Interdependence in supply chains and projects in construction
Abstract
Purpose: The aim of this paper is to inquire into the management of construction supply chains by directing attention toward the different types of interdependencies that exist in such chains and in construction projects. Design/methodology/approach: The paper is developed as part of two ongoing research projects on supply chain management (SCM) in construction. A case study approach is used for illustrating the production and subsequent delivery and installation of plasterboards to a specific construction project. This description reveals extensive coordination among a number of companies and features interesting examples of the consequences of the interdependencies identified. Findings: The paper concludes that the strong emphasis on coordination of sequential interdependence within individual supply chains does not fit with the complex interdependencies present in and among supply chains and projects in construction. In addition to sequential interdependence it describes and illustrates pooled interdependence based on joint resource utilisation, reciprocal interdependence among activities undertaken at the construction site, and interdependence owing to synchronisation of many supply chains in relation to each and every construction project. The combined effects of these interdependencies challenge traditional SCM recommendations, such as moving activities from the site to the factory. Originality/value: The main theoretical argument put forward in this paper is that the application of SCM models developed for other industrial contexts such as the automotive industry, are problematic to use in the construction industry. This is because these models emphasise integration of activities that are subject mainly to sequential interdependencies while the pattern of interdependence is very different in construction. A main implication for practice is that focusing on better planning in order to deal with activities that are mainly subject to sequential interdependence, is insufficient. The reciprocal interdependencies in construction require more frequent and direct interaction among the involved actors to enable mutual adjustments among the firms whose activities and resource use need to be coordinated.
Overview
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Systematic combining: an abductive approach to case research
Dubois, A., & Gadde, L.-E. (2002) · Journal of Business Research · doi:10.1016/s0148-2963(00)00195-8 · Cited by 4,941
Self-citationGann, D. M., & Salter, A. J. (2000) · Research Policy · doi:10.1016/s0048-7333(00)00114-1 · Cited by 1,315
The construction industry as a loosely coupled system: implications for productivity and innovation
Dubois, A., & Gadde, L.-E. (2002) · Construction Management and Economics · doi:10.1080/01446190210163543 · Cited by 1,041
Self-citationWhat is coordination theory and how can it help design cooperative work systems?
Malone, T. W., & Crowston, K. (1990) · Proceedings of the 1990 ACM conference on Computer-supported cooperative work - CSCW '90 · doi:10.1145/99332.99367 · Cited by 866
Pagell, M. (2004) · Journal of Operations Management · doi:10.1016/j.jom.2004.05.008 · Cited by 864
The four roles of supply chain management in construction
Vrijhoef, R., & Koskela, L. (2000) · European Journal of Purchasing & Supply Management · doi:10.1016/s0969-7012(00)00013-7 · Cited by 862
Supply chain management integration and implementation: a literature review
Power, D. (2005) · Supply Chain Management: An International Journal · doi:10.1108/13598540510612721 · Cited by 711
A survey of supply chain collaboration and management in the UK construction industry
Akintoye, A., McIntosh, G., & Fitzgerald, E. (2000) · European Journal of Purchasing & Supply Management · doi:10.1016/s0969-7012(00)00012-5 · Cited by 549
Supply chain integration and performance: a review of the evidence
Fabbe‐Costes, N., & Jahre, M. (2008) · The International Journal of Logistics Management · doi:10.1108/09574090810895933 · Cited by 409
Self-citationRe-engineering through pre-assembly: client expectations and drivers
Gibb, A., & Isack, F. (2003) · Building Research & Information · doi:10.1080/09613210302000 · Cited by 397
Cited by
Weng, Y., Li, M., Ruan, S., Wong, T. N., Tan, M. J., Ow Yeong, K. L., & Qian, S. (2020) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2020.121245 · Cited by 305
Construction industry productivity and the potential for collaborative practice
Fulford, R., & Standing, C. (2014) · International Journal of Project Management · doi:10.1016/j.ijproman.2013.05.007 · Cited by 259
Barriers to implementing reverse logistics in South Australian construction organisations
Chileshe, N., Rameezdeen, R., Hosseini, M. R., & Lehmann, S. (2015) · Supply Chain Management: An International Journal · doi:10.1108/scm-10-2014-0325 · Cited by 121
Metadata
- Authors
- Bankvall, L., Bygballe, L. E., Dubois, A., & Jahre, M.
- Venue
- Supply Chain Management: An International Journal
- Publisher
- Emerald
- Published
- 2010-08-10
- Volume
- 15
- Issue
- 5
- Pages
- 385-393
- ISSN
- 1359-8546 (ISSN-L)
- OpenAlex
- W2120341229
- Cited by
- 253
- References
- 41
- FWCI
- 14.83
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
How to cite
Cite CoChat for the checks on this page, and the paper for its own findings.
- This page
- CoChat. (2026). Citation check: Interdependence in supply chains and projects in construction. https://app.cochat.ai/papers/10.1108/13598541011068314
- The paper
- Bankvall, L., Bygballe, L. E., Dubois, A., & Jahre, M. (2010). Interdependence in supply chains and projects in construction. Supply Chain Management: An International Journal. https://doi.org/10.1108/13598541011068314
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.