Causes, Effects, Benefits, and Remedies of Change Orders on Public Construction Projects in Oman
The DOI matches its Crossref record; 10 of the 10 references it cites were found in a registry or an index.
Abstract
Change orders are usually issued to cover variations in scope of work, material quantities, design errors, and unit rate changes. This paper discusses variations in public construction projects in Oman by investigating causes of variations, studying their effects on the project, identifying the beneficial parties, and suggesting remedies to alleviate related problems. Tasks included an analysis of four actual case studies and conducting a field survey via a questionnaire. It was determined that the client’s additional works and modifications to design were the most important factors causing change orders, followed by the nonavailability of construction manuals and procedures. The most important effects of change orders on the project were found to be the schedule delays, disputes, and cost overruns. The contractor was found to be the party most benefiting from the change orders followed by the consultant and then the client. A set of remedial actions were suggested and respondents viewed that the revision of registration of consulting offices would be the most important action followed by establishing standard documents for design procedures and building a national database about soil conditions and services.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Causes of delay in large construction projects
Assaf, S. A., & Al-Hejji, S. (2006) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.11.010 · Cited by 1,705
Causes and effects of delays in Malaysian construction industry
Sambasivan, M., & Soon, Y. W. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.11.007 · Cited by 1,422
A comparative study of causes of time overruns in Hong Kong construction projects
Chan, D. W., & Kumaraswamy, M. M. (1997) · International Journal of Project Management · doi:10.1016/s0263-7863(96)00039-7 · Cited by 831
Factors influencing construction time and cost overruns on high-rise projects in Indonesia
Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997) · Construction Management and Economics · doi:10.1080/014461997373132 · Cited by 698
Construction delay: a quantitative analysis
Al-Momani, A. H. (2000) · International Journal of Project Management · doi:10.1016/s0263-7863(98)00060-x · Cited by 553
Cost Overrun and Cause in Korean Social Overhead Capital Projects: Roads, Rails, Airports, and Ports
Lee, J.-K. (2008) · Journal of Urban Planning and Development · doi:10.1061/(asce)0733-9488(2008)134:2(59 · Cited by 141
Quantitative Definition of Projects Impacted by Change Orders
Hanna, A. S., Camlic, R., Peterson, P. A., & Nordheim, E. V. (2002) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2002)128:1(57 · Cited by 131
Statistical analysis of causes for design change in highway construction on Taiwan
Wu, C.-H., Hsieh, T.-Y., & Cheng, W. (2005) · International Journal of Project Management · doi:10.1016/j.ijproman.2004.07.010 · Cited by 105
Hybrid ANN-CBR model for disputed change orders in construction projects
Chen, J., & Hsu, S. (2007) · Automation in Construction · doi:10.1016/j.autcon.2007.03.003 · Cited by 94
Methodology for Determining Price Variation in Project Execution
Akpan, E. O. P., & Igwe, O. (2001) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2001)127:5(367 · Cited by 35
Cited by
Du, J., Zou, Z., Shi, Y., & Zhao, D. (2018) · Automation in Construction · doi:10.1016/j.autcon.2017.10.009 · Cited by 324
Eybpoosh, M., Dikmen, I., & Talat Birgonul, M. (2011) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000382 · Cited by 217
Risk paths in international construction projects: Case study from Chinese contractors
Liu, J., Zhao, X., & Yan, P. (2016) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001116 · Cited by 203
Metadata
- Authors
- Alnuaimi, A. S., Taha, R. A., Al Mohsin, M., & Al-Harthi, A. S.
- Venue
- Journal of Construction Engineering and Management
- Published
- 2010-05
- Volume
- 136
- Issue
- 5
- Pages
- 615-622
- ISSN
- 0733-9364 (ISSN-L)
- 1943-7862
- OpenAlex
- W2166866184
- Cited by
- 233
- References
- 10
- FWCI
- 4.51
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.