Evaluation of Risk Factors Leading to Cost Overrun in Delivery of Highway Construction Projects
Open accessThe DOI matches its Crossref record; 20 of the 20 references it cites were found in a registry or an index.
Abstract
Accurate owner budget estimates are critical to the initial decision-to-build process for highway construction projects. However, transportation projects have historically experienced significant construction cost overruns from the time the decision to build has been taken by the owner. This paper addresses the problem of why highway projects overrun their predicted costs. It identifies the owner risk variables that contribute to significant cost overrun and then uses factor analysis, expert elicitation, and the nominal group technique to establish groups of importance ranked owner risks. Stepwise multivariate regression analysis is also used to investigate any correlation of the percentage of cost overrun with risks, together with attributes such as highway project type, indexed cost, geographic location, and project delivery method. The research results indicate a correlation between the reciprocal of project budget size and percentage cost overrun. This can be useful for owners in determining more realistic decision-to-build highway budget estimates by taking into account the economies of scale associated with larger projects.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
The Varimax Criterion for Analytic Rotation in Factor Analysis
Kaiser, H. F. (1958) · Psychometrika · doi:10.1007/bf02289233 · Cited by 7,580 · cited 1×
“This was much less than 0.6 that was sought in the literature (Kaiser 1958; Hutcheson and Sofroniou 1999) and threw initial doubt on the adequacy of the planned factor analysis technique in overcoming multicollinearity in the data.”
MethodInfluentialRelation of sample size to the stability of component patterns.
Guadagnoli, E., & Velicer, W. F. (1988) · Psychological Bulletin · doi:10.1037/0033-2909.103.2.265 · Cited by 2,880 · cited 1×
“This gives an acceptable ratio of 8.3 (Guadagnoli and Velicer 1988).”
BackgroundInfluentialGroup Techniques for Program Planning: A Guide to Nominal Group and Delphi Processes
(1976) · The Journal of Applied Behavioral Science · doi:10.1177/002188637601200414 · Cited by 2,813 · cited 1×
“The NGT is a consensus planning tool that helps prioritize issues (Delbecq et al. 1986).”
BackgroundMegaprojects and Risk: An Anatomy of Ambition
Flyvbjerg, B., Bruzelius, N., & Rothengatter, W. (2003) · Cambridge University Press eBooks · doi:10.1017/cbo9781107050891 · Cited by 2,415
The Multivariate Social Scientist
Hutcheson, G. (1999) · SAGE Publications Ltd eBooks · doi:10.4135/9780857028075 · Cited by 1,728
The Multivariate Social Scientist: Introductory Statistics Using Generalized Linear Models
Hutcheson, G. (1999) · Cited by 1,127
Underestimating Costs in Public Works Projects:Error or Lie?
Flyvbjerg, B., Holm, M. S., & Buhl, S. (2002) · Journal of the American Planning Association · doi:10.1080/01944360208976273 · Cited by 1,046 · cited 1×
“When this occurs, highway organizations lose creditability and time is often taken defending deviation from the published program (Flyvbjerg et al. 2002).”
BackgroundSystematic Risk Management Approach for Construction Projects
Al‐Bahar, J. F., & Crandall, K. C. (1990) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(1990)116:3(533 · Cited by 414 · cited 1×
“The interrogation of in-house historical databases is probably the best source of data to assess risk occurrences or consequences of risk events and in many cases these databases are inadequate or disjointed, unavailable or supplemented with personal information bias (Al-Bahar and Crandall 1990).”
BackgroundNeural Network Model for Parametric Cost Estimation of Highway Projects
Hegazy, T., & Ayed, A. (1998) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(1998)124:3(210 · Cited by 388 · cited 1×
“In a study conducted in Newfoundland, Hegazy and Ayed (1998) found that season, location, type of project, contract duration and contract size had a significant impact on individual contract costs.”
BackgroundGustafson, D. H., Shukla, R. K., Delbecq, A., & Walster, G. W. (1973) · Organizational Behavior and Human Performance · doi:10.1016/0030-5073(73)90052-4 · Cited by 376 · cited 1×
“NGT provides a constructive, problem-solving approach that permits equal participation by all the group members, and avoids the disproportionate influence by vocal individuals who are often present in group processes (Gustafson et al. 1973).”
Background
Cited by
Risk Assessment and Allocation in Highway Construction Projects in the UAE
El-Sayegh, S. M., & Mansour, M. H. (2015) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000365 · Cited by 236
From Construction Megaproject Management to Complex Project Management: Bibliographic Analysis
Hu, Y., Chan, A. P. C., Le, Y., & Jin, R.-Z. (2015) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000254 · Cited by 221
“…Yasin et al. 2009), 396 Delphi survey (Dzeng and Wen 2005; Sun et al. 2008), 397 Correlation analysis (Helen et al. 2010), 398 Regression analysis (Creedy et al. 2010), 399 Fuzzy analysis (Zammori et al. 2009; Dzeng and Wem, 2005), 400 Particle swarm optimization (Yang 2007), 401 Markov…”
BackgroundKwon, H., & Kang, C. W. (2019) · Project Management Journal · doi:10.1177/8756972818810963 · Cited by 50
“Researchers have indicated that these significant cost overruns are caused by uncertainties arising from risk events and inaccurate budget estimates (Bannerman, 2008; Creedy et al., 2010; Elkjaer, 2000; Hullet, 2012; Lai, Wang, & Wang, 2008).”
Background
Metadata
- Authors
- Creedy, G. D., Skitmore, M., & Wong, J. K. W.
- Venue
- Journal of Construction Engineering and Management
- Published
- 2010-05
- Volume
- 136
- Issue
- 5
- Pages
- 528-537
- ISSN
- 0733-9364 (ISSN-L)
- 1943-7862
- OpenAlex
- W1978471563
- Cited by
- 242
- References
- 20
- FWCI
- 8.28
- Type
- journal article
- Language
- en
- Open access
- bronze
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.