of work, which causes time-based anomalies as a conclusion. Considering the vital importance of the construction industry on the macro-economic structure of a country, it is inevitable to be aware of considerable effect of the timely completion on the allocated project budget. In this study, causes of time extensions in the Turkish construction industry and levels of their importance were examined together. In total, 34 factors affecting project duration were taken into account. A questionnaire survey, including these factors, was then applied to 71 construction companies in Turkey, and the outcomes were evaluated by means of statistical analyses. According to the results, “design and material changes” was found to be the most predominant factor, followed by “delay of payments” and “cash flow problems”. In terms of importance levels of factor groups, financial factors were found to be the first group, while environmental factors were the least effective group. It should be also noted that managerial causes of time extensions are encountered in developed and developing countries, whereas financial causes are experienced in developing countries only.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Construction Project Management
(2004) · Structural Survey · doi:10.1108/ss.2004.11022bae.009 · Cited by 340
Cited by
Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects
Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2016) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000391 · Cited by 365
Construction delays in privately funded large building projects in Bangladesh
Islam, M. S., & Suhariadi, B. T. (2018) · Asian Journal of Civil Engineering · doi:10.1007/s42107-018-0034-3 · Cited by 44
Metadata
- Authors
- Kazaz, A., Ulubeyli, S., & Tuncbilekli, N. A.
- Venue
- Journal of Civil Engineering and Management
- Published
- 2012-06-29
- Volume
- 18
- Issue
- 3
- Pages
- 426-435
- ISSN
- 1392-3730 (ISSN-L)
- 1822-3605
- OpenAlex
- W2085114513
- Cited by
- 234
- References
- 1
- FWCI
- 5.97
- Type
- journal article
- Language
- en
- Open access
- gold
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
How to cite
Cite CoChat for the checks on this page, and the paper for its own findings.
- This page
- CoChat. (2026). Citation check: CAUSES OF DELAYS IN CONSTRUCTION PROJECTS IN TURKEY. https://app.cochat.ai/papers/10.3846/13923730.2012.698913
- The paper
- Kazaz, A., Ulubeyli, S., & Tuncbilekli, N. A. (2012). CAUSES OF DELAYS IN CONSTRUCTION PROJECTS IN TURKEY. Journal of Civil Engineering and Management. https://doi.org/10.3846/13923730.2012.698913
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.