Time and cost overruns in the UAE construction industry: a critical analysis
The DOI matches its Crossref record; 15 of the 15 references it cites were found in a registry or an index.
Abstract
Time and cost are the two main indicators of success in a construction project as it affects all the project participants with equal positive and negative effects. Yet, poor time and cost performance have been a critical issue prevailing in the global construction market and UAE have not been an exception. This research adopted a concurrent mixed-methods approach, utilizing a questionnaire and an interview with UAE construction professionals, to analyse the major causes of this poor time and cost performance. The top five causes for time overrun were concluded as design variation from client and consultant, unrealistic schedules and completion dates projected by clients, delay in obtaining government permits and approvals, inaccurate time estimation by the consultants and change orders from clients. Whereas, the top five causes of cost overrun were summarized as design variation, poor cost estimation, delay in client’s decision-making process, financial constraints of client and inappropriate procurement method.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Research design: qualitative, quantitative, and mixed methods approaches
Caldas, M. P. (2003) · Revista de Administração Contemporânea · doi:10.1590/s1415-65552003000100015 · Cited by 18,745
Bell, E., Bryman, A., & Harley, B. (2022) · Oxford University Press eBooks · doi:10.1093/hebz/9780198869443.001.0001 · Cited by 10,965
Business Research Methods: An Applied Orientation
Sreejesh, S., Mohapatra, S., & Anusree, M. R. (2014) · Springer eBooks · doi:10.1007/978-3-319-00539-3 · Cited by 2,933
Causes of delay in large construction projects
Assaf, S. A., & Al-Hejji, S. (2006) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.11.010 · Cited by 1,705 · cited 2×
“The causes of 70% delay of Saudi building projects were summarized by Assaf and Al-Hejji (2006) as issue of variations in design, payment delays, poor planning and scheduling, lack of site management by contractor, labour deficiency and financial difficulties of contractors.”
BackgroundKey performance indicators for measuring construction success
Chan, A. P. C., & Chan, A. P. L. (2004) · Benchmarking: An International Journal · doi:10.1108/14635770410532624 · Cited by 968 · cited 1×
“Construction sector have been distinctive and dynamic in nature, constantly dealing with uncertainties and temporary teams from multi-lingual and multi-cultural background (Chan and Chan 2004; Puspasari 2005; Acharya et al. 2006; El-Sayegh 2008).”
BackgroundFrimpong, Y., Oluwoye, J., & Crawford, L. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00055-8 · Cited by 796
Modelling global risk factors affecting construction cost performance
Baloi, D., & Price, A. D. F. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00017-0 · Cited by 587 · cited 2×
“More often, these claims can lead to disputes and affect the clients’ cost and contractors’ profits (Baloi and Price 2003).”
BackgroundMethodLe-Hoai, L., Lee, Y. D., & Lee, J. Y. (2008) · KSCE Journal of Civil Engineering · doi:10.1007/s12205-008-0367-7 · Cited by 560 · cited 13×
“The financial capabilities of both contractors and clients are very essential for the uninterrupted project flow (Le-Hoai et al. 2008). 3. Lack of experience: Frimponga et al. (2003) identifies that low bidders are encouraged for public construction projects which may lead to deficiency of experience and skills for ma…”
BackgroundInfluentialSignificant factors causing delay in the UAE construction industry
Faridi, A. S., & El‐Sayegh, S. M. (2006) · Construction Management and Economics · doi:10.1080/01446190600827033 · Cited by 551 · cited 2×
“However, time and cost overrun are frequently and unceasingly faced in construction projects irrespective of its size, nature and complexity (Faridi and ElSayegh 2006; Ren et al. 2008).”
BackgroundRisk assessment and allocation in the UAE construction industry
El-Sayegh, S. M. (2008) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.07.004 · Cited by 468 · cited 5×
“The above study revalidates the causes of cost overrun reviewed in literature by El-Sayegh (2008), Ren, et al. (2008) and Motaleb and Kishk (2010) and the questionnaire analysis.”
BackgroundResultInfluential
Metadata
- Authors
- Johnson, R. M., & Babu, R. I. I.
- Venue
- International Journal of Construction Management
- Publisher
- Informa UK Limited
- Published
- 2018-11-13
- Volume
- 20
- Issue
- 5
- Pages
- 402-411
- ISSN
- 1562-3599 (ISSN-L)
- 2331-2327
- OpenAlex
- W2901914917
- Cited by
- 173
- References
- 15
- FWCI
- 7.80
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
How to cite
Cite CoChat for the checks on this page, and the paper for its own findings.
- This page
- CoChat. (2026). Citation check: Time and cost overruns in the UAE construction industry: a critical analysis. https://app.cochat.ai/papers/10.1080/15623599.2018.1484864
- The paper
- Johnson, R. M., & Babu, R. I. I. (2020). Time and cost overruns in the UAE construction industry: a critical analysis. International Journal of Construction Management. https://doi.org/10.1080/15623599.2018.1484864
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.