Abstract
Construction projects, private and public alike, have a long history of cost escalation. Transportation projects, which typically have long lead times between planning and construction, are historically underestimated, as shown through a review of the cost growth experienced with the Holland Tunnel. Approximately 50% of the active large transportation projects in the United States have overrun their initial budgets. A large number of studies and research projects have identified individual factors that lead to increased project cost. Although the factors identified can influence privately funded projects the effects are particularly detrimental to publicly funded projects. The public funds available for a pool of projects are limited and there is a backlog of critical infrastructure needs. Therefore, if any project exceeds its budget other projects are dropped from the program or the scope is reduced to provide the funds necessary to cover the cost growth. Such actions exacerbate the deterioration of a state’s transportation infrastructure. This study is an anthology and categorization of individual cost increase factors that were identified through an in-depth literature review. This categorization of 18 primary factors which impact the cost of all types of construction projects was verified by interviews with over 20 state highway agencies. These factors represent documented causes behind cost escalation problems. Engineers who address these escalation factors when assessing future project cost and who seek to mitigate the influence of these factors can improve the accuracy of their cost estimates and program budgets.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Baucus, M. S. (1982) · The Mathematics Enthusiast · Cited by 2,799
Underestimating Costs in Public Works Projects:Error or Lie?
Flyvbjerg, B., Holm, M. S., & Buhl, S. (2002) · Journal of the American Planning Association · doi:10.1080/01944360208976273 · Cited by 1,046
Construction Claims and Disputes: Causes and Cost/Time Overruns
Semple, C., Hartman, F. T., & Jergeas, G. F. (1994) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(1994)120:4(785 · Cited by 374
A Desire Named Streetcar Fantasy and Fact in Rail Transit Planning
Pickrell, D. H. (1992) · Journal of the American Planning Association · doi:10.1080/01944369208975791 · Cited by 321
Factors Affecting Contractors' Risk of Cost Overburden
Akinci, B., & Fischer, M. A. (1998) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(1998)14:1(67 · Cited by 155
Reasons for Cost and Schedule Increase for Engineering Design Projects
Chang, A. S.-T. (2002) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(2002)18:1(29 · Cited by 133
Big decisions, big risks: improving accountability in mega projects
Bruzelius, N., Flyvbjerg, B., & Rothengatter, W. (1998) · International Review of Administrative Sciences · doi:10.1177/002085239806400306 · Cited by 132
Cost overruns in public projects
Arditi, D., Akan, G. T., & Gurdamar, S. (1985) · International Journal of Project Management · doi:10.1016/0263-7863(85)90053-5 · Cited by 121
MEGAPROJECTS--THEY ARE A DIFFERENT BREED
Capka, J. R. (2004) · Public roads · Cited by 69
Research works printed but not linked: 20
- Arditi D., 1985, Journal of Project Management, 218
- 2003, The Big Dig: Key facts about cost, scope, schedule, and management
- Board on Infrastructure and the Constructed Environment, 2003, Completing the “Big Dig”: Managing the final stages of Boston's central artery/tunnel project
- Callahan J. T., 1998, Managing transit construction contract claims, 1
- Condon E., 2004, 2004 Association for the Advancement of Cost Engineering International Transactions
- Daniels B., 1998, A legacy of conflict: Utah’s growth and the legacy highway, Hinckly J. Polit, 1, 51
- “Megaprojects need more study up front to avoid cost overruns.” (2002). Enginering News Record McGraw-Hill.
- Harbuck R. H., 2004, 2004 Association for the Advancement of Cost Engineering International Transactions
- Hudachko T., 2004, Shared solutions
- Hufschmidt M. M., 1970, The analysis of public output
- Mackie P., 1998, Transport policy 5, 1
- Merrow E. W., 1988, Understanding the outcomes of mega projects: A quantitative analysis of very large civilian projects
- Noor I., 2004, 2004 Association for the Advancement of Cost Engineering International Transactions
- Parsons Brinckerhoff Quade & Douglas, Inc., 2002, Final draft: Design-build practice report
- Pearl R., 1994, 1994 Association for the Advancement of Civil Engineering International Transactions
- Ripley P. W., 2004, 2004 Association for the Advancement of Civil Engineering International Transactions
- Sawyer J. E., 1952, Entrepreneurial error and economic growth, Explorations in Entrepreneurial History, 4, 199
- Summary of independent review committee findings regarding the Woodrow Wilson Bridge superstructure contract. (2002). March 1.
- Weiss L. L., 2000, Design/build—Lessons learned to date
- Woodrow Wilson Bridge project bridge superstructure contract (BR-3): Review of the engineer’s estimate vs. the single bid . (2002). February 28.
Cited by
Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects
Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2016) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000391 · Cited by 365
Risk paths in international construction projects: Case study from Chinese contractors
Liu, J., Zhao, X., & Yan, P. (2016) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001116 · Cited by 203
Giezen, M. (2012) · International Journal of Project Management · doi:10.1016/j.ijproman.2012.01.010 · Cited by 188
Predicting construction cost overruns using text mining, numerical data and ensemble classifiers
Williams, T. P., & Gong, J. (2014) · Automation in Construction · doi:10.1016/j.autcon.2014.02.014 · Cited by 164
Ashtari, M. A., Ansari, R., Hassannayebi, E., & Jeong, J. (2022) · Buildings · doi:10.3390/buildings12101660 · Cited by 65
Ghazal, M. M., & Hammad, A. (2022) · International Journal of Construction Management · doi:10.1080/15623599.2020.1738205 · Cited by 52
Metadata
- Authors
- Shane, J. S., Molenaar, K. R., Anderson, S., & Schexnayder, C.
- Venue
- Journal of Management in Engineering
- Published
- 2009-10
- Volume
- 25
- Issue
- 4
- Pages
- 221-229
- ISSN
- 0742-597X (ISSN-L)
- 1943-5479
- DOI
- 10.1061/(asce)0742-597x(2009)25:4(221
- OpenAlex
- W1971045677
- Cited by
- 220
- References
- 9
- FWCI
- 8.12
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.