The DOI matches its Crossref record; 8 of the 8 references it cites were found in a registry or an index.
Delays and cost increases in the construction of private residential projects in Kuwait
Abstract
Time‐delays and cost‐increases associated with the construction of private residential projects in the State of Kuwait are determined. A person‐interview survey of 450 randomly selected private residential project owners and developers in 27 representative districts in metropolitan Kuwait formed the database for the study. The socio‐economic traits of the owners/developers, and the pre‐construction family planning, the design, and the construction phases of the sample projects are presented. Estimates of time‐delays and cost‐increases are made, and their causes identified. The three main causes of time‐delays included changing orders, owners' financial constraints and owners' lack of experience in the construction business. Regarding cost overruns, the three main causes were identified as contractor‐related problems, material‐related problems and, again, owners' financial constraints. A number of recommendations end the paper. The minimization of time delays and cost overruns in private residential projects would require: the availability of adequate funds, allocation of sufficient time and money at the design phase, and selection of a competent consultant and a reliable contractor to carry out the work.
Overview
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Journal of Construction Engineering and Management
de la Garza, J., Jahren, C. T., Jaselskis, E. J., Rowings, J. E., & Harris, R. B. (1983) · Cited by 969
The effects of construction delays on project delivery in Nigerian construction industry
Aibinu, A. A., & Jagboro, G. O. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00028-5 · Cited by 597
Causes of Delay in Large Building Construction Projects
Assaf, S. A., Al-Khalil, M., & Al-Hazmi, M. (1995) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(1995)11:2(45 · Cited by 544
Construction delays in a fast-growing economy: Comparing Thailand with other economies
Ogunlana, S. O., Promkuntong, K., & Jearkjirm, V. (1996) · International Journal of Project Management · doi:10.1016/0263-7863(95)00052-6 · Cited by 390
Morris, P. W. G., & Hough, G. (1987) · UCL Discovery (University College London) · Cited by 300
Compressing construction durations: lessons learned from Hong Kong building projects
W.M. Chan, D., & M. Kumaraswamy, M. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00032-6 · Cited by 209
Reasons for delays in public projects in Turkey
Arditi, D., Akan, G. T., & Gurdamar, S. (1985) · Construction Management and Economics · doi:10.1080/01446198500000013 · Cited by 198
Contractor project risks contingency allocation using linguistic approximation
Tah, J. H. M., Thorpe, A., & McCaffer, R. (1993) · Computing Systems in Engineering · doi:10.1016/0956-0521(93)90052-x · Cited by 98
Cited by
Le-Hoai, L., Lee, Y. D., & Lee, J. Y. (2008) · KSCE Journal of Civil Engineering · doi:10.1007/s12205-008-0367-7 · Cited by 560
Delays in construction projects: The case of Jordan
Sweis, G., Sweis, R., Abu Hammad, A., & Shboul, A. (2008) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.09.009 · Cited by 534
Applying lean thinking in construction and performance improvement
Aziz, R. F., & Hafez, S. M. (2013) · Alexandria Engineering Journal · doi:10.1016/j.aej.2013.04.008 · Cited by 513
Olawale, Y. A., & Sun, M. (2010) · Construction Management and Economics · doi:10.1080/01446191003674519 · Cited by 478
Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects
Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2016) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000391 · Cited by 365
Metadata
- Authors
- Koushki, P. A., Al‐Rashid, K., & Kartam, N.
- Venue
- Construction Management and Economics
- Publisher
- Informa UK Limited
- Published
- 2005-03
- Volume
- 23
- Issue
- 3
- Pages
- 285-294
- ISSN
- 0144-6193 (ISSN-L)
- 1466-433X
- OpenAlex
- W2096275307
- Cited by
- 456
- References
- 8
- FWCI
- 12.56
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
How to cite
Cite CoChat for the checks on this page, and the paper for its own findings.
- This page
- CoChat. (2026). Citation check: Delays and cost increases in the construction of private residential projects in Kuwait. https://app.cochat.ai/papers/10.1080/0144619042000326710
- The paper
- Koushki, P. A., Al‐Rashid, K., & Kartam, N. (2005). Delays and cost increases in the construction of private residential projects in Kuwait. Construction Management and Economics. https://doi.org/10.1080/0144619042000326710
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.