Circular Public Procurement through Integrated Contracts in the Infrastructure Sector
Abstract
Public clients’ procurement strategies are central in facilitating innovation towards sustainability. In the infrastructure sector, the three main project activities—design, production, and maintenance—are traditionally not procured in an integrated way, which results in sub-optimizations and a lack of life cycle perspective. As project actors are accustomed to traditional, non-integrated forms of contract, implementing integrated contracts imposes fundamental changes to the interdependencies among actors, resources, and activities. This study analyzes the interfaces among key project actors and the related interdependencies across design, production, and maintenance in Design–Build–Maintain contracts, and initiates a discussion on how to manage these interdependencies when implementing integrated contracts. This study of circular public procurement (CPP) focused on three infrastructure projects using integrated contracting and applied the industrial network approach (INA) to analyze interdependencies in how they may influence innovation and sustainable development. The study found significant obstacles to clients obtaining the benefits of integrated contracting and concludes that understanding interdependencies is necessary to implement integrated contracts successfully. The study contributes to the construction management literature by adapting the INA to contracting, and to the CPP literature by providing empirical evidence of sustainability and circularity in infrastructure projects.
Overview
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Claims other papers make about this one
Each is checked against this paper’s own text: does it say what the citing paper says it does?
Interdependencies among actors need to be understood to benefit from circularity.
“the interdependencies among actors need to be understood to benefit from circularity (Lingegård et al., 2021)”
From Rethinking the project life cycle – how circularity challenges processes, roles and governance (2025) · cites this paper as Lingegård et al., 2021
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Sustainable procurement in the public sector: an international comparative study
Brammer, S., & Walker, H. (2011) · International Journal of Operations & Production Management · doi:10.1108/01443571111119551 · Cited by 731
Review of green and sustainable public procurement: Towards circular public procurement
Sönnichsen, S. D., & Clement, J. (2020) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2019.118901 · Cited by 322 · cited 25×
“Collaboration between actors is necessary to identify and explore CPP [10]—especially since lack of knowledge and awareness, as well as resistance to change are key obstacles to the implementation of CPP [3,5,50,51,53].”
BackgroundMethodInfluentialExploiting the potential of public procurement: opportunities for circular economy
Alhola, K., Ryding, S. O., Salmenperä, H., & Busch, N. J. (2019) · Journal of Industrial Ecology · doi:10.1111/jiec.12770 · Cited by 284
Flagged first, then by citations
Research works printed but not linked: 60
- Hafsa, F., Darnall, N., and Bretschneider, S. (2021). Estimating the true size of public procurement to assess sustainability impact. Sustainability, 13. · DOI
- Lăzăroiu, G., Ionescu, L., Uță, C., Hurloiu, I., Andronie, M., and Dijmărescu, I. (2020). Environmentally responsible behavior and sustainability policy adoption in green public procurement. Sustainability, 12. · DOI
- Lindahl, 2015, Integrated product service offerings for rail infrastructure—Benefits and challenges regarding knowledge transfer and cultural change in a Swedish case, J. Clean. Prod., 98, 166, 10.1016/j.jclepro.2014.06.039 · DOI
- Christensen, 2021, Towards a circular economy in cities: Exploring local modes of governance in the transition towards a circular economy in construction and textile recycling, J. Clean. Prod., 305, 127058, 10.1016/j.jclepro.2021.127058 · DOI
- Lenferink, 2013, Towards sustainable infrastructure development through integrated contracts: Experiences with inclusiveness in Dutch infrastructure projects, Int. J. Proj. Manag., 31, 615, 10.1016/j.ijproman.2012.09.014 · DOI
- Fuentes-Bargues, J.L., Ferrer-Gisbert, P.S., González-Cruz, M.C., and Bastante-Ceca, M.J. (2019). Green public procurement at a regional level. Case study: The Valencia region of Spain. Int. J. Environ. Res. Public Health, 16. · DOI
- Kadefors, 2021, Designing and implementing procurement requirements for carbon reduction in infrastructure construction—International overview and experiences, J. Environ. Plan. Manag., 64, 611, 10.1080/09640568.2020.1778453 · DOI
- Džupka, P., Kubák, M., and Nemec, P. (2020). Sustainable public procurement in central European countries. Can it also bring savings?. Sustainability, 12. · DOI
- Testa, 2012, What factors influence the uptake of GPP (green public procurement) practices? New evidence from an Italian survey, Ecol. Econ., 82, 88, 10.1016/j.ecolecon.2012.07.011 · DOI · Paper page
- Vluggen, R., Gelderman, C.J., Semeijn, J., and van Pelt, M. (2019). Sustainable public procurement—External forces and accountability. Sustainability, 11. · DOI
- Igarashi, 2017, Analyzing buyer behavior when selecting green criteria in public procurement, J. Public Procure., 17, 141, 10.1108/JOPP-17-02-2017-B001 · DOI · Paper page
- Park, 2017, Design-bid-build (DBB) vs. Design-build (DB) in the U.S. public transportation projects: The choice and consequences, Int. J. Proj. Manag., 35, 280, 10.1016/j.ijproman.2016.10.013 · DOI
- Ibbs, 2003, Project delivery systems and project change: Quantitative analysis, J. Constr. Eng. Manag., 129, 382, 10.1061/(ASCE)0733-9364(2003)129:4(382) · DOI
- Chen, 2016, Time and cost performance of design–build projects, J. Constr. Eng. Manag., 142, 04015074, 10.1061/(ASCE)CO.1943-7862.0001056 · DOI
- Shrestha, 2012, Performance comparison of large design-build and design-bid-build highway projects, J. Constr. Eng. Manag., 138, 1, 10.1061/(ASCE)CO.1943-7862.0000390 · DOI
- Messner, 2006, Comparing procurement methods for design-build projects, J. Constr. Eng. Manag., 132, 230, 10.1061/(ASCE)0733-9364(2006)132:3(230) · DOI
- Hale, 2009, Empirical comparison of design/build and design/bid/build project delivery methods, J. Constr. Eng. Manag., 135, 579, 10.1061/(ASCE)CO.1943-7862.0000017 · DOI
- Minchin, 2013, Comparison of cost and time performance of design-build and design-bid-build delivery systems in Florida, J. Constr. Eng. Manag., 139, 04013007, 10.1061/(ASCE)CO.1943-7862.0000746 · DOI
- Ibrahim, 2020, Quantitative comparison of project performance between project delivery systems, J. Manag. Eng., 36, 04020082, 10.1061/(ASCE)ME.1943-5479.0000837 · DOI
- Okere, 2018, Comparison of DB to DBB on highway projects in Washington State, USA, J. Constr. Supply Chain Manag., 8, 73
- Songer, 1996, Selecting design-build: Public and private sector owner attitudes, J. Manag. Eng., 12, 47, 10.1061/(ASCE)0742-597X(1996)12:6(47) · DOI
- Demetracopoulou, 2020, Lessons learned from selection of project delivery methods in highway projects: The Texas experience, J. Leg. Aff. Disput. Resolut. Eng. Constr., 12, 04519040, 10.1061/(ASCE)LA.1943-4170.0000340 · DOI
- Cheung, 2001, An analytical hierarchy process based procurement selection method, Constr. Manag. Econ., 19, 427, 10.1080/014461901300132401 · DOI
- Ruparathna, 2015, Sustainable procurement in the Canadian construction industry: Current practices, drivers and opportunities, J. Clean. Prod., 109, 305, 10.1016/j.jclepro.2015.07.007 · DOI · Paper page
- Tawiah, 2008, Assessing infrastructure project innovation potential as a function of procurement mode, J. Manag. Eng., 24, 173, 10.1061/(ASCE)0742-597X(2008)24:3(173) · DOI
- Eriksson, 2017, Procurement strategies for enhancing exploration and exploitation in construction projects, J. Financ. Manag. Prop. Constr., 22, 211, 10.1108/JFMPC-05-2016-0018 · DOI
- Lind, 2010, Service-led construction: Is it really the future?, Constr. Manag. Econ., 28, 1145, 10.1080/01446193.2010.529452 · DOI
- Thompson, 2004, The design of functional (total care) products, J. Eng. Des., 15, 515, 10.1080/09544820412331271176 · DOI
- Mont, 2002, Clarifying the concept of product–service system, J. Clean. Prod., 10, 237, 10.1016/S0959-6526(01)00039-7 · DOI · Paper page
- Håkansson, H., and Waluszewski, A. (2007). Introducing “old” knowledge in an established user context: How to use wood in the construction industry. Knowledge and Innovation in Business and Industry: The Importance of Using Others, Routledge. · DOI
- Havenvid, 2015, Antecedents of project partnering in the construction industry—The impact of relationship history, Ind. Mark. Manag., 50, 4, 10.1016/j.indmarman.2015.07.018 · DOI
- Havenvid, 2016, Renewal in construction projects: Tracing effects of client requirements, Constr. Manag. Econ., 34, 790, 10.1080/01446193.2016.1208364 · DOI
- Dubois, 2002, Systematic combining: An abductive approach to case research, J. Bus. Res., 55, 553, 10.1016/S0148-2963(00)00195-8 · DOI · Paper page
- Håkansson, H., Ford, D., Gadde, L.-E., Snehota, I., and Waluszewski, A. (2009). Business in Networks, John Wiley & Sons.
- Håkansson, H., and Snehota, I. (1995). Developing Relationships in Business Networks, Routledge.
- Prenkert, 2019, Towards a systematic analytical framework of resource interfaces, J. Bus. Res., 100, 139, 10.1016/j.jbusres.2019.03.027 · DOI
- Korczynski, 1996, The low-trust route to economic development: Inter-firm relations in the UK engineering construction industry in the 1980S and 1990s, J. Manag. Stud., 33, 787, 10.1111/j.1467-6486.1996.tb00172.x · DOI
- Eriksson, 2011, Effects of cooperative procurement procedures on construction project performance: A conceptual framework, Int. J. Proj. Manag., 29, 197, 10.1016/j.ijproman.2010.01.003 · DOI
- Styhre, 2004, Learning capabilities in organizational networks: Case studies of six construction projects, Constr. Manag. Econ., 22, 957, 10.1080/0144619042000241417 · DOI
- Son, 2011, Implementing sustainable development in the construction industry: Constructors’ perspectives in the US and Korea, Sustain. Dev., 19, 337, 10.1002/sd.442 · DOI
- Ahola, 2008, Purchasing strategies and value creation in industrial turnkey projects, Int. J. Proj. Manag., 26, 87, 10.1016/j.ijproman.2007.08.008 · DOI
- Witjes, 2016, Towards a more circular economy: Proposing a framework linking sustainable public procurement and sustainable business models, Resour. Conserv. Recycl., 112, 37, 10.1016/j.resconrec.2016.04.015 · DOI · Paper page
- Bocken, 2016, Product design and business model strategies for a circular economy, J. Ind. Prod. Eng., 33, 308
- Vejaratnam, 2020, A systematic review of barriers impeding the implementation of government green procurement, J. Public Procure., 20, 451, 10.1108/JOPP-02-2020-0013 · DOI · Paper page
- Kristensen, 2021, Circular public procurement practices in Danish municipalities, J. Clean. Prod., 281, 124962, 10.1016/j.jclepro.2020.124962 · DOI · Paper page
- Droege, H., Raggi, A., and Ramos, T.B. (2021). Co-development of a framework for circular economy assessment in organisations: Learnings from the public sector. Corp. Soc. Responsib. Environ. Manag., 1–15. · DOI
- Håkansson, H.E. (1982). International Marketing and Purchasing of Industrial Goods—An Interaction Approach, Wiley.
- Håkan, H., and Ivan, S. (2017). The Significance of Business Relationships. No Business Is an Island: Making Sense of the Interactive Business World, Emerald Publishing Limited.
- Håkan, H., and Ivan, S. (2017). Researching the interactive business landscape. No Business Is an Island: Making Sense of the Interactive Business World, Emerald Publishing Limited.
- Baraldi, 2012, Resource interaction in inter-organizational networks: Foundations, comparison, and a research agenda, J. Bus. Res., 65, 266, 10.1016/j.jbusres.2011.05.030 · DOI
- Håkansson, H., and Waluszewski, A. (2002). Managing Technological Development: IKEA, the Environment and Technology, Routledge.
- Håkan, H., and Ivan, S. (2017). Interdendencies—Blessings and curses. No Business Is an Island: Making Sense of the Interactive Business World, Emerald Publishing Limited.
- Håkan, H., and Ivan, S. (2017). Management in the interactive business world. No Business Is an Island: Making Sense of the Interactive Business World, Emerald Publishing Limited.
- Yin, R.K. (2014). Case Study Research. Design and Methods, SAGE Publications. [5th ed.].
- Wilkins, 1991, Better stories, not better constructs, to generate better theory: A rejoinder to Eisenhardt, Acad. Manag. Rev., 16, 613, 10.2307/258920 · DOI
- Eisenhardt, 2007, Theory building from cases: Opportunities and challenges, Acad. Manag. J., 50, 25, 10.5465/amj.2007.24160888 · DOI · Paper page
- Gioia, 2013, Seeking qualitative rigor in inductive research: Notes on the Gioia methodology, Organ. Res. Methods, 16, 15, 10.1177/1094428112452151 · DOI · Paper page
- Eisenhardt, 1989, Building theories from case study research, Acad. Manag. Rev., 14, 532, 10.2307/258557 · DOI · Paper page
- Aggeri, 2021, Stimulating innovation and creating new markets—The potential of circular public procurement, J. Clean. Prod., 308, 127303, 10.1016/j.jclepro.2021.127303 · DOI · Paper page
- Metcalf, 2012, Leadership for sustainability: An evolution of leadership ability, J. Bus. Ethics, 112, 369, 10.1007/s10551-012-1278-6 · DOI
Cited by
Sorted by citations
Implementation and management of a circular public procurement contract for furniture
Lingegård, S., & von Oelreich, K. (2023) · Frontiers in Sustainability · doi:10.3389/frsus.2023.1136725 · Cited by 15
“Studies of CPP often focus on the drivers of, and barriers to, the implementation of this policy tool (Alhola et al., 2019; Kristensen et al., 2021; Lingegård et al., 2021a).”
BackgroundSelf-citationRethinking the project life cycle – how circularity challenges processes, roles and governance
Lingegård, S., & Hedborg, S. (2025) · Project Leadership and Society · doi:10.1016/j.plas.2025.100194 · Cited by 10
Self-citation
Metadata
- Authors
- Lingegård, S., Havenvid, M. I., & Eriksson, P.-E.
- Affiliations
- Department of Sustainable Development, Environmental Science and Engineering, KTH Royal Institute of Technology, 100 44 Stockholm, Sweden
- Department of Real Estate and Construction Management, KTH Royal Institute of Technology, 100 44 Stockholm, Sweden
- Department of Civil, Environmental and Natural Resources Engineering, Luleå University of Technology, 971 87 Luleå, Sweden
- Venue
- Sustainability
- Publisher
- MDPI AG
- Published
- 2021-10-29
- Volume
- 13
- Issue
- 21
- Pages
- 11983
- ISSN
- 2071-1050
- Cited by
- 20
- References
- 3
- Language
- en
- Funders
- Svenska Forskningsrådet Formas (254-2013-1837, 942-2016-126)
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review