Cost Overruns and Failure in Project Management: Understanding the Roles of Key Stakeholders in Construction Projects
The DOI matches its Crossref record; 16 of the 16 references it cites were found in a registry or an index.
Abstract
The subject of poor cost performance has been widely published in the mainstream project and construction management literature. Nevertheless, the underlying responsibilities of the key stakeholders (clients, consultants, and contractors) in managing this chronic problem in the Australian construction industry remain unclear. By performing an in-depth analysis of the roles and responsibilities of these key stakeholders, this research is intended to unfold the industrywide perception of cost performance being heavily reliant on the contractor’s performance alone. Based on a thorough literature review and relevant industry inputs, 73 attributes associated with cost performance were identified for investigation. Based on the relative importance weighing technique on 48 selected attributes, planning and scheduling deficiencies have the highest impact on cost performance from clients, consultants, and contractors’ perspectives. Confirmatory factor analysis on the combined responses across all three groups suggests that robust control procedures and adequate programming, along with efficient design and effective site management, are the most critical factors. These factors are primarily associated with the responsibilities of contractors and consultants for managing cost overruns in projects. However, the client’s responsibility in facilitating effective management of these factors within the project environment is crucial. Multivariate regression analysis performed on eight factors’ scores highlighted the influence of five significant factors (p<5%) on managing cost overruns. The findings are expected to abridge a significant knowledge gap by shifting the priorities in cost estimation and management practices across all industry sectors.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Discovering Statistics Using SPSS
Field, A. P., & Miles, J. N. V. (2000) · Medical Entomology and Zoology · Cited by 28,294
A comparative study of causes of time overruns in Hong Kong construction projects
Chan, D. W., & Kumaraswamy, M. M. (1997) · International Journal of Project Management · doi:10.1016/s0263-7863(96)00039-7 · Cited by 831
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00055-8 · Cited by 796
Analysing factors affecting delays in Indian construction projects
Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012) · International Journal of Project Management · doi:10.1016/j.ijproman.2011.10.004 · Cited by 745
Self-citationAnalysis of factors influencing project cost estimating practice
Akintoye, A. (2000) · Construction Management and Economics · doi:10.1080/014461900370979 · Cited by 608
Modelling global risk factors affecting construction cost performance
Baloi, D., & Price, A. D. F. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00017-0 · Cited by 587
Factors affecting cost performance: evidence from Indian construction projects
Iyer, K. C., & Jha, K. N. (2005) · International Journal of Project Management · doi:10.1016/j.ijproman.2004.10.003 · Cited by 504
Causes of delay and cost overruns in Nigerian construction projects
Mansfield, N., Ugwu, O., & Doran, T. (1994) · International Journal of Project Management · doi:10.1016/0263-7863(94)90050-7 · Cited by 457
Delays and cost overruns in the construction projects in the Gaza Strip
Enshassi, A., Al‐Najjar, J., & Kumaraswamy, M. (2009) · Journal of Financial Management of Property and Construction · doi:10.1108/13664380910977592 · Cited by 278
Motivation, commitment and the use of incentives in partnerships and alliances
Bresnen, M., & Marshall, N. (2000) · Construction Management and Economics · doi:10.1080/014461900407392 · Cited by 266
Analysis of pre‐qualification criteria in contractor selection and their impacts on project success
Doloi, H. (2009) · Construction Management and Economics · doi:10.1080/01446190903394541 · Cited by 170
Self-citationFactors Affecting Contractors' Risk of Cost Overburden
Akinci, B., & Fischer, M. A. (1998) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(1998)14:1(67 · Cited by 155
A survey of indirect cost estimating in practice
Tah, J. H. M., Thorpe, A., & McCaffer, R. (1994) · Construction Management and Economics · doi:10.1080/01446199400000004 · Cited by 79
The coefficient of concordance for vague data
Grzegorzewski, P. (2006) · Computational Statistics & Data Analysis · doi:10.1016/j.csda.2006.04.027 · Cited by 39
Fortune, C. (2006) · Construction Management and Economics · doi:10.1080/01446190600851116 · Cited by 16
A study of clients' and estimators' tolerance towards estimating errors
Cheung, F. K. T., Wong, M., & Skitmore, M. (2008) · Construction Management and Economics · doi:10.1080/01446190701802380 · Cited by 13
Cited by
Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects
Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2016) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000391 · Cited by 365
Cost overrun in the Malaysian construction industry projects: A deeper insight
Shehu, Z., Endut, I. R., Akintoye, A., & Holt, G. D. (2014) · International Journal of Project Management · doi:10.1016/j.ijproman.2014.04.004 · Cited by 210
“, 2013) and the significance of this, has attracted much research over recent decades (Arditi et al., 1985; Creedy, 2004; Dawood, 1998; Dlakwa and Culpin, 1990; Doloi, 2013; Frimpong et al., 2003; Kaming et al., 1997; Koushki et al., 2005; Mansfield et al., 1994).”
BackgroundParsamehr, M., Perera, U. S., Dodanwala, T. C., Perera, P., & Ruparathna, R. (2023) · Asian Journal of Civil Engineering · doi:10.1007/s42107-022-00501-4 · Cited by 193
“The key bottom lines of the AEC industry are schedule, cost, quality, and safety considerations, which is a particularly accurate assumption in the context of construction project management (Doloi, 2013; Khademi, 2014; Memon et al., 2011).”
BackgroundKwon, H., & Kang, C. W. (2019) · Project Management Journal · doi:10.1177/8756972818810963 · Cited by 50
“However, in reality, project cost overruns and scope creep are normal phenomena in infrastructure and construction projects carried out in both developed and developing countries (Bhargava, Anastrasopoulous, Labi, Shiha, & Mannering, 2010; Doloi, 2013; Enshassi, Al-Najjar, & Kumaraswamy, 2009; Frimpong, Oluwoye, & Cra…”
Background
Metadata
- Authors
- Doloi, H.
- Venue
- Journal of Construction Engineering and Management
- Published
- 2013-03
- Volume
- 139
- Issue
- 3
- Pages
- 267-279
- ISSN
- 0733-9364 (ISSN-L)
- 1943-7862
- OpenAlex
- W2150536746
- Cited by
- 325
- References
- 16
- FWCI
- 11.54
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.