Identification and assessment of risk factors affecting construction projects

Open access
Abd El-Karim, Mohamed Sayed Bassiony Ahmed, Mosa El Nawawy, Omar Aly, Abdel-Alim, Ahmed Mohamed · 2017 · HBRC Journal
Cited by 201

The DOI matches its Crossref record; 4 of the 4 references it cites were found in a registry or an index.

Abstract

Cost saving and time performance are usually essential to all parties who are involved in a construction project, that is owner, contractor, subcontractor. The main causes of disputes in construction projects involve delay and failure to complete the work in the specified cost and time frame. The delivery time of a project is a key factor to the owner in terms of cost as much as it is for the contractor.Unexpected increase in cost and delays in construction projects are caused by owner, contractor, environments, etc. in which several types of risk factors may occur concurrently. The effect of cost overrun and schedule overrun do not only influence the construction industry but the overall economy as well. Even though construction project increasing in cost and schedule has received extensive attention of researchers, but because of continuous changes and development in the field, the study considered of added value to the construction industry in Egypt, in addition to risk strategy and plan analysis. In order to meet the deadline of a project and due to the complex nature of construction projects, cost and scheduling should be flexible enough to accommodate changes without negatively affecting the overall project cost and duration. As such, the objectives of the presented research in this paper are to identify, study, and assess the effect of the factors that affect cost and time contingency. Data are collected from sixteen construction companies in Egypt. The collected data, output charts and analyses spreadsheets will be used for the development of computerized model built by the authors with identification abbreviation RIAM.

Overview

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.1016/j.hbrcj.2015.05.001

Cites

4 of 4 references verified0 citation errors · 0 not checkable

Statistics

Verification

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

Citations

Cites

Show all 4 references

Cited by

See all 201

Metadata

Authors
Abd El-Karim, M. S. B. A., Mosa El Nawawy, O. A., & Abdel-Alim, A. M.
Venue
HBRC Journal
Published
2017-08
Volume
13
Issue
2
Pages
202-216
ISSN
1687-4048 (ISSN-L)
OpenAlex
W648654991
Cited by
201
References
4
FWCI
5.82
Type
journal article
Language
en
Open access
diamond

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review

How to cite

Cite CoChat for the checks on this page, and the paper for its own findings.

This page
CoChat. (2026). Citation check: Identification and assessment of risk factors affecting construction projects. https://app.cochat.ai/papers/10.1016/j.hbrcj.2015.05.001
The paper
Abd El-Karim, M. S. B. A., Mosa El Nawawy, O. A., & Abdel-Alim, A. M. (2017). Identification and assessment of risk factors affecting construction projects. HBRC Journal. https://doi.org/10.1016/j.hbrcj.2015.05.001

Data sources

Bibliographic data: Semantic Scholar, OpenAlex, Crossref.

Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).

Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.