Risk management in oil and gas construction projects in Vietnam
The DOI matches its Crossref record; 8 of the 8 references it cites were found in a registry or an index.
Abstract
Purpose: The purpose of the paper is to the identify risk factors, which affect oil and gas construction projects in Vietnam and derive risk responses. Design/methodology/approach: Questionnaire survey was conducted with the involvement of project executives of PetroVietnam and statistical analysis was carried out in order to identify the major project risks. Subsequently, mitigating measures were derived using informal interviews with the various levels of management of PetroVietnam. Findings: Bureaucratic government system and long project approval procedures, poor design, incompetence of project team, inadequate tendering practices, and late internal approval processes from the owner were identified as major risks. The executives suggested various strategies to mitigate the identified risks. Reforming the government system, effective partnership with foreign collaborators, training project executives, implementing contractor evaluation using multiple criteria decision‐making technique, and enhancing authorities of project people were suggested as viable approaches. Practical implications: The improvement measures as derived in this study would improve chances of project success in the oil and gas industry in Vietnam. Originality/value: There are several risk management studies on managing projects in developing countries. However, as risk factors vary considerably across industry and countries, the study of risk management for successful projects in the oil and gas industry in Vietnam is unique and has tremendous importance for effective project management.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Project management : a systems approach to planning, scheduling, and controlling
Kerzner, H. (1995) · Thammasat University Digital Collections · Cited by 3,099
Training in Organizations: Needs Assessment, Development, and Evaluation
Goldstein, I. L., & Ford, J. K. (1986) · Cited by 1,061
Project Management: Strategic Design and Implementation
Cleland, D. I. (1990) · Cited by 744
Smith, M. (1991) · Analyzing Organizational Behaviour · doi:10.1007/978-1-349-21542-3_4 · Cited by 400
Lowest price or value? Investigation of UK construction clients' tender selection process
Wong, C. H., Holt, G. D., & Cooper, P. A. (2000) · Construction Management and Economics · doi:10.1080/014461900433050 · Cited by 177 · cited 1×
“In addition, since tendering is a very sensitive issue, accepting the lowest-price tender may help the public owners to defend themselves from criticisms and to show accountability (Wong et al., 2000).”
BackgroundRisk and risk management in construction: a review and future directions for research
Edwards, P. J., & Bowen, P. A. (1998) · Engineering Construction and Architectural Management · doi:10.1046/j.1365-232x.1998.54072.x · Cited by 160
New Project Procurement Process
Brown, D. C., Ashleigh, M., Riley, M. J., & Shaw, R. D. (2001) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(2001)17:4(192 · Cited by 61
Bajracharya, A., Ogunlana, S. O., & Bach, N. L. (2000) · System Dynamics Review · doi:10.1002/1099-1727(200022)16:2 · Cited by 19 · cited 1×
“Bajracharya et al. (2000) also suggested that training should be aligned to organizational goals with training outcomes properly integrated to organizational processes.”
BackgroundSelf-citation
Cited by
Kassem, M. A. (2022) · Gases · doi:10.3390/gases2020003 · Cited by 36
“Project management risk factors: According to [3,79], the existence of high-ranking management-related hazards demonstrates the customers’ inability to plan, organize, motivate, lead, and control projects.”
Background
Metadata
- Authors
- Van Thuyet, N., Ogunlana, S. O., & Dey, P. K.
- Venue
- International Journal of Energy Sector Management
- Publisher
- Emerald
- Published
- 2007-02-27
- Volume
- 1
- Issue
- 2
- Pages
- 175-194
- ISSN
- 1750-6220 (ISSN-L)
- OpenAlex
- W2004397129
- Cited by
- 162
- References
- 8
- FWCI
- 1.43
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.