Critical risk factors in the application of modular integrated construction: a systematic review
Open accessThe DOI matches its Crossref record; 3 of the 3 references it cites were found in a registry or an index.
Abstract
The business model of modular integrated construction (MiC) demands a unique design, engineering, supply chain, stakeholder composition, construction and management. These requirements engender manifold uncertainties and risks events which may derail the success of MiC projects. Empirical studies have examined the risks associated with MiC in different countries. However, the critical risk factors (CRFs) in the application of MiC have not been reviewed. This study conducted a systematic review and synthesis of 39 empirical studies on the risks of MiC and identified 30 CRFs. Based on the frequency of occurrences, the top ten (10) CRFs in the application of MiC have been discussed. Of these, stakeholder fragmentation and management complexity; higher initial capital cost; poor supply chain integration and disturbances; delays in delivery of modular components to the site and poor government support and regulations constitute the five (5) most CRFs. The findings are useful to countries which are yet to adopt MiC and may broaden the understanding of offsite construction researchers and practitioners on the risks of MiC. Future studies would make a quantitative ranking of the CRFs and propose management strategies.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Analyzing the Past to Prepare for the Future: Writing a Literature Review
Webster, J., & Watson, R. T. (2002) · MIS Quarterly · doi:10.2307/4132319 · Cited by 7,449 · cited 3×
“These were organized into a summary table, referred to as a thematic content matrix augmented with units of analyses (Webster and Watson 2002).”
BackgroundMethodWohlin, C. (2014) · Proceedings of the 18th International Conference on Evaluation and Assessment in Software Engineering · doi:10.1145/2601248.2601268 · Cited by 4,234 · cited 3×
“The snowballing search is an iterative process of locating additional studies based on the reference lists (backward snowballing) and citations (forward snowballing) of the previously identified 29 articles (Wohlin 2014).”
BackgroundMethodQuale, J., Eckelman, M. J., Williams, K. W., Sloditskie, G., & Zimmerman, J. B. (2012) · Journal of Industrial Ecology · doi:10.1111/j.1530-9290.2011.00424.x · Cited by 220 · cited 1×
“The superior contribution of the Journal of Cleaner Production (JCLP) is justifiable because MiC is considered a cleaner construction approach (Quale et al. 2012; Mao et al. 2013; Hwang et al. 2018) and thus, JCLP may be considered an appropriate research outlet for MiC studies.”
Background
Cited by
Critical success factors for modular integrated construction projects: a review
Wuni, I. Y., & Shen, G. Q. (2020) · Building Research & Information · doi:10.1080/09613218.2019.1669009 · Cited by 237
Self-citation
Metadata
- Authors
- Wuni, I. Y., Shen, G. Q. P., & Mahmud, A. T.
- Venue
- International Journal of Construction Management
- Publisher
- Informa UK Limited
- Published
- 2019-05-13
- Volume
- 22
- Issue
- 2
- Pages
- 133-147
- ISSN
- 1562-3599 (ISSN-L)
- 2331-2327
- OpenAlex
- W2945839074
- Cited by
- 185
- References
- 3
- FWCI
- 4.42
- Type
- journal article
- Language
- en
- Open access
- green
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
How to cite
Cite CoChat for the checks on this page, and the paper for its own findings.
- This page
- CoChat. (2026). Citation check: Critical risk factors in the application of modular integrated construction: a systematic review. https://app.cochat.ai/papers/10.1080/15623599.2019.1613212
- The paper
- Wuni, I. Y., Shen, G. Q. P., & Mahmud, A. T. (2022). Critical risk factors in the application of modular integrated construction: a systematic review. International Journal of Construction Management. https://doi.org/10.1080/15623599.2019.1613212
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.