Causes of delay in the global construction industry: a meta analytical review

Sanni-Anibire, Muizz O., Mohamad Zin, Rosli, Olatunji, Sunday Olusanya · 2022 · International Journal of Construction Management
Cited by 173

The DOI matches its Crossref record; 50 of the 50 references it cites were found in a registry or an index.

Abstract

The construction industry continues to suffer from efficiency and productivity losses such as delays. The effects of delays may include time and cost overruns, litigation and project abandonment. Thus, the global research domain is saturated with studies investigating the causes of construction delay. However, despite the rising trend of construction globalization, a systematic review of what has been achieved so far in construction delay research is lacking. Such a study will synthesize extant data from previous studies to illustrate the global picture and will be of potential benefit to concerned stakeholders. Consequently, this study presents an overall review of studies on the causes of construction delays and executes a meta-data analysis utilizing Relative Importance Index (RII) values from some influential studies in the last 15 years. 36 common delay causes investigated globally were identified, and the effect summaries derived from the meta-analysis showed that the top five causes include: “contractor’s financial difficulties”, “delay in approval of completed work”, “slow delivery of materials”, “poor site organization and coordination between various parties”, and “poor planning of resources and duration estimation/scheduling”.

Overview

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.1080/15623599.2020.1716132

Cites

50 of 50 references verified0 citation errors · 0 not checkable

Statistics

Verification

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

Citations

Cites

Research works printed but not linked: 29

  1. Aaditya SP, 2018, GSTF J Eng Technol (JET), 5, 1
  2. Alinaitwe H, 2013, J Construct Devel Countries, 18, 33
  3. 10.1016/S0263-7863(98)00020-9 · doi:10.1016/s0263-7863(98)00020-9
  4. 10.1016/j.proeng.2016.04.121 · doi:10.1016/j.proeng.2016.04.121
  5. 10.1016/j.aej.2016.03.006 · doi:10.1016/j.aej.2016.03.006
  6. 10.1061/9780784412909.006 · doi:10.1061/9780784412909.006
  7. 10.1016/j.ijproman.2012.06.003 · doi:10.1016/j.ijproman.2012.06.003
  8. Fugar FD, 2010, CEB, 10, 103
  9. 10.1016/j.proeng.2011.11.192 · doi:10.1016/j.proeng.2011.11.192
  10. Haseeb M, 2011, Australian J Bus Manage Res, 1, 41
  11. Islam MS, Trigunarsyah B, Hassanain M, Assaf S. 2015. Causes of delay in construction projects in Bangladesh. In: The 6th International Conference on Construction Engineering and Project Management (ICCEPM 2015), Korea Institute of Construction Engineering and Management (KICEM). Vol. 6, p. 82–86.
  12. Kesavan M, Gobidan NN, Dissanayake PBG. 2015. Analysis of factors contributing civil engineering project delays in Sri Lanka. In: 6th International Conference on Structural Engineering and Construction Management 2015, Kandy, Sri Lanka. p. 40.
  13. 10.1061/(ASCE)0733-9364(1987)113:4(591) · doi:10.1061/(asce)0733-9364(1987)113:4(591
  14. Lessing B, 2017, J Manag Econ Ind Organ, 1, 63
  15. 10.1061/(ASCE)0733-9364(2006)132:6(636) · doi:10.1061/(asce)0733-9364(2006)132:6(636
  16. Masood R, 2015, J Civil Eng Arch Res, 2, 947
  17. 10.1590/s1678-86212017000300169 · doi:10.1590/s1678-86212017000300169
  18. Mbala M, 2018, International conference on applied human factors and ergonomics, 489
  19. Megha D, 2013, Int J Emerg Tech Adv Eng, 3, 396
  20. 10.1108/eb021079 · doi:10.1108/eb021079 · Paper page
  21. Muhwezi L, 2014, Int J Construct Eng Manage, 3, 13
  22. 10.1108/13664381211274335 · doi:10.1108/13664381211274335
  23. Pourrostam T, Ismail A. 2011. Significant factors causing and effects of delay in Iranian construction projects. Aus J Basic App Sci. 5(7):450–456.
  24. Ravisankar KL, 2014, Int J Emerg Technol Adv Eng, 4, 105
  25. Ren Z, Atout M, Jones J. 2008. ‘Root causes of construction project delays in Dubai’, In 24th Annual ARCOM Conference, 1–3 September 2008, Cardiff, UK, Association of Researchers in Construction Management, p. 749–757.
  26. Tafazzoli M, 2017, Construction Projects’, 53rd ASC Annual International Conference Proceedings by the Associated Schools of Construction
  27. 10.1016/B978-1-85617-677-4.00002-7 · doi:10.1016/b978-1-85617-677-4.00002-7
  28. Tumi SAH, 2009, The International Conference on Economics and Administration, 265
  29. Zidane Y, 2018, J Modern Proj Manage, 5, 80

Cited by

See all 173

Metadata

Authors
Sanni-Anibire, M. O., Mohamad Zin, R., & Olatunji, S. O.
Venue
International Journal of Construction Management
Published
2020-02-12
Volume
22
Issue
8
Pages
1395-1407
ISSN
  • 1562-3599 (ISSN-L)
  • 2331-2327
OpenAlex
W3005971019
Cited by
173
References
50
FWCI
12.11
Type
journal article
Language
en
Open access
closed

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review

Data sources

Bibliographic data: Semantic Scholar, OpenAlex, Crossref.

Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).

Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.