A study on project success factors in large construction projects in Vietnam
The DOI matches its Crossref record; 21 of the 21 references it cites were found in a registry or an index.
Abstract
Large construction projects are inherently complex and dynamic. A comprehensive answer on how to manage such projects successfully is difficult to provide. This paper expounds on the success factors for large construction projects in Vietnam. A survey questionnaire was used to collect data from practitioners. Factor analysis was employed to categorize these success factors perceived by 109 respondents from 42 construction‐related organizations. Factor analysis uncovered that these success factors can be grouped under four categories, here titled the four COMs: comfort, competence, commitment, and communication. The result can be used as a guideline to successfully handle construction projects in Vietnam as well as in other countries, especially in the emerging economies in Asia and the rest of the world.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Herne, H., Cooley, W. W., & Lohnes, P. R. (1973) · Journal of the Royal Statistical Society. Series A (General) · doi:10.2307/2344428 · Cited by 35,697
Project management : a systems approach to planning, scheduling, and controlling
Kerzner, H. (1995) · Thammasat University Digital Collections · Cited by 3,099
Chief executives define their own data needs.
Rockart, J. F. (1979) · PubMed · Cited by 2,802
The “real” success factors on projects
Cooke-Davies, T. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(01)00067-9 · Cited by 1,837
A new framework for determining critical success/failure factors in projects
Belassi, W., & Tukel, O. I. (1996) · International Journal of Project Management · doi:10.1016/0263-7863(95)00064-x · Cited by 1,187
The Logical Framework Method for Defining Project Success
Baccarini, D. (1999) · Project Management Journal · doi:10.1177/875697289903000405 · Cited by 1,136
Measurement of project success
de Wit, A. (1988) · International Journal of Project Management · doi:10.1016/0263-7863(88)90043-9 · Cited by 977
The role of project management in achieving project success
Munns, A., & Bjeirmi, B. (1996) · International Journal of Project Management · doi:10.1016/0263-7863(95)00057-7 · Cited by 910
Current practice in project management — an empirical study
White, D., & Fortune, J. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00029-6 · Cited by 705
An assessment of critical success factors
Zahidy, I. (1984) · Cited by 679
Cited by
Toor, S.-U.-R., & Ogunlana, S. O. (2010) · International Journal of Project Management · doi:10.1016/j.ijproman.2009.05.005 · Cited by 619
Self-citationLe-Hoai, L., Lee, Y. D., & Lee, J. Y. (2008) · KSCE Journal of Civil Engineering · doi:10.1007/s12205-008-0367-7 · Cited by 560
Banihashemi, S., Hosseini, M. R., Golizadeh, H., & Sankaran, S. (2017) · International Journal of Project Management · doi:10.1016/j.ijproman.2017.01.014 · Cited by 441
Alzahrani, J. I., & Emsley, M. W. (2013) · International Journal of Project Management · doi:10.1016/j.ijproman.2012.06.006 · Cited by 344
Structural Equation Model for Evaluating Factors Affecting Quality of Social Infrastructure Projects
Hussain, S., Fangwei, Z., Siddiqi, A. F., Ali, Z., & Shabbir, M. S. (2018) · Sustainability · doi:10.3390/su10051415 · Cited by 245
“[42] Vietnam Chan and Tam [23] Hong Kong”
BackgroundIdentification of variables that impact project success in Brazilian companies
Berssaneti, F. T., & Carvalho, M. M. (2015) · International Journal of Project Management · doi:10.1016/j.ijproman.2014.07.002 · Cited by 225
From Construction Megaproject Management to Complex Project Management: Bibliographic Analysis
Hu, Y., Chan, A. P. C., Le, Y., & Jin, R.-Z. (2015) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000254 · Cited by 221
Integrating sustainability indicators into project management: The case of construction industry
Stanitsas, M., Kirytopoulos, K., & Leopoulos, V. (2021) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2020.123774 · Cited by 220
Improving project management performance of large contractors using benchmarking approach
Luu, V. T., Kim, S.-Y., & Huynh, T.-A. (2008) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.10.002 · Cited by 208
“[29] uncovered 15 project success factors grouped under four COMs: comfort, competence, commitment and communication.”
BackgroundMethodCritical Project Management Factors of AEC Firms for Delivering Green Building Projects in Singapore
Li, Y. Y., Chen, P.-H., Chew, D. A. S., Teo, C. C., & Ding, R. G. (2011) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000370 · Cited by 174
Zuo, J., Zhao, X., Nguyen, Q. B. M., Ma, T., & Gao, S. (2018) · Engineering, Construction and Architectural Management · doi:10.1108/ecam-01-2016-0016 · Cited by 172
Recycling the construction and demolition waste in Vietnam: opportunities and challenges in practice
Lockrey, S., Nguyen, H., Crossin, E., & Verghese, K. (2016) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2016.05.175 · Cited by 161
Manzoor, B., Othman, I., Durdyev, S., Ismail, S., & Wahab, M. (2021) · Applied System Innovation · doi:10.3390/asi4030052 · Cited by 118
“Changes or circumstances that occur during the lifespan of projects create a variety of needs or for a variety of reasons [85,86].”
Background
Metadata
- Authors
- Duy Nguyen, L., Ogunlana, S. O., & Thi Xuan Lan, D.
- Venue
- Engineering, Construction and Architectural Management
- Publisher
- Emerald
- Published
- 2004-12-01
- Volume
- 11
- Issue
- 6
- Pages
- 404-413
- ISSN
- 0969-9988 (ISSN-L)
- OpenAlex
- W2094030958
- Cited by
- 415
- References
- 21
- FWCI
- 4.72
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.