Significant Factors Causing Cost Overruns in Large Construction Projects in Malaysia

Open access
Rahman, Ismail Abdul, Hameed Mem, Aftab, Abd. Karim, Ahmad Tarmizi · 2013 · Journal of Applied Sciences

Abstract

Once a construction projects fails in achieving effective cost performance, it will result to cost overruns. These overruns are caused from several factors which are very important to uncover for improving the cost performance. In Malaysia, not many research works have been carried out on studying cost performance factors. Hence, this study was conducted to identify the significant factors causing cost overrun in large construction projects in Malaysia. Questionnaire for the survey was developed based on 35 common factors of cost overrun identified from literature work. These factors were grouped in 7 categories and validated by interviewing five experienced personnel of construction industry. The feedback of from the survey resulted in receiving 262 sets of completed valid responses against 400 questionnaires distributed amongst contractors, consultants and clients involved in large construction projects. The data from the questionnaire was analyzed statistically. Relative importance index method was used for hierarchal assessment of factors and found that the top 3 most significant factors of cost overrun are fluctuation of prices of material, cash flow and financial difficulties faced by contractors and poor site management and supervision. These factors belong to two categories i.e., contractor's site management and financial management category, thus improvements in these categories are paramount for controlling cost overrun in construction projects.

Overview

The claims and statistics of this paper haven’t been checked yet.

Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.3923/jas.2013.286.293

Cites

2 of 2 references verified0 citation errors · 0 not checkable

Statistics

Verification

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.

A few free checks a day · papers already verified open instantly · results are public

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

Citations

Cites

Cited by

See all 193

Metadata

Authors
Rahman, I. A., Hameed Mem, A., & Abd. Karim, A. T.
Venue
Journal of Applied Sciences
Publisher
Science Alert
Published
2013-01-01
Volume
13
Issue
2
Pages
286-293
ISSN
1812-5654 (ISSN-L)
OpenAlex
W1995540032
Cited by
193
References
2
FWCI
14.96
Type
journal article
Language
en
Open access
bronze

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review

How to cite

Cite CoChat for the checks on this page, and the paper for its own findings.

This page
CoChat. (2026). Citation check: Significant Factors Causing Cost Overruns in Large Construction Projects in Malaysia. https://app.cochat.ai/papers/10.3923/jas.2013.286.293
The paper
Rahman, I. A., Hameed Mem, A., & Abd. Karim, A. T. (2013). Significant Factors Causing Cost Overruns in Large Construction Projects in Malaysia. Journal of Applied Sciences. https://doi.org/10.3923/jas.2013.286.293

Data sources

Bibliographic data: Semantic Scholar, OpenAlex, Crossref.

Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).

Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.