Fuzzy Monte Carlo Simulation and Risk Assessment in Construction
Open accessThe DOI matches its Crossref record; 27 of the 27 references it cites were found in a registry or an index.
Abstract
Monte Carlo simulation has been used extensively for addressing probabilistic uncertainty in range estimating for construction projects. However, subjective and linguistically expressed information results in added non‐probabilistic uncertainty in construction management. Fuzzy logic has been used successfully for representing such uncertainties in construction projects. In practice, an approach that can handle both random and fuzzy uncertainties in a risk assessment model is necessary. This article discusses the deficiencies of the available methods and proposes a Fuzzy Monte Carlo Simulation (FMCS) framework for risk analysis of construction projects. In this framework, we construct a fuzzy cumulative distribution function as a novel way to represent uncertainty. To verify the feasibility of the FMCS framework and demonstrate its main features, the authors have developed a special purpose simulation template for cost range estimating. This template is employed to estimate the cost of a highway overpass project.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Zadeh, L. A. (1965) · Information and Control · doi:10.1016/s0019-9958(65)90241-x · Cited by 67,855
Zadeh, L. A. (1996) · Cited by 46,857
A Mathematical Theory of Evidence
Shafer, G. (1976) · Princeton University Press eBooks · doi:10.1515/9780691214696 · Cited by 9,083
Fuzzy logic and approximate reasoning: In memory of Grigore Moisil
Zadeh, L. A. (1975) · Synthese · doi:10.1007/bf00485052 · Cited by 1,617
Witold Pedrycz, C., & Gomide, F. A. C. (1998) · The MIT Press eBooks · doi:10.7551/mitpress/3926.001.0001 · Cited by 1,208
Statistical Methods for Eliciting Probability Distributions
Garthwaite, P. H., Kadane, J. B., & O'Hagan, A. (2005) · Journal of the American Statistical Association · doi:10.1198/016214505000000105 · Cited by 801 · cited 2×
“This estimated probability may be used directly in a risk analysis problem (Ahuja et al., 1994), or it may be combined with available data using Bayesian methods to estimate a parameter that considers both subjective judgment and historical data (Garthwaite et al., 2005).”
BackgroundMethodProbability-Possibility Transformations, Triangular Fuzzy Sets, and Probabilistic Inequalities
Dubois, D., Foulloy, L., Mauris, G. P., & Prade, H. M. (2004) · Reliable Computing · doi:10.1023/b:reom.0000032115.22510.b5 · Cited by 620 · cited 3×
“To experiment with the FMCS approach using a combination of fuzzy and probabilistic inputs, some of the probability distributions of Table 2 are transformed into fuzzy sets using the probability-possibility transformation method of Dubois et al. (2004).”
BackgroundMethodInfluentialFuzzy Systems Engineering: Toward Human‐Centric Computing
Pedrycz, W., & Gomide, F. (2007) · Wiley eBooks · doi:10.1002/9780470168967 · Cited by 507
Self-citationProject Management: Techniques in Planning and Controlling Construction Projects
Ahuja, H. N., Dozzi, S. P., & AbouRizk, S. (1984) · Cited by 234
Subjective Bayesian Analysis: Principles and Practice
Goldstein, M. (2006) · Bayesian Analysis · doi:10.1214/06-ba116 · Cited by 214 · cited 2×
“because subjective reasoning of individuals may not be appropriate for objective scientific conclusions (Goldstein, 2006).”
BackgroundInfluentialHybrid Approach for Addressing Uncertainty in Risk Assessments
Guyonnet, D., Bourgine, B., Dubois, D., Fargier, H., Co⁁me, B., & Chilès, J.-P. (2003) · Journal of Environmental Engineering · doi:10.1061/(asce)0733-9372(2003)129:1(68 · Cited by 208 · cited 11×
“For decision making based on the hybrid approach, Guyonnet et al. (2003) developed the histograms of the Inf and Sup values of the α-cuts at each α-level and calculated the final Inf and Sup of the output α-cut based on a 5% probability of getting values lower than Inf and higher than Sup (Figure…”
BackgroundMethodInfluentialA fuzzy approach for the expression of uncertainty in measurement
Mauris, G., Lasserre, V., & Foulloy, L. (2001) · Measurement · doi:10.1016/s0263-2241(00)00036-1 · Cited by 207 · cited 1×
“This range is calculated by finding the α-cut at the value of 1 minus the confidence level (Mauris et al., 2001).”
BackgroundLife‐cycle cost optimization of steel structures
Sarma, K. C., & Adeli, H. (2002) · International Journal for Numerical Methods in Engineering · doi:10.1002/nme.549 · Cited by 185 · cited 1×
“…(Fayek and Oduba, 2005), saving energy in domestic heating systems (Villar et al., 2009), cost and life-cycle cost optimization of steel structures (Sarma and Adeli, 2000a, 2000b, 2002), freeway work zone capacity estimation (Adeli and Jiang, 2003), traffic flow forecasting (Stathopoulos et al.,…”
BackgroundDynamic fuzzy wavelet neuroemulator for non‐linear control of irregular building structures
Jiang, X., & Adeli, H. (2008) · International Journal for Numerical Methods in Engineering · doi:10.1002/nme.2195 · Cited by 178 · cited 2×
“…estimation (Adeli and Jiang, 2003), traffic flow forecasting (Stathopoulos et al., 2008), structural health monitoring (Carden and Brownjohn, 2008), and nonlinear control of high-rise building structures (Nomura et al., 2007; Jiang and Adeli, 2008), just to name a few representative examples.”
BackgroundNeuro-Fuzzy Logic Model for Freeway Work Zone Capacity Estimation
Adeli, H., & Jiang, X. (2003) · Journal of Transportation Engineering · doi:10.1061/(asce)0733-947x(2003)129:5(484 · Cited by 170 · cited 2×
“, 2009), cost and life-cycle cost optimization of steel structures (Sarma and Adeli, 2000a, 2000b, 2002), freeway work zone capacity estimation (Adeli and Jiang, 2003), traffic flow forecasting (Stathopoulos et al.”
BackgroundFuzzy Genetic Algorithm for Optimization of Steel Structures
Sarma, K. C., & Adeli, H. (2000) · Journal of Structural Engineering · doi:10.1061/(asce)0733-9445(2000)126:5(596 · Cited by 159 · cited 1×
“…(Fayek and Oduba, 2005), saving energy in domestic heating systems (Villar et al., 2009), cost and life-cycle cost optimization of steel structures (Sarma and Adeli, 2000a, 2000b, 2002), freeway work zone capacity estimation (Adeli and Jiang, 2003), traffic flow forecasting (Stathopoulos et al.,…”
BackgroundFuzzy Discrete Multicriteria Cost Optimization of Steel Structures
Sarma, K. C., & Adeli, H. (2000) · Journal of Structural Engineering · doi:10.1061/(asce)0733-9445(2000)126:11(1339 · Cited by 143 · cited 1×
“…(Fayek and Oduba, 2005), saving energy in domestic heating systems (Villar et al., 2009), cost and life-cycle cost optimization of steel structures (Sarma and Adeli, 2000a, 2000b, 2002), freeway work zone capacity estimation (Adeli and Jiang, 2003), traffic flow forecasting (Stathopoulos et al.,…”
BackgroundFuzzy Genetic Algorithm for Optimization of Steel Structures
(2006) · Cost Optimization of Structures · doi:10.1002/0470867353.ch4 · Cited by 140
Fuzzy Modeling Approach for Combined Forecasting of Urban Traffic Flow
Stathopoulos, A., Dimitriou, L., & Tsekeris, T. (2008) · Computer-Aided Civil and Infrastructure Engineering · doi:10.1111/j.1467-8667.2008.00558.x · Cited by 136 · cited 1×
“…of steel structures (Sarma and Adeli, 2000a, 2000b, 2002), freeway work zone capacity estimation (Adeli and Jiang, 2003), traffic flow forecasting (Stathopoulos et al., 2008), structural health monitoring (Carden and Brownjohn, 2008), and nonlinear control of high-rise building structures (Nomura…”
BackgroundPredicting Industrial Construction Labor Productivity Using Fuzzy Expert Systems
Fayek, A. R., & Oduba, A. (2005) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2005)131:8(938 · Cited by 119 · cited 2×
“…modeling risk allocation in privately financed infrastructure projects (Jin and Doloi, 2009), predicting industrial construction labor productivity (Fayek and Oduba, 2005), saving energy in domestic heating systems (Villar et al., 2009), cost and life-cycle cost optimization of steel structures…”
BackgroundSelf-citationFuzzy Clustering of Stability Diagrams for Vibration‐Based Structural Health Monitoring
Carden, E. P., & Brownjohn, J. (2008) · Computer-Aided Civil and Infrastructure Engineering · doi:10.1111/j.1467-8667.2008.00543.x · Cited by 105 · cited 2×
“, 2008), structural health monitoring (Carden and Brownjohn, 2008), and nonlinear control of high-rise building structures (Nomura et al.”
BackgroundProbabilistic Model for Cost Contingency
Touran, A. (2003) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2003)129:3(280 · Cited by 105 · cited 2×
“Adeli and Wu, 1998) and for determining a contingency value (Touran, 2003).”
BackgroundMethodFuzzy Numbers in Cost Range Estimating
Shaheen, A. A., Fayek, A. R., & AbouRizk, S. (2007) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2007)133:4(325 · Cited by 97 · cited 3×
“Shaheen et al. (2007) suggested an alternative method of using fuzzy set theory for modeling uncertainties in range estimating problems.”
MethodSelf-citationA fuzzy logic based efficient energy saving approach for domestic heating systems
Villar, J. R., de la Cal, E., & Sedano, J. (2009) · Integrated Computer-Aided Engineering · doi:10.3233/ica-2009-0302 · Cited by 54 · cited 2×
“For example, fuzzy logic approaches have been implemented for project scheduling (Lorterapong and Moselhi, 1996), construction bidding (Chao, 2007), modeling risk allocation in privately financed infrastructure projects (Jin and Doloi, 2009), predicting industrial construction labor productivity (Fayek and Oduba, 2005…”
BackgroundAn Integrated Fuzzy Control System for Structural Vibration
Nomura, Y., Furuta, H., & Hirokane, M. (2007) · Computer-Aided Civil and Infrastructure Engineering · doi:10.1111/j.1467-8667.2007.00487.x · Cited by 45 · cited 2×
“…estimation (Adeli and Jiang, 2003), traffic flow forecasting (Stathopoulos et al., 2008), structural health monitoring (Carden and Brownjohn, 2008), and nonlinear control of high-rise building structures (Nomura et al., 2007; Jiang and Adeli, 2008), just to name a few representative examples.”
BackgroundModeling Risk Allocation in Privately Financed Infrastructure Projects Using Fuzzy Logic
Jin, X., & Doloi, H. K. (2009) · Computer-Aided Civil and Infrastructure Engineering · doi:10.1111/j.1467-8667.2009.00609.x · Cited by 42 · cited 1×
“…(Lorterapong and Moselhi, 1996), construction bidding (Chao, 2007), modeling risk allocation in privately financed infrastructure projects (Jin and Doloi, 2009), predicting industrial construction labor productivity (Fayek and Oduba, 2005), saving energy in domestic heating systems…”
BackgroundProbabilistic foundations for measurement modelling with fuzzy random variables
Terán, P. (2006) · Fuzzy Sets and Systems · doi:10.1016/j.fss.2006.12.006 · Cited by 37 · cited 6×
“This scenario is similar to results obtained from FMCS. Terán (2007) suggested the use of fuzzy arithmetic to perform statistical calculations on the fuzzy samples.”
BackgroundMethodResultInfluential
Cited by
Machine learning algorithms for construction projects delay risk prediction
Gondia, A., Siam, A., El-Dakhakhni, W., & Nassar, A. H. (2020) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001736 · Cited by 327
Smart structures: Part I—Active and semi-active control
Fisco, N. R., & Adeli, H. (2011) · Scientia Iranica · doi:10.1016/j.scient.2011.05.034 · Cited by 270
Smart structures: Part II — Hybrid control systems and control strategies
Fisco, N. R., & Adeli, H. (2011) · Scientia Iranica · doi:10.1016/j.scient.2011.05.035 · Cited by 177
Afzal, F., Yunfei, S., Nazir, M., & Bhatti, S. M. (2021) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-02-2019-0047 · Cited by 172
Islam, M. S., Nepal, M. P., Skitmore, M., & Attarzadeh, M. (2017) · Advanced Engineering Informatics · doi:10.1016/j.aei.2017.06.001 · Cited by 163
Metadata
- Authors
- Sadeghi, N., Fayek, A. R., & Pedrycz, W.
- Venue
- Computer-Aided Civil and Infrastructure Engineering
- Publisher
- Elsevier BV
- Published
- 2010-03-19
- Volume
- 25
- Issue
- 4
- Pages
- 238-252
- ISSN
- 1093-9687 (ISSN-L)
- 1467-8667
- OpenAlex
- W2058350584
- Cited by
- 204
- References
- 27
- FWCI
- 11.28
- Type
- journal article
- Language
- en
- Open access
- hybrid
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.