Causes of Delay in Building Construction Projects in Egypt

Abd El-Razek, M. E., Bassioni, H. A., Mobarak, A. M. · 2008 · Journal of Construction Engineering and Management
DOI 10.1061/(asce)0733-9364(2008)134:11(831

Abstract

Delay in construction projects is considered one of the most common problems causing a multitude of negative effects on the project and its participating parties. This paper aims to identify the main causes of delay in construction projects in Egypt from the point of view of contractors, consultants, and owners. A literature review was conducted to compile a list of delay causes that was purged based on appropriateness to Egypt in seven semistructured interviews. The resulting list of delay causes was subjected to a questionnaire survey for quantitative confirmation and identification of the most important causes of delay. The overall results indicated that the most important causes are: financing by contractor during construction, delays in contractor’s payment by owner, design changes by owner or his agent during construction, partial payments during construction, and nonutilization of professional construction/contractual management. The contractor and owner were found to have opposing views, mostly blaming one another for delays, while the consultant was seen as having a more intermediate view. Results’ analyses suggest that in order to significantly reduce delay a joint effort based on teamwork is required. Furthermore, causes of project delay were discussed based on the type and size of the project.

Overview

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.1061/(asce)0733-9364(2008)134:11(831)

Cites

6 of 6 references verified0 citation errors · 0 not checkable

Statistics

Verification

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

Citations

Cites

Show all 6 references

Cited by

See all 463

Metadata

Authors
Abd El-Razek, M. E., Bassioni, H. A., & Mobarak, A. M.
Venue
Journal of Construction Engineering and Management
Published
2008-11
Volume
134
Issue
11
Pages
831-841
ISSN
  • 0733-9364 (ISSN-L)
  • 1943-7862
DOI
10.1061/(asce)0733-9364(2008)134:11(831
OpenAlex
W1976508356
Cited by
463
References
6
FWCI
4.10
Type
journal article
Language
en
Open access
closed

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review

How to cite

Cite CoChat for the checks on this page, and the paper for its own findings.

This page
CoChat. (2026). Citation check: Causes of Delay in Building Construction Projects in Egypt. https://app.cochat.ai/papers/10.1061/(asce)0733-9364(2008)134:11(831
The paper
Abd El-Razek, M. E., Bassioni, H. A., & Mobarak, A. M. (2008). Causes of Delay in Building Construction Projects in Egypt. Journal of Construction Engineering and Management. https://doi.org/10.1061/(asce)0733-9364(2008)134%3A11(831

Data sources

Bibliographic data: Semantic Scholar, OpenAlex, Crossref.

Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).

Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.