Public private partnership projects in Singapore: Factors, critical risks and preferred risk allocation from the perspective of contractors
Open accessAbstract
Abstract Public private partnership (PPP) procurement was introduced into Singapore in 2003, and 10 PPP projects were successfully completed and have been in operation. This study aims to examine the critical success factors as well as the relative importance of positive and negative factors influencing the attractiveness of PPP projects in Singapore, and to identify the critical risk factors and preferred risk allocations for PPP projects in Singapore. The questionnaire survey results indicated that negative factors were more affirmative than the positive factors, and that 23 risk factors had significant criticalities. Eight risks would be preferably allocated to the public sector while 19 risks could be assigned to the private sector. 11 risks were preferred to be shared by both parties and the allocation of four risks depended on project circumstances. The findings of this study provide valuable information for organizations that intend to participate in PPP projects in Singapore.
Overview
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Weber, R. (1990) · doi:10.4135/9781412983488 · Cited by 7,750
Basic content analysis, 2nd ed.
Weber, R. P. (1990) · Cited by 1,611
Research methods for construction
Fellowa, R., & Liu, A. M. M. (2003) · Cited by 1,448
Evaluating the risks of public private partnerships for infrastructure projects
Grimsey, D., & Lewis, M. K. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00040-5 · Cited by 964
The allocation of risk in PPP/PFI construction projects in the UK
Bing, L., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005) · International Journal of Project Management · doi:10.1016/j.ijproman.2004.04.006 · Cited by 901
Understanding the key risks in construction projects in China
Zou, P. X. W., Zhang, G., & Wang, J. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.03.001 · Cited by 859
Critical Success Factors for Public–Private Partnerships in Infrastructure Development
Zhang, X. (2005) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2005)131:1(3 · Cited by 748
An assessment of critical success factors
Zahidy, I. (1984) · Cited by 679
Analysis of factors influencing project cost estimating practice
Akintoye, A. (2000) · Construction Management and Economics · doi:10.1080/014461900370979 · Cited by 608
Risk allocation in the private provision of public infrastructure
Ng, A., & Loosemore, M. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.06.005 · Cited by 505
Cited by
Osei-Kyei, R., & Chan, A. P. C. (2015) · International Journal of Project Management · doi:10.1016/j.ijproman.2015.02.008 · Cited by 803
Metadata
- Authors
- Hwang, B.-G., Zhao, X., & Gay, M. J. S.
- Venue
- International Journal of Project Management
- Publisher
- Elsevier BV
- Published
- 2013-04
- Volume
- 31
- Issue
- 3
- Pages
- 424-433
- ISSN
- 0263-7863 (ISSN-L)
- OpenAlex
- W1997646129
- Cited by
- 410
- References
- 17
- FWCI
- 34.44
- Type
- journal article
- Language
- en
- Open access
- green
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
How to cite
Cite CoChat for the checks on this page, and the paper for its own findings.
- This page
- CoChat. (2026). Citation check: Public private partnership projects in Singapore: Factors, critical risks and preferred risk allocation from the perspective of contractors. https://app.cochat.ai/papers/10.1016/j.ijproman.2012.08.003
- The paper
- Hwang, B.-G., Zhao, X., & Gay, M. J. S. (2013). Public private partnership projects in Singapore: Factors, critical risks and preferred risk allocation from the perspective of contractors. International Journal of Project Management. https://doi.org/10.1016/j.ijproman.2012.08.003
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.