Impact of aleatoric, stochastic and epistemic uncertainties on project cost contingency reserves
Open accessAbstract
In construction projects, contingency reserves have traditionally been estimated based on a percentage of the total project cost, which is arbitrary and, thus, unreliable in practical cases. Monte Carlo simulation provides a more reliable estimation. However, works on this topic have focused exclusively on the effects of aleatoric uncertainty, but ignored the impacts of other uncertainty types. In this paper, we present a method to quantitatively determine project cost contingency reserves based on Monte Carlo Simulation that considers the impact of not only aleatoric uncertainty, but also of the effects of other uncertainty kinds (stochastic, epistemic) on the total project cost. The proposed method has been validated with a real-case construction project in Spain. The obtained results demonstrate that the approach will be helpful for construction Project Managers because the obtained cost contingency reserves are consistent with the actual uncertainty type that affects the risks identified in their projects.
Overview
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Claims other papers make about this one
Each is checked against this paper’s own text: does it say what the citing paper says it does?
Probabilistic representations of uncertainty have been successfully employed with uniform distributions to characterise uncertainty when knowledge is sparse or absent.
“Probabilistic representations of uncertainty have been successfully employed with uniform distributions to characterise uncertainty when knowledge is sparse or absent (Curto et al. 2022;Vanhoucke, 2018;Helton et al. 2006).”
From Beyond probability-impact matrices in project risk management: A quantitative methodology for risk prioritisation (2024) · cites this paper as Curto et al. 2022
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
No references could be resolved yet.
Research works printed but not linked: 74
- 2011, Integrated cost and schedule risk analysis using Monte Carlo simulation of a CPM model, AACE International Recommended Practice No. 57R-09
- Acebes, 2014, A new approach for project control under uncertainty. Going back to the basics, Int. J. Proj. Manag., 32, 423, 10.1016/j.ijproman.2013.08.003 · DOI · Paper page
- Acebes, 2015, Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques, Int. J. Proj. Manag., 33, 1597, 10.1016/j.ijproman.2015.06.012 · DOI · Paper page
- Acebes, 2022, Stochastic earned duration analysis for project schedule management, Engineering, 9, 148, 10.1016/j.eng.2021.07.019 · DOI
- Acebes, 2021, On the project risk baseline : integrating aleatory uncertainty into project scheduling, Comput. Ind. Eng., 160
- Afzal, 2020, Cost-risk contingency framework for managing cost overrun in metropolitan projects: using fuzzy-AHP and simulation, Int. J. Manag. Proj. Bus., 13, 1121, 10.1108/IJMPB-07-2019-0175 · DOI
- Ahmad, 1992, Contingency allocation: a computer-aided approach, AACE Transactions, F5, 1
- Akintoye, 1997, Risk analysis and management in construction, Int. J. Proj. Manag., 15, 31, 10.1016/S0263-7863(96)00035-X · DOI
- Alleman, 2018, Increasing the probability of program succes with continuous risk management, Coll. Perf. Manag. Meas. News, 27
- Alleman, 2018, What is Risk?, Meas. News, 1, 25
- Baccarini, 1996, The concept of project complexity - a review, Int. J. Proj. Manag., 14, 201, 10.1016/0263-7863(95)00093-3 · DOI
- Baccarini, 2004, Estimating project cost contingency - a model and exploration of research questions, 20th Ann. ARCOM Conf., 1, 105
- Baccarini, 2014, Statistical characteristics of cost contingency in water infrastructure projects, J. Construct. Eng. Manag., 140, 10.1061/(ASCE)CO.1943-7862.0000820 · DOI
- Bae, 2004, Epistemic uncertainty quantification techniques including evidence theory for large-scale structures, Comput. Struct., 82, 1101, 10.1016/j.compstruc.2004.03.014 · DOI
- Ballesteros-Pérez, 2019, Performance comparison of activity sensitivity metrics in schedule risk analysis, Autom. ConStruct., 106
- Baloi, 2003, Modelling global risk factors affecting construction cost performance, Int. J. Proj. Manag., 21, 261, 10.1016/S0263-7863(02)00017-0 · DOI
- Barraza, 2007, Cost contingency management, J. Manag. Eng., 140
- Bu-Qammaz, 2009, Risk assessment of international construction projects using the analytic network process, Can. J. Civ. Eng., 36, 1170, 10.1139/L09-061 · DOI
- Cagliano, 2015, Choosing project risk management techniques. A theoretical framework, J. Risk Res., 18, 232, 10.1080/13669877.2014.896398 · DOI
- Chang, 2017, New approach to estimating the standard deviations of lognormal cost variables in the Monte Carlo analysis of construction risks, J. Construct. Eng. Manag., 143, 10.1061/(ASCE)CO.1943-7862.0001207 · DOI
- Chapman, 2004, Why risk efficiency is a key aspect of best practice projects, Int. J. Proj. Manag., 22, 619, 10.1016/j.ijproman.2004.05.001 · DOI
- Clark, 2001, Monte Carlo analysis: ten years of experience, Cost Eng., 43, 40
- Colin, 2016, Empirical perspective on activity durations for project-management simulation studies, J. Construct. Eng. Manag., 142, 10.1061/(ASCE)CO.1943-7862.0001022 · DOI
- Diab, 2017, Modeling the construction risk ratings to estimate the contingency in highway projects, J. Construct. Eng. Manag., 143, 10.1061/(ASCE)CO.1943-7862.0001334 · DOI
- Duijm, 2015, Recommendations on the use and design of risk matrices, Saf. Sci., 76, 21, 10.1016/j.ssci.2015.02.014 · DOI · Paper page
- El-Kholy, 2020, Prediction of simulated cost contingency for steel reinforcement in building projects: ANN versus regression-based models, Int. J. Construct. Manag., 1
- El-Matbaegy, 2017, Risk analysis of construction sector in Egypt (during the economic recession periods), Port-Said Eng. Res. J., 21, 37, 10.21608/pserj.2017.33231 · DOI
- El-Sayegh, 2008, Risk assessment and allocation in the UAE construction industry, Int. J. Proj. Manag., 26, 431, 10.1016/j.ijproman.2007.07.004 · DOI · Paper page
- Eldosouky, 2014, Management of construction cost contingency covering upside and downside risks, Alex. Eng. J., 53, 863, 10.1016/j.aej.2014.09.008 · DOI
- Elms, 2004, Structural safety: issues and progress, Prog. Struct. Eng. Mater., 6, 116, 10.1002/pse.176 · DOI
- Fan, 2008, Choosing a project risk-handling strategy: an analytical model, Int. J. Prod. Econ., 112, 700, 10.1016/j.ijpe.2007.06.006 · DOI
- Frank, 1999, Treatment of uncertainties in space nuclear risk assessment with examples from Cassini mission implications, Reliab. Eng. Syst. Saf., 66, 203, 10.1016/S0951-8320(99)00002-2 · DOI
- Gosling, 2013, Identifying and categorizing the sources of uncertainty in construction supply chains, J. Construct. Eng. Manag., 139, 102, 10.1061/(ASCE)CO.1943-7862.0000574 · DOI
- Hammad, 2015, A new method of cost contingency management, IEEE Int. Conf. Ind. Eng. Eng. Manag., 38
- Hammad, 2016, Allocation and management of cost contingency in projects, J. Manag. Eng., 32, 1
- Han, 2001, Approaches for making risk-based go/no-go decision for international projects, J. Construct. Eng. Manag., 127, 300, 10.1061/(ASCE)0733-9364(2001)127:4(300) · DOI
- Helton, 2006, Sensitivity analysis in conjunction with evidence theory representations of epistemic uncertainty, Reliab. Eng. Syst. Saf., 91, 1414, 10.1016/j.ress.2005.11.055 · DOI · Paper page
- Hillson, 2005, vol. 1
- Hillson, 2014, How to manage the risks you didn't know you were taking, PMI® Glob. Congr., 1
- Hong, 2016, Uncertainty analysis for measuring greenhouse gas emissions in the building construction phase: a case study in China, J. Clean. Prod., 129, 183, 10.1016/j.jclepro.2016.04.085 · DOI
- Hoseini, 2020, Cost contingency and cost evolvement of construction projects in the preconstruction phase, J. Construct. Eng. Manag., 146, 10.1061/(ASCE)CO.1943-7862.0001842 · DOI
- Hosny, 2018, Risk management framework for Continuous Flight Auger piles construction in Egypt, Alex. Eng. J., 57, 2667, 10.1016/j.aej.2017.10.003 · DOI
- Idrus, 2011, Development of project cost contingency estimation model using risk analysis and fuzzy expert system, Expert Syst. Appl., 38, 1501, 10.1016/j.eswa.2010.07.061 · DOI
- Islam, 2021, Risk induced contingency cost modeling for power plant projects, Autom. ConStruct., 123
- Jung, 2015, The computer-based contingency estimation through analysis cost overrun risk of public construction project, KSCE J. Civ. Eng., 20, 1119, 10.1007/s12205-015-0184-8 · DOI
- Kwon, 2019, Improving project budget estimation accuracy and precision by analyzing reserves for both identified and unidentified risks, Proj. Manag. J., 50, 86, 10.1177/8756972818810963 · DOI · Paper page
- Lam, 2017, Risk management and contingency sum of construction projects, J. Finance Manag. Prop. Construct., 22, 237
- Lee, 2017, Management-reserve estimation for international construction projects based on risk-informed k-NN, J. Manag. Eng., 33
- Lhee, 2012, Prediction of financial contingency for asphalt resurfacing projects using artificial neural networks, J. Construct. Eng. Manag., 138, 22, 10.1061/(ASCE)CO.1943-7862.0000408 · DOI
- Liu, 2017, Improving risk assessment in financial feasibility of international engineering projects: a risk driver perspective, Int. J. Proj. Manag., 35, 204, 10.1016/j.ijproman.2016.11.004 · DOI
- Long, 2008, Fuzzy critical chain method for project scheduling under resource constraints and uncertainty, Int. J. Proj. Manag., 26, 688, 10.1016/j.ijproman.2007.09.012 · DOI
- Lorance, 2001, Basic techniques for analyzing and presentation of cost risk analysis, Cost Eng., 43, 25
- Mahendra, 2013, A study of risk management techniques for construction projects in developing countries, Int. J. Innovative Technol. Explor. Eng., 3, 139
- Mak, 2000, Using risk analisys to determine construction project contingencies, J. Construct. Eng. Manag., 126, 130, 10.1061/(ASCE)0733-9364(2000)126:2(130) · DOI
- Maronati, 2019, Estimating cost uncertainties in nuclear power plant construction through Monte Carlo sampled correlated random variables, Prog. Nucl. Energy, 111, 211, 10.1016/j.pnucene.2018.11.011 · DOI
- Mohamed, 2020, Simulation-based approach for risk assessment in onshore wind farm construction projects. 2020 Asia-Pacific International Symposium on Advanced Reliability and Maintenance Modeling, APARM, 2020
- Moreno-Cabezali, 2020, Application of a fuzzy-logic based model for risk assessment in additive manufacturing R&D projects, Comput. Ind. Eng., 145
- Moret, 2016, Construction cost and duration uncertainty model: application to high-speed rail line project, J. Construct. Eng. Manag., 142, 10.1061/(ASCE)CO.1943-7862.0001161 · DOI
- Moselhi, 1997, Risk assessment and contingency estimating, AACE Int. Trans., 90, 1
- Para-González, 2018, Obtaining the budget contingency reserve through the Monte Carlo method: study of a ferry construction project, Brodogradnja, 69, 79, 10.21278/brod69305 · DOI
- Salah, 2015, Contingency modelling for construction projects using fuzzy-set theory, Eng. Construct. Architect. Manag., 22, 214, 10.1108/ECAM-03-2014-0039 · DOI
- Seyedhoseini, 2009, An integrated methodology for assessment and selection of the project risk response actions, Risk Anal., 29, 752, 10.1111/j.1539-6924.2008.01187.x · DOI
- Shahtaheri, 2017, Applying very large scale integration reliability theory for understanding the impacts of type II risks on megaprojects, J. Manag. Eng., 33
- Sonmez, 2007, Quantitative methodology for determination of cost, J. Manag. Eng., 23, 35
- Thal, 2010, Estimation of cost contingency for air force construction projects, J. Construct. Eng. Manag., 136, 1181, 10.1061/(ASCE)CO.1943-7862.0000227 · DOI
- Touran, 2003, Probabilistic model for cost contingency, J. Construct. Eng. Manag., 129, 280, 10.1061/(ASCE)0733-9364(2003)129:3(280) · DOI
- Traynor, 2019, Time and cost contingency management using Monte Carlo simulation, Aust. J. Civ. Eng., 17, 11, 10.1080/14488353.2019.1606499 · DOI · Paper page
- Trietsch, 2012, Modeling activity times by the Parkinson distribution with a lognormal core: theory and validation, Eur. J. Oper. Res., 216, 386, 10.1016/j.ejor.2011.07.054 · DOI
- Uzzafer, 2013, A contingency estimation model for software projects, Int. J. Proj. Manag., 31, 981, 10.1016/j.ijproman.2012.12.002 · DOI
- Van, 2019, Predicting implementation cost contingencies for residential construction projects in flood-prone areas, Int. J. Manag. Proj. Bus., 12, 1097, 10.1108/IJMPB-04-2018-0071 · DOI
- Vasvári, 2015, Risk, risk perception, risk management - a review of the literature, Publ. Finance Quart., 60, 29
- Zhang, 2014, An optimization method for selecting project risk response strategies, Int. J. Proj. Manag., 32, 412, 10.1016/j.ijproman.2013.06.006 · DOI
- Zhi, 1995, Risk management for overseas construction projects, Int. J. Proj. Manag., 13, 231, 10.1016/0263-7863(95)00015-I · DOI
- Zou, 2010, Understanding and improving your risk management capability : assessment model for construction organizations, J. Construct. Eng. Manag., 136, 854, 10.1061/(ASCE)CO.1943-7862.0000175 · DOI
Cited by
Sorted by citations
Acebes, F., González-Varona, J. M., López-Paredes, A., & Pajares, J. (2024) · Humanities and Social Sciences Communications · doi:10.1057/s41599-024-03180-5 · Cited by 74
Self-citation
Metadata
- Authors
- Curto, D., Acebes, F., González-Varona, J. M., & Poza, D.
- Affiliations
- Universidad de Valladolid (ES)
- Corresponding author
- Acebes, F.
- Venue
- International Journal of Production Economics
- Publisher
- Elsevier BV
- Published
- 2022-11
- Volume
- 253
- Pages
- 108626
- ISSN
- 0925-5273 (ISSN-L)
- OpenAlex
- W4293331463
- Cited by
- 47
- References
- 0
- Citations by year
- 2026: 20 · 2025: 13 · 2024: 8 · 2023: 6
- FWCI
- 3.57
- Type
- journal article
- Language
- en
- Open access
- hybrid
- doi.org
- Licence
- Locations
- International Journal of Production Economics (publishedVersion, cc-by-nc-nd)
- Hispana (publishedVersion, cc-by-nc-nd)
- RePEc: Research Papers in Economics (submittedVersion)
- arXiv (Cornell University) (submittedVersion, cc-by-nc-nd)
- Repositorio Institucional de la Universidad de Málaga (University of Málaga) (submittedVersion, cc-by-nc-nd)
- UVaDOC UVaDOC University of Valladolid Documentary Repository (University of Valladolid) (submittedVersion, cc-by-nc-nd)
- arXiv (Cornell University)
- Funders
- Junta de Castilla y León (VA180P20)
- Topics
- Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
- Social Sciences › Economics, Econometrics and Finance › Finance › Capital Investment and Risk Analysis
- Physical Sciences › Engineering › Building and Construction › BIM and Construction Integration
- Keywords
- aleatoric uncertainty, epistemic uncertainty, construction risk, cost estimation, uncertainty quantification, construction project management
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review