Risk management in small construction projects in Singapore: Status, barriers and impact
Open accessThe DOI matches its Crossref record; 30 of the 30 references it cites were found in a registry or an index.
Abstract
Abstract Risk management (RM) should be implemented in construction projects to assure the achievement of project objectives, regardless of project size. This study aims to investigate RM in small projects in Singapore in terms of status, barriers and impact of RM on project performance. To achieve the objectives, a questionnaire survey was conducted and data were collected from 668 projects submitted by 34 companies. The analysis results indicated a relatively low level of RM implementation in small projects, and that “lack of time”, “lack of budget”, “low profit margin”, and “not economical” were prominent barriers. Also, the results reported the positive correlation between RM implementation and improvement in quality, cost and schedule performance of small projects, respectively. The findings of this study can provide an in-depth understanding of RM in small projects in Singapore and make benefits of RM convincing to the participants of small projects.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
An Introduction to Statistical Methods and Data Analysis
(1994) · Technometrics · doi:10.1080/00401706.1994.10485832 · Cited by 5,346
Likert scales, levels of measurement, and the “laws” of statistics
Norman, G. (2010) · Advances in Health Sciences Education · doi:10.1007/s10459-010-9222-y · Cited by 4,850
A Guide to the project management body of knowledge
(1996) · Choice Reviews Online · doi:10.5860/choice.34-1636 · Cited by 4,339
Resolving the 50‐year debate around using and misusing Likert scales
Carifio, J., & Perla, R. (2008) · Medical Education · doi:10.1111/j.1365-2923.2008.03172.x · Cited by 1,043
Identification and Review of Sensitivity Analysis Methods
Christopher Frey, H., & Patil, S. R. (2002) · Risk Analysis · doi:10.1111/0272-4332.00039 · Cited by 1,036
Risk Management and Construction
Flanagan, R. (1993) · Medical Entomology and Zoology · Cited by 910
Risk analysis and management in construction
Akintoye, A. S., & MacLeod, M. J. (1997) · International Journal of Project Management · doi:10.1016/s0263-7863(96)00035-x · Cited by 755
Handbook of Evaluation Research
Ross, L., & Cronbach, L. J. (1976) · Educational Researcher · doi:10.2307/1174773 · Cited by 698
Project Risk Management: Processes, Techniques and Insights
Smith, J. U. M. (1998) · Journal of the Operational Research Society · doi:10.1057/palgrave.jors.2600022 · Cited by 555
Use and benefits of tools for project risk management
Raz, T., & Michael, E. (2001) · International Journal of Project Management · doi:10.1016/s0263-7863(99)00036-8 · Cited by 402
Cited by
AMEYAW, E. E., HU, Y., SHAN, M., CHAN, A. P. C., & LE, Y. (2016) · JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT · doi:10.3846/13923730.2014.945953 · Cited by 307
Impact of integration management on construction project management performance
Demirkesen, S., & Ozorhon, B. (2017) · International Journal of Project Management · doi:10.1016/j.ijproman.2017.09.008 · Cited by 259
RISK MANAGEMENT IN CONSTRUCTION PROJECTS
IQBAL, S., CHOUDHRY, R. M., HOLSCHEMACHER, K., ALI, A., & TAMOŠAITIENĖ, J. (2015) · Technological and Economic Development of Economy · doi:10.3846/20294913.2014.994582 · Cited by 236
Xia, N., Zou, P. X. W., Griffin, M. A., Wang, X., & Zhong, R. (2018) · International Journal of Project Management · doi:10.1016/j.ijproman.2018.03.006 · Cited by 229
“Following this definition, the purpose of project RM is to increase the likelihood and impact of positive events, and reduce those of negative events in the project (Arashpour et al., 2017; Hwang et al., 2014).”
Method
Metadata
- Authors
- Hwang, B.-G., Zhao, X., & Toh, L. P.
- Venue
- International Journal of Project Management
- Publisher
- Elsevier BV
- Published
- 2014-01
- Volume
- 32
- Issue
- 1
- Pages
- 116-124
- ISSN
- 0263-7863 (ISSN-L)
- OpenAlex
- W2050113962
- Cited by
- 234
- References
- 30
- FWCI
- 15.87
- Type
- journal article
- Language
- en
- Open access
- green
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.