An analytical hierarchy process based procurement selection method
The DOI matches its Crossref record; 10 of the 10 references it cites were found in a registry or an index.
Abstract
Procurement selection continues to be topical, and several advanced studies have been reported. One of the key concerns of procurement selection is how to enhance objectivity. A selection method developed using multi-attribute utility technology (MAUT) and the analytical hierarchy process (AHP) is proposed. With the input of industrial experts, critical procurement selection criteria and procurement strategies commonly used in Hong Kong were identified. Against these criteria, utility factors corresponding to various procurement strategies were then assigned by the experts to create a utility factor table. To cater for individual project characteristics, the relative importance weightings of the selection criteria were assessed using the analytical hierarchy process. Final selection was then based on the highest utility value derived from the procurement strategies, taking into account the relative importance of the selection criteria. The use of the model is illustrated with actual data.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Moutinho, L., & Curry, B. (1994) · ENLIGHTEN (Jurnal Bimbingan dan Konseling Islam) · Cited by 1,813
Saaty, T. L. (1985) · IEEE Transactions on Systems Man and Cybernetics · doi:10.1109/tsmc.1985.6313384 · Cited by 1,344
Prediction, Projection and Forecasting
Saaty, T. L., & Vargas, L. G. (1991) · Springer eBooks · doi:10.1007/978-94-015-7952-0 · Cited by 500
Loudenback, L. J. (1984) · Industrial Marketing Management · doi:10.1016/0019-8501(84)90013-0 · Cited by 475
Final contractor selection using the analytical hierarchy process
Fong, P. S. W., & Choi, S. K.-Y. (2000) · Construction Management and Economics · doi:10.1080/014461900407356 · Cited by 335 · cited 2×
“, 1998); design and build project assessments (Alhazmi and McCaffer, 2000) and contractor selection (Fong and Choi, 2000).”
BackgroundMethodSelecting a suitable procurement method for a building project
Love, P. E. D., Skitmore, M., & Earl, G. (1998) · Construction Management and Economics · doi:10.1080/014461998372501 · Cited by 281
Shen, Q., Lo, K. K., & Wang, Q. (1998) · Construction Management and Economics · doi:10.1080/014461998371980 · Cited by 118 · cited 1×
“In construction, successful use of the technique has been reported in: prioritizing maintenance schedules (Shen et al., 1998); design and build project assessments (Alhazmi and McCaffer, 2000) and contractor selection (Fong and Choi, 2000).”
MethodA multi-attribute utility model for dispute resolution strategy selection
Cheung, S. O., & Suen, H. C. H. (2002) · Construction Management and Economics · doi:10.1080/01446190210157568 · Cited by 114
Self-citationCONSTRUCTION MANAGEMENT IN PRACTICE
(2022) · Proceedings of the International Conferences on: Educational Technologies 2022 (ICEduTech 2022), Sustainability, Technology and Education 2022 (STE 2022), Internet Technologies & Society 2022 (ITS 2022) and Applied Management Advances in the 21st Century 2022 (AMA21 2022) · doi:10.33965/ice2022_202210l016 · Cited by 61
(1980) · Andalas University Repository (Andalas University)
Cited by
Fuzzy MCDM approach for planning and design tenders selection in public office buildings
Hsieh, T.-Y., Lu, S.-T., & Tzeng, G.-H. (2004) · International Journal of Project Management · doi:10.1016/j.ijproman.2004.01.002 · Cited by 694
Wong, J. K. W., & Li, H. (2008) · Building and Environment · doi:10.1016/j.buildenv.2006.11.019 · Cited by 432
Eriksson, P. E., & Westerberg, M. (2011) · International Journal of Project Management · doi:10.1016/j.ijproman.2010.01.003 · Cited by 363
Huang, Y., & Bian, L. (2009) · Expert Systems with Applications · doi:10.1016/j.eswa.2007.10.019 · Cited by 216
AHP-Based Equipment Selection Model for Construction Projects
Shapira, A., & Goldenberg, M. (2005) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2005)131:12(1263 · Cited by 184
A case-based reasoning cost estimating model using experience by analytic hierarchy process
An, S.-H., Kim, G.-H., & Kang, K.-I. (2007) · Building and Environment · doi:10.1016/j.buildenv.2006.06.007 · Cited by 174
Improved AHP Method and Its Application in Risk Identification
Li, F., Phoon, K. K., Du, X., & Zhang, M. (2013) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000605 · Cited by 168
“…2001; Chan et al. 2004), contractor selection (Fong and Choi 2000; Kahraman et al. 2003; Hsieh et al. 2004; Cheng and Li 2004), procurement (Cheung et al. 2001), facility location determination (Yang and Lee 1997), construction safety management (Teo and Ling 2006), project and proposal…”
BackgroundCircular public procurement through integrated contracts in the infrastructure sector
Lingegård, S., Havenvid, M. I., & Eriksson, P.-E. (2021) · Sustainability · doi:10.3390/su132111983 · Cited by 20
Metadata
- Authors
- Cheung, S.-O., Lam, T.-I., Leung, M.-Y., & Wan, Y.-W.
- Venue
- Construction Management and Economics
- Publisher
- Informa UK Limited
- Published
- 2001-07
- Volume
- 19
- Issue
- 4
- Pages
- 427-437
- ISSN
- 0144-6193 (ISSN-L)
- 1466-433X
- OpenAlex
- W2104690553
- Cited by
- 166
- References
- 10
- FWCI
- 4.98
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.