Machine Learning Algorithms for Construction Projects Delay Risk Prediction
The DOI matches its Crossref record; 62 of the 62 references it cites were found in a registry or an index.
Abstract
Projects delays are among the most pressing challenges faced by the construction sector attributed to the sector’s complexity and its inherent delay risk sources’ interdependence. Machine learning offers an ideal set of techniques capable of tackling such complex systems; however, adopting such techniques within the construction sector remains at an early stage. The goal of this study was to identify and develop machine learning models in order to facilitate accurate project delay risk analysis and prediction using objective data sources. As such, relevant delay risk sources and factors were first identified, and a multivariate data set of previous projects’ time performance and delay-inducing risk sources was then compiled. Subsequently, the complexity and interdependence of the system was uncovered through an exploratory data analysis. Accordingly, two suitable machine learning models, utilizing decision tree and naïve Bayesian classification algorithms, were identified and trained using the data set for predicting project delay extents. Finally, the predictive performances of both models were evaluated through cross validation tests, and the models were further compared using machine-learning-relevant performance indices. The evaluation results indicated that the naïve Bayesian model provides a better predictive performance for the data set examined. Ultimately, the work presented herein harnesses the power of machine learning to facilitate evidence-based decision making, while inherent risk factors are active, interdependent, and dynamic, thus empowering proactive project risk management strategies.
Overview
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
Claims other papers make about this one
Each is checked against this paper’s own text: does it say what the citing paper says it does?
In the citing paper
“Gondia et al. [22] proved that ML-based approaches are superior in predicting construction projects' delay risk over statistical learning.”
From Cost Overrun Risk Assessment and Prediction in Construction Projects: A Bayesian Network Classifier Approach (2022) · cites this paper as [22]
In the citing paper
“The present study considered a 10-fold CV because numerous studies have indicated that this is the optimal value for computational time, error estimation, and indices variance [22].”
From Cost Overrun Risk Assessment and Prediction in Construction Projects: A Bayesian Network Classifier Approach (2022) · cites this paper as [22]
In the citing paper
“| Gondia et al. [22] | NB | Accuracy: 78.4% |”
From Cost Overrun Risk Assessment and Prediction in Construction Projects: A Bayesian Network Classifier Approach (2022) · cites this paper as [22]
In the citing paper
“For instance, in a Gondia et al. [22] study, the best ML model was the NB, which had a 51.2% accuracy rate.”
From Cost Overrun Risk Assessment and Prediction in Construction Projects: A Bayesian Network Classifier Approach (2022) · cites this paper as Gondia et al. [22]
Citations
Cites
The Elements of Statistical Learning
Hastie, T., Tibshirani, R., & Friedman, J. (2009) · Springer Series in Statistics · doi:10.1007/978-0-387-84858-7 · Cited by 25,970
A Study of Cross-Validation and Bootstrap for Accuracy Estimation and Model Selection
Kohavi, R. (1995) · Zenodo · doi:10.5281/zenodo.19712698 · Cited by 10,909
Advances in Neural Information Processing Systems 14: Proceedings of the 2001 Conference
(2002) · The MIT Press eBooks · doi:10.7551/mitpress/1120.001.0001 · Cited by 8,890
Statistical Modeling: The Two Cultures (with comments and a rejoinder by the author)
Breiman, L. (2001) · Statistical Science · doi:10.1214/ss/1009213726 · Cited by 4,340
A Guide to the project management body of knowledge
(1996) · Choice Reviews Online · doi:10.5860/choice.34-1636 · Cited by 4,339
A survey of cross-validation procedures for model selection
Arlot, S., & Célisse, A. (2010) · LillOA (Université de Lille (University Of Lille)) · Cited by 3,662
A survey of cross-validation procedures for model selection
Arlot, S., & Celisse, A. (2010) · Statistics Surveys · doi:10.1214/09-ss054 · Cited by 3,522
Project management: A systems approach to planning, scheduling and controlling
Botter, C. H. (1982) · European Journal of Operational Research · doi:10.1016/0377-2217(82)90164-3 · Cited by 2,408
Causes of delay in large construction projects
Assaf, S. A., & Al-Hejji, S. (2006) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.11.010 · Cited by 1,705
Causes and effects of delays in Malaysian construction industry
Sambasivan, M., & Soon, Y. W. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.11.007 · Cited by 1,422
Research works printed but not linked: 3
- Ismail I., 2014, Expert opinion on risk level for factors affecting time and cost overrun along the project lifecycle in Malaysian construction projects, Int. J. Constr. Technol. Manage., 1, 10
- Ng A. Y., 2002, Advances in neural information processing systems, 841
- R Core Team, 2013, A language and environment for statistical computing
Cited by
Items 201–300 of 374
Artificial Intelligence Application for Risk Template Generation in Major Transportation Projects
Erfani, A., Villeda, V. H., & Cui, Q. (2022) · ASCE Construction Research Congress (CRC) · doi:10.1061/9780784483961.003 · Cited by 5
Incorporating Emerging Technologies in the Forensic Analysis of Construction Project Delays
Boyacioglu, S. E., Greenwood, D. J., & Rogage, K. (2022) · IOP Conference Series Earth and Environmental Science · doi:10.1088/1755-1315/1101/5/052029 · Cited by 5
“…was examined [57]; ML models were developed to facilitate accurate project delay risk analysis and prediction, and evidence-based decision making [58]; a hybrid architecture (where AI is teamed with human experts) was introduced for forensic evidence examination [59]; a two-layered fuzzy…”
BackgroundMethodMachine Learning-Based Construction Planning and Forecasting Model
Keser, A. E., & Tokdemir, O. B. (2023) · Proceedings e report · doi:10.36253/10.36253/979-12-215-0289-3.71 · Cited by 5
Omoboye, O., Sofolahan, O., Awodele, I. A., Eze, E. C., & Loya, S. O. (2024) · ITEGAM- Journal of Engineering and Technology for Industrial Applications (ITEGAM-JETIA) · doi:10.5935/jetia.v10i47.1072 · Cited by 4
Sun, J., Murphy, M. R., Hazlett, D., Shuai, C., & Gao, L. (2025) · Journal of Construction Engineering and Management · doi:10.1061/jcemd4.coeng-16088 · Cited by 4
Tedjo, C., Berawi, M. A., & Sari, M. (2022) · Lecture notes in civil engineering · doi:10.1007/978-981-16-9348-9_74 · Cited by 4
The Energy Contents of Broken Rice for Lactating Dairy Cows
Gunha, T., Kongphitee, K., Binsulong, B., & Sommart, K. (2023) · Animals · doi:10.3390/ani13193042 · Cited by 6
Nguyen, V. T., Do, S. T., Tran, C. N. N., & Aung, Z. M. (2024) · International Journal of Construction Management · doi:10.1080/15623599.2024.2304389 · Cited by 5
“Gondia et al. (2020) also employed machine learning to anticipate construction project delays.”
Aziz, Z., & Nenzhelele, T. E. (2026) · International Journal of Applied Research in Business and Management · doi:10.51137/wrp.ijarbm.629 · Cited by 3
Yazdanian, M., Esfahani, M. M., Sheikhkhoshkar, M., & Khanzadi, M. (2024) · International Journal of Engineering · doi:10.5829/ije.2024.37.12c.10 · Cited by 3
Assessment of Factors Causing Construction Delays in Building Construction Projects in Somaliland
Duale, A. Y., Hareru, W. K., Ghebrab, T., Mulugeta, S., & Gedefaye, T. (2025) · Advances in Civil Engineering · doi:10.1155/adce/7915818 · Cited by 3
Predicting schedule delays of construction projects in the oil and gas industry: comparative study
Mohammed, A., Bahatheq, A., Ghaithan, A. M., Alshibani, A., Mazher, K. M., & Alrashidi, A. (2025) · Built Environment Project and Asset Management · doi:10.1108/bepam-12-2024-0286 · Cited by 3
Erfani, A., & Naghdi, M. (2026) · Advanced Engineering Informatics · doi:10.1016/j.aei.2026.104543 · Cited by 3
Multistage assessment of construction delay factors using expert evaluation and real project data
Eid, A., Halabya, A., Nagy, N. M., & Hassan, A. A. (2026) · Scientific Reports · doi:10.1038/s41598-026-53262-4 · Cited by 3
Advancing project success prediction through machine learning-driven models
Ojiako, U., Iqbal, M., Dacre, N., Baxter, D., Dong, H., Qazi, A. J., Chipulu, M., & Al-Mhdawi, M. K. S. (2026) · Production Planning & Control · doi:10.1080/09537287.2026.2676289 · Cited by 3
Park, C. Y., & Yun, S. (2024) · Journal of Management in Engineering · doi:10.1061/jmenea.meeng-6017 · Cited by 3
Hicham, R., Abdallah, L., & Mohamed, M. (2024) · Eng—Advances in Engineering · doi:10.3390/eng5030071 · Cited by 3
Pourdoustmohammadi, S., & Ansari, R. (2024) · Iranian Journal of Science and Technology Transactions of Civil Engineering · doi:10.1007/s40996-024-01590-8 · Cited by 3
Phishing Attack Response and Risk Mitigation Using Deep Learning and Machine Learning
Bhimavarapu, U. (2025) · IGI Global eBooks · doi:10.4018/979-8-3693-8784-9.ch006 · Cited by 3
Mohamedein, S. M., & Nassar, A. H. (2025) · International Journal of Construction Management · doi:10.1080/15623599.2025.2567747 · Cited by 3
“Conversely, a low contingency can result in insufficient funds for project execution, an unrealistic financial climate, and unsatisfactory performance outcomes (Gondia et al. 2020).”
Self-citationTechnology Trends and Digital Transformation in Construction
Halder, S. (2025) · Springer eBooks · doi:10.1007/978-981-96-7631-6_25 · Cited by 3
Construction Productivity Analysis in Construction Industry: An Indian Perspective
Katyare, P., & Joshi, S. S. (2022) · Algorithms for intelligent systems · doi:10.1007/978-981-19-0863-7_11 · Cited by 3
Aydın, Y., Bekdaş, G., Nigdeli, S. M., Işıkdağ, Ü., & Geem, Z. W. (2023) · Studies in systems, decision and control · doi:10.1007/978-3-031-34728-3_12 · Cited by 4
Artificial Intelligence Engineering for Predictive Analytics
Issaro, S., Nilsook, P., & Wannapiroon, P. (2023) · Research, Invention, and Innovation Congress: Innovative Electricals and Electronics (RI2C) · doi:10.1109/ri2c60382.2023.10355979 · Cited by 3
Improving Culvert Condition Prediction Models Using Federated Learning: The Case Study of Utah
Mohammadi, P., Rashidi, A., & Asgari, S. (2024) · ASCE Construction Research Congress (CRC) · doi:10.1061/9780784485262.037 · Cited by 3
Omole, O., & Ghosh, S. (2024) · International Journal of Construction Education and Research · doi:10.1080/15578771.2024.2333402 · Cited by 3
“These findings are supported by several existing studies (Florez ‐ Perez et al., 2022; Gondia et al., 2020; Karatas & Budak, 2022; Mahdavian et al., 2021; Momade et al., 2022; Sadatnya et al., 2023; Shoar et al., 2022; Williams & Gong, 2014).”
AHP Approach for Risk Factors Prioritisation in Tunnel Construction
Band, P., Shelake, A. G., & Gogate, N. G. (2024) · Lecture notes in civil engineering · doi:10.1007/978-981-99-9610-0_16 · Cited by 3
Ayat, M., Ullah, M., Pervez, Z., Lawrence, J., Kang, C. W., & Ullah, A. (2024) · Engineering Construction & Architectural Management · doi:10.1108/ecam-01-2024-0134 · Cited by 3
Ranković, N., Ranković, D., Ivanović, M. D., & Lazić, L. (2024) · Artificial intelligence-enhanced software and systems engineering · doi:10.1007/978-3-031-76572-8_5 · Cited by 3
Wu, Q., Xue, M., & Lu, B. (2025) · Journal of Current Social Issues Studies · doi:10.71113/jcsis.v2i5.263 · Cited by 4
“Key applications include: 1 . Predictive Analytics: AI algorithms analyze historical project data to forecast potential risks, cost overruns, and schedule delays (F. Afzal et al., 2019; Gondia et al., 2020).”
Ghodsi, V. B., & Dadashzadeh, N. (2025) · Sustainable Cities and Society · doi:10.1016/j.scs.2025.106801 · Cited by 3
Identifying cyber risk factors associated with construction projects
Yao, D., de Soto, B. G., & Wilkes, M. (2025) · Journal of Civil Engineering and Management · doi:10.3846/jcem.2025.25213 · Cited by 3
Highway Project Clustering Using Unsupervised Machine Learning Approach
Alikhani, H., & Jeong, H. D. (2022) · ASCE International Conference on Computing in Civil Engineering (i3CE) · doi:10.1061/9780784483893.022 · Cited by 4
Multi-Factor superposition influence analysis in engineering projects: a Bayesian network approach
Zhang, C., Hu, K., & Liu, X. (2025) · Journal of Asian Architecture and Building Engineering · doi:10.1080/13467581.2025.2513064 · Cited by 2
“In the research of Gondia et al. (Gondia et al. 2020), two suitable machine learning models, utilizing decision tree and Naive Bayesian Classification Algorithms(NBCA), were identified and trained using the data set for predicting project delay extents.”
Conflicts and optimization of multiple promotions combinations for merchants
Huang, R., Zhang, Z., Lv, B., & Zhao, H. (2025) · Expert Systems with Applications · doi:10.1016/j.eswa.2025.128455 · Cited by 2
Kamil, B. A. (2025) · Engineering Technology & Applied Science Research · doi:10.48084/etasr.13781 · Cited by 4
“This is particularly evident in Iraq, where bureaucracy and lack of funding and supply lines still hinder timely project implementation [15].”
Duan, B., Ding, Y., Lu, W., Liu, Y., Zhao, X., Hu, H., & Zhu, Q. (2025) · International Journal of Digital Earth · doi:10.1080/17538947.2025.2564903 · Cited by 2
“Recent studies have emphasized the utility of decision trees and naive Bayesian classification algorithms for predicting project delays (Gondia et al. 2020; Mohamed and Moselhi 2022).”
Data-driven model for delay estimation in construction projects
Mohammed, A., Al-Qahtani, A., Ghaithan, A. M., & Alshibani, A. (2025) · Journal of the Chinese Institute of Engineers · doi:10.1080/02533839.2025.2574452 · Cited by 2
“For instance, Gondia et al. (2020) utilized two machine learning models, Decision Tree and Naïve Bayes classifiers, achieving accuracy rates of 74.5% and 78.4%, respectively, to enhance risk assessment and forecasting of project delays in building projects in Egypt.”
InfluentialHou, Y., Elwakil, E., & Jiang, Y. J. (2026) · Journal of structural design and construction practice. · doi:10.1061/jsdccc.sceng-1953 · Cited by 6
Nguyen, L. M. L., & Luu, V. T. (2026) · Journal of Asian Architecture and Building Engineering · doi:10.1080/13467581.2026.2700079 · Cited by 2
Hasan, M., & Barua, M. K. (2024) · doi:10.63125/x7te4644 · Cited by 13
Fairly Apportioning Concurrent Delay Liability: A Game Theory Approach
Huynh, H. T., Lucko, G., & Eid, M. S. (2022) · ASCE Construction Research Congress (CRC) · doi:10.1061/9780784483978.002 · Cited by 2
Mejía, G., Gutiérrez-Prada, J. A., Portilla-Carreño, O., & Martinez, B. A. M. (2022) · ENTRAMADO · doi:10.18041/1900-3803/entramado.2.8006 · Cited by 7
Kostrzewa-Demczuk, P., & Rogalska, M. (2023) · Archives of Civil Engineering · doi:10.24425/ace.2023.145278 · Cited by 2
“Sweis and his team say that despite the advanced technology and project management techniques available to practitioners, construction projects face delays [6].”
BackgroundData-Driven Evaluation of Project Risk Registers
Erfani, A., Ma, Z., Cui, Q., & Baecher, G. B. (2023) · ASCE Geo-Risk Conference (GeoRisk) · doi:10.1061/9780784484975.017 · Cited by 2
Xu, J., Zhu, J., & Xie, J. (2023) · Frontiers in Earth Science · doi:10.3389/feart.2023.1237884 · Cited by 2
Cost Performace of Road Construction Projects in Nigeria
Aligamhe, V. I., Mustapa, M., & Ogbu, C. P. (2024) · International Journal of Academic Research in Accounting Finance and Management Sciences · doi:10.6007/ijarafms/v14-i1/20783 · Cited by 5
Ivanova, M., Grims, M., Karas, D., Höfinger, G., Bornschlegl, M. X., & Hemmje, M. (2024) · IFIP advances in information and communication technology · doi:10.1007/978-3-031-63215-0_12 · Cited by 2
Jalam, A. A., Keftin, N. A., Abdullahi, U. A., yayajo, S. M., Datti, U. M., & Saleh, I. M. (2024) · Mikailalsys Journal of Advanced Engineering International · doi:10.58578/mjaei.v1i3.3888 · Cited by 2
“Similarly, Gondia et al. (2020) revealed that ML provides an appropriate set of tools for dealing building project delays.”
BackgroundAn Effective Software Risk Prediction Management Analysis of Data Using Machine Learning and Data
Xu, J., Wang, Y. A., Li, R., Wang, Z., & Zhao, Q. (2025) · IEEE International Conference on Artificial Intelligence, Computer Science and Information Processing (AICSIP) · doi:10.1109/aicsip65423.2025.11427270 · Cited by 2
“To improve the explanation of the Att-Bilstm model, risk evolution is examined using the Latin hypercube sampling (LHS) approach, and the Shapley Additive explanations (SHAP) analysis is used to quantify the contribution of components in risk prediction [27].”
Development of ANN-Based Risk Prediction Model in Construction Projects
Anirudh, N., Padala, S. P. S., & Reddy, H. N. E. (2022) · Lecture notes in civil engineering · doi:10.1007/978-981-19-5077-3_9 · Cited by 2
DATA-DRIVEN RISK MODELING FOR INFRASTRUCTURE PROJECTS USING ARTIFICIAL INTELLIGENCE TECHNIQUESPreprint
Erfani, A. (2023) · arXiv (Cornell University) · doi:10.13016/dspace/qnkm-thiy · Cited by 5
Assessing the Causes and Effects of Delay and Disruption in Construction Projects in Malaysia
Sohu, S., Kassim, T. R. M., Mustafa, A., Arshad, M. U., & Nagapan, S. (2024) · Journal of Applied Engineering Sciences · doi:10.2478/jaes-2024-0041 · Cited by 1
A Framework of Project Risk Simulation with Event Knowledge Graph
Wen, H., AbouRizk, S., Mohamed, Y., & Huang, R. (2024) · Winter Simulation Conference · doi:10.1109/wsc63780.2024.10838960 · Cited by 1
“Despite these advancements, risk simulation techniques integrating statistical methods (Senthil and Muthukannan 2021) and machine learning (Gondia et al. 2020) are continually evolving, and progress in this area has been hindered by the predominance of project data in textual form, which impedes…”
Chauhan, N. (2025) · International Journal of Research -GRANTHAALAYAH · doi:10.29121/granthaalayah.v13.i4.2025.6215 · Cited by 1
Patel, D. T., Scheepbouwer, A. P. E., & van der Walt, J. D. (2025) · CIB Conferences · doi:10.7771/3067-4883.1793 · Cited by 1
Enhanced Construction Schedule Prediction Using Ensemble Machine Learning: A Comparative Case Study
Kothapalli, S. (2024) · Journal of architecture and civil engineering. · doi:10.35629/8193-09022836 · Cited by 1
Yao, T., & Luo, X. Q. (2025) · Informatica · doi:10.31449/inf.v49i11.9783 · Cited by 1
Rana, M. (2025) · American Journal of Scholarly Research and Innovation · doi:10.63125/jce79s31 · Cited by 2
Joshi, P. P., Sadgir, P. A., & Patil, A. P. (2025) · Lecture notes in civil engineering · doi:10.1007/978-981-95-2266-8_43 · Cited by 2
Deng, J. (2025) · Engineering Construction & Architectural Management · doi:10.1108/ecam-06-2025-0911 · Cited by 1
Chen, N., Naderpajouh, N., Hong, W.-T., & Mohammadi, N. (2026) · Advanced Engineering Informatics · doi:10.1016/j.aei.2026.104401 · Cited by 1
Hengbing, Y., Jing, K. T., Qinghua, L., & Yao, L. (2026) · International Journal of Management Studies · doi:10.32890/ijms2026.33.1.8 · Cited by 2
Garmroudi, Y. A., & Noorzai, E. (2026) · Engineering Construction & Architectural Management · doi:10.1108/ecam-10-2025-1646 · Cited by 1
Knezevic, M., Knežević, D., & Dunović, Č. (2026) · Buildings · doi:10.3390/buildings16132652 · Cited by 1
“Machine-learning methods have been used to predict delay risk and construction duration from historical project data [34,35].”
Elkabir, A. M. A., Naimi, S., Amro, S. O. A., & Aburqaq, I. S. A. (2026) · Sustainability · doi:10.3390/su18157599 · Cited by 1
Agyekum, K., Pittri, H., Sackey, K. N. Y. S., Gasu, J. S., & Oduro, J. A. (2026) · Journal of Engineering Design and Technology · doi:10.1108/jedt-05-2026-0350 · Cited by 1
Employing Predictive Trend Analysis to Decrease Construction Schedule Delay
Austin, V., McLane, Z., O'Keeffe, C., Rashid, D., Zimmerman, A., Duran, D. F., Heydarian, A., & Bagwell, T. (2021) · Systems and Information Engineering Design Symposium · doi:10.1109/sieds52267.2021.9483796 · Cited by 1
Liang, Q., & Qiu, Y. (2021) · Springer eBooks · doi:10.1007/978-981-16-3587-8_19 · Cited by 1
Siewior, H., & Madej, Ł. (2021) · Computer Methods in Materials Science. · doi:10.7494/cmms.2021.4.0769 · Cited by 1
“ML is a group of approaches used in many different fields, e.g., to predict a protein’s behav - iour (Kozuch et al., 2018), design new materials (Cur - tarolo et al., 2013; Shi et al., 2019), or to predict the risk of delays in construction work (Gondia et al., 2020).”
BackgroundIntroduction to Construction Analytics
Shahandashti, M., Abediniangerabi, B., Zahed, E., & Kim, S. (2023) · Springer eBooks · doi:10.1007/978-3-031-27292-9_1 · Cited by 1
A Data-driven Approach to Predict Maintenance Delays for Time-based Maintenance
Khurmi, R., Sankaranarayanan, K., & Harvel, G. (2023) · IEEE International Conference on Industrial Engineering and Engineering Management (IEEM) · doi:10.1109/ieem58616.2023.10406556 · Cited by 1
“Reference [15] used naïve Bayesian and decision tree models on construction project data to determine what project risks will potentially delay construction.”
MethodPerformance Measurement of Classification Algorithms for Aerial Image Registration
Merza, H. M., Sbeity, I., Dbouk, M., Ibrahim, Z. A. A., & Kadhim, A. S. (2024) · Studies in computational intelligence · doi:10.1007/978-3-031-53717-2_37 · Cited by 1
Aligamhe, V. I., Mustapa, M., Ogbu, C. P., & Misnan, M. S. (2024) · Journal of Construction in Developing Countries · doi:10.21315/jcdc.2024.29.s1.6 · Cited by 1
Liu, H., Liu, R., Bai, S., Chen, Y., & Liu, L. (2024) · Water · doi:10.3390/w16213067 · Cited by 1
ISM‐BN‐Based Schedule Risk Analysis in Large‐Scale Public Projects
Yuan, C., Li, Y., & Zha, Y. (2024) · Advances in Civil Engineering · doi:10.1155/adce/5517481 · Cited by 1
Machine Learning Techniques Evaluating Housing Projects Performance
Hassoon, A., Ghazali, F. E. M., Khaleel, T. A., Hadi, A., & Alsamarraie, M. M. (2025) · The Open Civil Engineering Journal · doi:10.2174/0118741495398469250428061055 · Cited by 1
Wei, M. (2025) · International Conference on Electronic Information Technology (EIT) · doi:10.1109/eit67313.2025.11232196 · Cited by 1
A Comparative Study on Machine Learning Algorithms for Predicting Construction Projects Delay
Egwim, C. N., & Alaka, H. (2021) · University of Hertfordshire Research Archive (University of Hertfordshire) · Cited by 1
Dicks, E. P., & Molenaar, K. R. (2022) · ASCE Construction Research Congress (CRC) · doi:10.1061/9780784483978.079
Development of AI-based Warning System for Construction Rate Forecasting
Jung, H., Han, G., Lee, B., Han, Y., Heo, K. H., Choi, H., & Han, S. W. (2022) · Journal of Korean Institute of Industrial Engineers · doi:10.7232/jkiie.2022.48.4.420
اسماعیل, ا. ص. ع. ا. ع. (2022) · Engineering Research Journal · doi:10.21608/erj.2022.258592
RETRACTED: Compressing project to minimize the increased risk and cost
Chen, Q., Chen, L., Zeng, X.-T., & Wei, C. (2022) · Concurrent Engineering · doi:10.1177/1063293x221133344
RetractedBig Data and Analytics in the Deep Renovation Life Cycle
Koukaras, P., Krinidis, S., Ioannidis, D., Tjortjis, C., & Tzovaras, D. K. (2023) · Palgrave studies in digital business & enabling technologies · doi:10.1007/978-3-031-32309-6_5
Predictive analytics for ensuring the autonomy of urban infrastructure socially significant elements
Adamtsevich, L. A. (2023) · E3S Web of Conferences · doi:10.1051/e3sconf/202341004013
Analysis of Contractor-Related Delay Factors in Building Construction
Sangeetha, M., & Thomas, A. V. (2023) · AIJR Proceedings · doi:10.21467/proceedings.156.13
Altuntaş, H. B., & Başağa, H. B. (2023) · SSRN Electronic Journal · doi:10.2139/ssrn.4664602
Comito, M. B. (2024) · Digital Library of Theses and Dissertations (Universidade de São Paulo) · doi:10.11606/d.104.2024.tde-10062024-165509
Impact of risk on time performance of highway projects in Nigeria
Aligamhe, V. I., Mustapa, M., & Ogbu, C. P. (2024) · International Conference on Science, Engineering and Business for Driving Sustainable Development Goals (SEB4SDG) · doi:10.1109/seb4sdg60871.2024.10629757
“The focus group meeting was conducted by 10 experts in the construction industry [19, 23] with 15–25 years of experience in project and construction management.”
BackgroundMethodSimulation and Machine Learning Based Real-Time Delay Prediction for Complex Queuing Systems
Fatma, N., Girish, P. S., & Ramamohan, V. (2024) · Simulation foundations, methods and applications · doi:10.1007/978-3-031-59999-6_8
Top AI Techniques for Every Phase of Software Project Management
Ranković, N., Ranković, D., Ivanović, M. D., & Lazić, L. (2024) · Artificial intelligence-enhanced software and systems engineering · doi:10.1007/978-3-031-76572-8_2
Wu, W. (2024) · International Journal of Reliability Quality and Safety Engineering · doi:10.1142/s021853932450058x
AI for Construction Risk Management
Cecconi, F. R., Khodabakhshian, A., & Rampini, L. (2025) · SpringerBriefs in applied sciences and technology · doi:10.1007/978-3-031-77197-2_4
Mohammadi, P., Rashidi, A., & Asgari, S. (2024) · Winter Simulation Conference · doi:10.1109/wsc63780.2024.10838786
“Typically, this method randomly splits the dataset into training and testing subsets (Gondia et al. 2020), with 80% of the data allocated for training and 20% reserved for testing.”
Andalib, M. (2025) · International Journal of Construction Education and Research · doi:10.1080/15578771.2025.2485061
“However, its adoption remains limited, making construction one of the least digitalized industries globally (Abioye et al., 2021; Gondia et al., 2020; Musarat et al., 2021Najafzadeh et al., 2024).”
InfluentialDemystifying machine learning for predictive analytics in construction
Delgado, J. M. D. (2025) · Elsevier eBooks · doi:10.1016/b978-0-443-29861-5.00023-8
A Machine Learning–Based Buffer Estimation for Construction Schedules Under Uncertainty
Lozi, N. M. A., & He, N. (2025) · Emerald Group Publishing Limited eBooks · doi:10.1108/978-1-83662-518-620251002
Kothapalli, S. (2023) · International Journal For Multidisciplinary Research · doi:10.36948/ijfmr.2023.v05i06.47565
Overview on the Potential of Construction Technologies Implementation in the Construction Industry
Mohd, S., Abidin, N. I., Brahim, J., & Jusoh, Z. M. (2025) · Lecture notes in civil engineering · doi:10.1007/978-981-96-4694-4_48
Opoku, R. A. (2025) · International Journal of Construction Management · doi:10.1080/15623599.2025.2528914
“Some studies have also leveraged machine learning and artificial intelligence to predict and manage construction delays (Gondia et al. 2020; Yaseen et al. 2020).”
Metadata
- Authors
- Gondia, A., Siam, A., El-Dakhakhni, W., & Nassar, A. H.
- Affiliations
- McMaster University (CA)
- German University in Cairo (EG)
- Corresponding author
- Gondia, Ahmed
- Venue
- Journal of Construction Engineering and Management
- Published
- 2020-01
- Volume
- 146
- Issue
- 1
- ISSN
- 0733-9364 (ISSN-L)
- 1943-7862
- OpenAlex
- W2982358567
- Semantic Scholar
- f377710bec5c1ae3454e26eb951728250b2d2cb2
- Cited by
- 327
- References
- 61
- Citations by year
- 2026: 52 · 2025: 72 · 2024: 58 · 2023: 50 · 2022: 54 · 2021: 28 · 2020: 13
- FWCI
- 16.94
- Type
- journal article
- Language
- en
- Open access
- closed
- Locations
- Journal of Construction Engineering and Management (publishedVersion)
- Topics
- Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
- Physical Sciences › Engineering › Building and Construction › BIM and Construction Integration
- Social Sciences › Economics, Econometrics and Finance › Finance › Capital Investment and Risk Analysis
- Keywords
- construction delays, decision tree, naive Bayesian classification, project time performance, project risk management
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.