Causes of delay in the global construction industry: a meta analytical review
The DOI matches its Crossref record; 50 of the 50 references it cites were found in a registry or an index.
Abstract
The construction industry continues to suffer from efficiency and productivity losses such as delays. The effects of delays may include time and cost overruns, litigation and project abandonment. Thus, the global research domain is saturated with studies investigating the causes of construction delay. However, despite the rising trend of construction globalization, a systematic review of what has been achieved so far in construction delay research is lacking. Such a study will synthesize extant data from previous studies to illustrate the global picture and will be of potential benefit to concerned stakeholders. Consequently, this study presents an overall review of studies on the causes of construction delays and executes a meta-data analysis utilizing Relative Importance Index (RII) values from some influential studies in the last 15 years. 36 common delay causes investigated globally were identified, and the effect summaries derived from the meta-analysis showed that the top five causes include: “contractor’s financial difficulties”, “delay in approval of completed work”, “slow delivery of materials”, “poor site organization and coordination between various parties”, and “poor planning of resources and duration estimation/scheduling”.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Borenstein, M., Hedges, L. V., Higgins, J. P. T., & Rothstein, H. R. (2009) · doi:10.1002/9780470743386 · Cited by 14,225 · cited 2×
“In other words, it is required that a narrative summary be followed by a numerical aggregation of the results of various studies to compute the effect summary (Borenstein et al. 2009).”
Causes of delay in large construction projects
Assaf, S. A., & Al-Hejji, S. (2006) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.11.010 · Cited by 1,705
Causes and effects of delays in Malaysian construction industry
Sambasivan, M., & Soon, Y. W. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.11.007 · Cited by 1,422
A comparative study of causes of time overruns in Hong Kong construction projects
Chan, D. W., & Kumaraswamy, M. M. (1997) · International Journal of Project Management · doi:10.1016/s0263-7863(96)00039-7 · Cited by 831
Causes of construction delay: traditional contracts
Odeh, A. M., & Battaineh, H. T. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00037-5 · Cited by 810
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00055-8 · Cited by 796
Analysing factors affecting delays in Indian construction projects
Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012) · International Journal of Project Management · doi:10.1016/j.ijproman.2011.10.004 · Cited by 745
Neyeloff, J. L., Fuchs, S. C., & Moreira, L. B. (2012) · BMC Research Notes · doi:10.1186/1756-0500-5-52 · Cited by 727
Factors influencing construction time and cost overruns on high-rise projects in Indonesia
Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997) · Construction Management and Economics · doi:10.1080/014461997373132 · Cited by 698
The effects of construction delays on project delivery in Nigerian construction industry
Aibinu, A. A., & Jagboro, G. O. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00028-5 · Cited by 597
Research works printed but not linked: 29
- Aaditya SP, 2018, GSTF J Eng Technol (JET), 5, 1
- Alinaitwe H, 2013, J Construct Devel Countries, 18, 33
- 10.1016/S0263-7863(98)00020-9 · doi:10.1016/s0263-7863(98)00020-9
- 10.1016/j.proeng.2016.04.121 · doi:10.1016/j.proeng.2016.04.121
- 10.1016/j.aej.2016.03.006 · doi:10.1016/j.aej.2016.03.006
- 10.1061/9780784412909.006 · doi:10.1061/9780784412909.006
- 10.1016/j.ijproman.2012.06.003 · doi:10.1016/j.ijproman.2012.06.003
- Fugar FD, 2010, CEB, 10, 103
- 10.1016/j.proeng.2011.11.192 · doi:10.1016/j.proeng.2011.11.192
- Haseeb M, 2011, Australian J Bus Manage Res, 1, 41
- Islam MS, Trigunarsyah B, Hassanain M, Assaf S. 2015. Causes of delay in construction projects in Bangladesh. In: The 6th International Conference on Construction Engineering and Project Management (ICCEPM 2015), Korea Institute of Construction Engineering and Management (KICEM). Vol. 6, p. 82–86.
- Kesavan M, Gobidan NN, Dissanayake PBG. 2015. Analysis of factors contributing civil engineering project delays in Sri Lanka. In: 6th International Conference on Structural Engineering and Construction Management 2015, Kandy, Sri Lanka. p. 40.
- 10.1061/(ASCE)0733-9364(1987)113:4(591) · doi:10.1061/(asce)0733-9364(1987)113:4(591
- Lessing B, 2017, J Manag Econ Ind Organ, 1, 63
- 10.1061/(ASCE)0733-9364(2006)132:6(636) · doi:10.1061/(asce)0733-9364(2006)132:6(636
- Masood R, 2015, J Civil Eng Arch Res, 2, 947
- 10.1590/s1678-86212017000300169 · doi:10.1590/s1678-86212017000300169
- Mbala M, 2018, International conference on applied human factors and ergonomics, 489
- Megha D, 2013, Int J Emerg Tech Adv Eng, 3, 396
- 10.1108/eb021079 · doi:10.1108/eb021079 · Paper page
- Muhwezi L, 2014, Int J Construct Eng Manage, 3, 13
- 10.1108/13664381211274335 · doi:10.1108/13664381211274335
- Pourrostam T, Ismail A. 2011. Significant factors causing and effects of delay in Iranian construction projects. Aus J Basic App Sci. 5(7):450–456.
- Ravisankar KL, 2014, Int J Emerg Technol Adv Eng, 4, 105
- Ren Z, Atout M, Jones J. 2008. ‘Root causes of construction project delays in Dubai’, In 24th Annual ARCOM Conference, 1–3 September 2008, Cardiff, UK, Association of Researchers in Construction Management, p. 749–757.
- Tafazzoli M, 2017, Construction Projects’, 53rd ASC Annual International Conference Proceedings by the Associated Schools of Construction
- 10.1016/B978-1-85617-677-4.00002-7 · doi:10.1016/b978-1-85617-677-4.00002-7
- Tumi SAH, 2009, The International Conference on Economics and Administration, 265
- Zidane Y, 2018, J Modern Proj Manage, 5, 80
Cited by
Ahmed Bukar, A., & Abbas Ibrahim, U. (2021) · Science Journal of Business and Management · doi:10.11648/j.sjbm.20210903.20 · Cited by 10
Metadata
- Authors
- Sanni-Anibire, M. O., Mohamad Zin, R., & Olatunji, S. O.
- Venue
- International Journal of Construction Management
- Publisher
- Informa UK Limited
- Published
- 2020-02-12
- Volume
- 22
- Issue
- 8
- Pages
- 1395-1407
- ISSN
- 1562-3599 (ISSN-L)
- 2331-2327
- OpenAlex
- W3005971019
- Cited by
- 173
- References
- 50
- FWCI
- 12.11
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.