Construction Project Cost Escalation Factors

Shane, Jennifer S., Molenaar, Keith R., Anderson, Stuart, Schexnayder, Cliff · 2009 · Journal of Management in Engineering
DOI 10.1061/(asce)0742-597x(2009)25:4(221

Abstract

Construction projects, private and public alike, have a long history of cost escalation. Transportation projects, which typically have long lead times between planning and construction, are historically underestimated, as shown through a review of the cost growth experienced with the Holland Tunnel. Approximately 50% of the active large transportation projects in the United States have overrun their initial budgets. A large number of studies and research projects have identified individual factors that lead to increased project cost. Although the factors identified can influence privately funded projects the effects are particularly detrimental to publicly funded projects. The public funds available for a pool of projects are limited and there is a backlog of critical infrastructure needs. Therefore, if any project exceeds its budget other projects are dropped from the program or the scope is reduced to provide the funds necessary to cover the cost growth. Such actions exacerbate the deterioration of a state’s transportation infrastructure. This study is an anthology and categorization of individual cost increase factors that were identified through an in-depth literature review. This categorization of 18 primary factors which impact the cost of all types of construction projects was verified by interviews with over 20 state highway agencies. These factors represent documented causes behind cost escalation problems. Engineers who address these escalation factors when assessing future project cost and who seek to mitigate the influence of these factors can improve the accuracy of their cost estimates and program budgets.

Overview

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.1061/(asce)0742-597x(2009)25:4(221)

Cites

Statistics

Verification

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

Citations

Cites

No references could be resolved yet.

Research works printed but not linked: 27

  1. 10.1061/(ASCE)0742-597X(1998)14:1(67) · doi:10.1061/(asce)0742-597x(1998)14:1(67
  2. Arditi D., 1985, Journal of Project Management, 218
  3. 2003, The Big Dig: Key facts about cost, scope, schedule, and management
  4. Board on Infrastructure and the Constructed Environment, 2003, Completing the “Big Dig”: Managing the final stages of Boston's central artery/tunnel project
  5. 10.1177/002085239806400306 · DOI
  6. Callahan J. T., 1998, Managing transit construction contract claims, 1
  7. Capka J. R., 2004, Megaprojects—They are a different breed, Public Roads, 68
  8. 10.1061/(ASCE)0742-597X(2002)18:1(29) · doi:10.1061/(asce)0742-597x(2002)18:1(29
  9. Condon E., 2004, 2004 Association for the Advancement of Cost Engineering International Transactions
  10. Daniels B., 1998, A legacy of conflict: Utah’s growth and the legacy highway, Hinckly J. Polit, 1, 51
  11. “Megaprojects need more study up front to avoid cost overruns.” (2002). Enginering News Record McGraw-Hill.
  12. 10.1080/01944360208976273 · DOI · Paper page
  13. Harbuck R. H., 2004, 2004 Association for the Advancement of Cost Engineering International Transactions
  14. Hudachko T., 2004, Shared solutions
  15. Hufschmidt M. M., 1970, The analysis of public output
  16. Mackie P., 1998, Transport policy 5, 1
  17. Merrow E. W., 1988, Understanding the outcomes of mega projects: A quantitative analysis of very large civilian projects
  18. Noor I., 2004, 2004 Association for the Advancement of Cost Engineering International Transactions
  19. Parsons Brinckerhoff Quade & Douglas, Inc., 2002, Final draft: Design-build practice report
  20. Pearl R., 1994, 1994 Association for the Advancement of Civil Engineering International Transactions
  21. 10.1080/01944369208975791 · DOI · Paper page
  22. Ripley P. W., 2004, 2004 Association for the Advancement of Civil Engineering International Transactions
  23. Sawyer J. E., 1952, Entrepreneurial error and economic growth, Explorations in Entrepreneurial History, 4, 199
  24. 10.1061/(ASCE)0733-9364(1994)120:4(785) · doi:10.1061/(asce)0733-9364(1994)120:4(785
  25. Summary of independent review committee findings regarding the Woodrow Wilson Bridge superstructure contract. (2002). March 1.
  26. Weiss L. L., 2000, Design/build—Lessons learned to date
  27. Woodrow Wilson Bridge project bridge superstructure contract (BR-3): Review of the engineer’s estimate vs. the single bid . (2002). February 28.

Cited by

See all 220

Metadata

Authors
Shane, J. S., Molenaar, K. R., Anderson, S., & Schexnayder, C.
Venue
Journal of Management in Engineering
Published
2009-10
Volume
25
Issue
4
Pages
221-229
ISSN
  • 0742-597X (ISSN-L)
  • 1943-5479
DOI
10.1061/(asce)0742-597x(2009)25:4(221
OpenAlex
W1971045677
Cited by
220
References
0
FWCI
8.12
Type
journal article
Language
en
Open access
closed

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review

How to cite

Cite CoChat for the checks on this page, and the paper for its own findings.

This page
CoChat. (2026). Citation check: Construction Project Cost Escalation Factors. https://app.cochat.ai/papers/10.1061/(asce)0742-597x(2009)25:4(221
The paper
Shane, J. S., Molenaar, K. R., Anderson, S., & Schexnayder, C. (2009). Construction Project Cost Escalation Factors. Journal of Management in Engineering. https://doi.org/10.1061/(asce)0742-597x(2009)25%3A4(221

Data sources

Bibliographic data: Semantic Scholar, OpenAlex, Crossref.

Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).

Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.