Causes of Delay in Building Construction Projects in Egypt
Abstract
Delay in construction projects is considered one of the most common problems causing a multitude of negative effects on the project and its participating parties. This paper aims to identify the main causes of delay in construction projects in Egypt from the point of view of contractors, consultants, and owners. A literature review was conducted to compile a list of delay causes that was purged based on appropriateness to Egypt in seven semistructured interviews. The resulting list of delay causes was subjected to a questionnaire survey for quantitative confirmation and identification of the most important causes of delay. The overall results indicated that the most important causes are: financing by contractor during construction, delays in contractor’s payment by owner, design changes by owner or his agent during construction, partial payments during construction, and nonutilization of professional construction/contractual management. The contractor and owner were found to have opposing views, mostly blaming one another for delays, while the consultant was seen as having a more intermediate view. Results’ analyses suggest that in order to significantly reduce delay a joint effort based on teamwork is required. Furthermore, causes of project delay were discussed based on the type and size of the project.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
How Many Interviews Are Enough?: An Experiment with Data Saturation and Variability
Guest, G., Bunce, A., & Johnson, L. (2006) · Field Methods · doi:10.1177/1525822x05279903 · Cited by 20,808
Causes of delay in large construction projects
Assaf, S. A., & Al-Hejji, S. (2006) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.11.010 · Cited by 1,705
Causes of Delay in Large Building Construction Projects
Assaf, S. A., Al-Khalil, M., & Al-Hazmi, M. (1995) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(1995)11:2(45 · Cited by 544
Causes of delay and cost overruns in Nigerian construction projects
Mansfield, N., Ugwu, O., & Doran, T. (1994) · International Journal of Project Management · doi:10.1016/0263-7863(94)90050-7 · Cited by 457
Delay Mitigation in the Malaysian Construction Industry
Abdul‐Rahman, H., Berawi, M. A., Berawi, A. R. B., Mohamed, O., Othman, M., & Yahya, I. A. (2006) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2006)132:2(125 · Cited by 256
Causes of Delay in the Construction Industry
Baldwin, J. R., Manthei, J. M., Rothbart, H. A., & Harris, R. B. (1971) · Journal of the Construction Division · doi:10.1061/jcceaz.0000305 · Cited by 118
Cited by
Analysing factors affecting delays in Indian construction projects
Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012) · International Journal of Project Management · doi:10.1016/j.ijproman.2011.10.004 · Cited by 745
Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects
Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2016) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000391 · Cited by 365
Machine learning algorithms for construction projects delay risk prediction
Gondia, A., Siam, A., El-Dakhakhni, W., & Nassar, A. H. (2020) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001736 · Cited by 327
Construction delays in privately funded large building projects in Bangladesh
Islam, M. S., & Suhariadi, B. T. (2018) · Asian Journal of Civil Engineering · doi:10.1007/s42107-018-0034-3 · Cited by 44
Metadata
- Authors
- Abd El-Razek, M. E., Bassioni, H. A., & Mobarak, A. M.
- Venue
- Journal of Construction Engineering and Management
- Published
- 2008-11
- Volume
- 134
- Issue
- 11
- Pages
- 831-841
- ISSN
- 0733-9364 (ISSN-L)
- 1943-7862
- DOI
- 10.1061/(asce)0733-9364(2008)134:11(831
- OpenAlex
- W1976508356
- Cited by
- 463
- References
- 6
- FWCI
- 4.10
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
How to cite
Cite CoChat for the checks on this page, and the paper for its own findings.
- This page
- CoChat. (2026). Citation check: Causes of Delay in Building Construction Projects in Egypt. https://app.cochat.ai/papers/10.1061/(asce)0733-9364(2008)134:11(831
- The paper
- Abd El-Razek, M. E., Bassioni, H. A., & Mobarak, A. M. (2008). Causes of Delay in Building Construction Projects in Egypt. Journal of Construction Engineering and Management. https://doi.org/10.1061/(asce)0733-9364(2008)134%3A11(831
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.