Significant Factors Causing Cost Overruns in Large Construction Projects in Malaysia
Open accessAbstract
Once a construction projects fails in achieving effective cost performance, it will result to cost overruns. These overruns are caused from several factors which are very important to uncover for improving the cost performance. In Malaysia, not many research works have been carried out on studying cost performance factors. Hence, this study was conducted to identify the significant factors causing cost overrun in large construction projects in Malaysia. Questionnaire for the survey was developed based on 35 common factors of cost overrun identified from literature work. These factors were grouped in 7 categories and validated by interviewing five experienced personnel of construction industry. The feedback of from the survey resulted in receiving 262 sets of completed valid responses against 400 questionnaires distributed amongst contractors, consultants and clients involved in large construction projects. The data from the questionnaire was analyzed statistically. Relative importance index method was used for hierarchal assessment of factors and found that the top 3 most significant factors of cost overrun are fluctuation of prices of material, cash flow and financial difficulties faced by contractors and poor site management and supervision. These factors belong to two categories i.e., contractor's site management and financial management category, thus improvements in these categories are paramount for controlling cost overrun in construction projects.
Overview
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Olawale, Y. A., & Sun, M. (2010) · Construction Management and Economics · doi:10.1080/01446191003674519 · Cited by 478
A quantitative assessment of the cost and time impact of variation orders on construction projects
Oladapo, A. A. (2007) · Journal of Engineering, Design and Technology · doi:10.1108/17260530710746597 · Cited by 93
Cited by
A critical comparison of green building rating systems
Doan, D. T., Ghaffarianhoseini, A., Naismith, N., Zhang, T., Ghaffarianhoseini, A., & Tookey, J. (2017) · Building and Environment · doi:10.1016/j.buildenv.2017.07.007 · Cited by 627
Construction delays in privately funded large building projects in Bangladesh
Islam, M. S., & Suhariadi, B. T. (2018) · Asian Journal of Civil Engineering · doi:10.1007/s42107-018-0034-3 · Cited by 44
Metadata
- Authors
- Rahman, I. A., Hameed Mem, A., & Abd. Karim, A. T.
- Venue
- Journal of Applied Sciences
- Publisher
- Science Alert
- Published
- 2013-01-01
- Volume
- 13
- Issue
- 2
- Pages
- 286-293
- ISSN
- 1812-5654 (ISSN-L)
- OpenAlex
- W1995540032
- Cited by
- 193
- References
- 2
- FWCI
- 14.96
- Type
- journal article
- Language
- en
- Open access
- bronze
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.