Machine Learning Algorithms for Construction Projects Delay Risk Prediction
The DOI matches its Crossref record; 62 of the 62 references it cites were found in a registry or an index.
Abstract
Projects delays are among the most pressing challenges faced by the construction sector attributed to the sector’s complexity and its inherent delay risk sources’ interdependence. Machine learning offers an ideal set of techniques capable of tackling such complex systems; however, adopting such techniques within the construction sector remains at an early stage. The goal of this study was to identify and develop machine learning models in order to facilitate accurate project delay risk analysis and prediction using objective data sources. As such, relevant delay risk sources and factors were first identified, and a multivariate data set of previous projects’ time performance and delay-inducing risk sources was then compiled. Subsequently, the complexity and interdependence of the system was uncovered through an exploratory data analysis. Accordingly, two suitable machine learning models, utilizing decision tree and naïve Bayesian classification algorithms, were identified and trained using the data set for predicting project delay extents. Finally, the predictive performances of both models were evaluated through cross validation tests, and the models were further compared using machine-learning-relevant performance indices. The evaluation results indicated that the naïve Bayesian model provides a better predictive performance for the data set examined. Ultimately, the work presented herein harnesses the power of machine learning to facilitate evidence-based decision making, while inherent risk factors are active, interdependent, and dynamic, thus empowering proactive project risk management strategies.
Overview
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
Claims other papers make about this one
Each is checked against this paper’s own text: does it say what the citing paper says it does?
In the citing paper
“Gondia et al. [22] proved that ML-based approaches are superior in predicting construction projects' delay risk over statistical learning.”
From Cost Overrun Risk Assessment and Prediction in Construction Projects: A Bayesian Network Classifier Approach (2022) · cites this paper as [22]
In the citing paper
“The present study considered a 10-fold CV because numerous studies have indicated that this is the optimal value for computational time, error estimation, and indices variance [22].”
From Cost Overrun Risk Assessment and Prediction in Construction Projects: A Bayesian Network Classifier Approach (2022) · cites this paper as [22]
In the citing paper
“| Gondia et al. [22] | NB | Accuracy: 78.4% |”
From Cost Overrun Risk Assessment and Prediction in Construction Projects: A Bayesian Network Classifier Approach (2022) · cites this paper as [22]
In the citing paper
“For instance, in a Gondia et al. [22] study, the best ML model was the NB, which had a 51.2% accuracy rate.”
From Cost Overrun Risk Assessment and Prediction in Construction Projects: A Bayesian Network Classifier Approach (2022) · cites this paper as Gondia et al. [22]
Citations
Cites
The Elements of Statistical Learning
Hastie, T., Tibshirani, R., & Friedman, J. (2009) · Springer Series in Statistics · doi:10.1007/978-0-387-84858-7 · Cited by 25,970
A Study of Cross-Validation and Bootstrap for Accuracy Estimation and Model Selection
Kohavi, R. (1995) · Zenodo · doi:10.5281/zenodo.19712698 · Cited by 10,909
Advances in Neural Information Processing Systems 14: Proceedings of the 2001 Conference
(2002) · The MIT Press eBooks · doi:10.7551/mitpress/1120.001.0001 · Cited by 8,890
Statistical Modeling: The Two Cultures (with comments and a rejoinder by the author)
Breiman, L. (2001) · Statistical Science · doi:10.1214/ss/1009213726 · Cited by 4,340
A Guide to the project management body of knowledge
(1996) · Choice Reviews Online · doi:10.5860/choice.34-1636 · Cited by 4,339
A survey of cross-validation procedures for model selection
Arlot, S., & Célisse, A. (2010) · LillOA (Université de Lille (University Of Lille)) · Cited by 3,662
A survey of cross-validation procedures for model selection
Arlot, S., & Celisse, A. (2010) · Statistics Surveys · doi:10.1214/09-ss054 · Cited by 3,522
Project management: A systems approach to planning, scheduling and controlling
Botter, C. H. (1982) · European Journal of Operational Research · doi:10.1016/0377-2217(82)90164-3 · Cited by 2,408
Causes of delay in large construction projects
Assaf, S. A., & Al-Hejji, S. (2006) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.11.010 · Cited by 1,705
Causes and effects of delays in Malaysian construction industry
Sambasivan, M., & Soon, Y. W. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.11.007 · Cited by 1,422
Research works printed but not linked: 3
- Ismail I., 2014, Expert opinion on risk level for factors affecting time and cost overrun along the project lifecycle in Malaysian construction projects, Int. J. Constr. Technol. Manage., 1, 10
- Ng A. Y., 2002, Advances in neural information processing systems, 841
- R Core Team, 2013, A language and environment for statistical computing
Cited by
Opportunities and Adoption Challenges of AI in the Construction Industry: A PRISMA Review
Regona, M., Yigitcanlar, T., Xia, B., & Li, R. Y. M. (2022) · Journal of Open Innovation: Technology, Market, and Complexity · doi:10.3390/joitmc8010045 · Cited by 543
“This uncertainty is being magnified as large construction companies are still implementing a traditional process that could be automated, and small subcontractors are following a similar business model [42].”
BackgroundPrediction of Risk Delay in Construction Projects Using a Hybrid Artificial Intelligence Model
Yaseen, Z. M., Ali, Z. H., Salih, S. Q., & Al-Ansari, N. (2020) · Sustainability · doi:10.3390/su12041514 · Cited by 194
“The study revealed the power of AI models in delay risk prediction and improving risk management strategies [11].”
BackgroundMethodInfluentialZhang, P., Wu, H.-N., Chen, R.-P., & Chan, T. H. T. (2020) · Tunnelling and Underground Space Technology · doi:10.1016/j.tust.2020.103383 · Cited by 233
A critical evaluation of machine learning and deep learning in shield-ground interaction prediction
Zhang, P., Wu, H.-N., Chen, R.-P., Dai, T., Meng, F.-Y., & Wang, H.-B. (2020) · Tunnelling and Underground Space Technology · doi:10.1016/j.tust.2020.103593 · Cited by 175
Data mining in the construction industry: Present status, opportunities, and future trends
Yan, H., Yang, N., Peng, Y., & Ren, Y. (2020) · Automation in Construction · doi:10.1016/j.autcon.2020.103331 · Cited by 161
Applied artificial intelligence for predicting construction projects delay
Egwim, C. N., Alaka, H., Toriola-Coker, L. O., Balogun, H., & Sunmola, F. (2021) · Machine Learning with Applications · doi:10.1016/j.mlwa.2021.100166 · Cited by 125
Big Data in Construction: Current Applications and Future Opportunities
Munawar, H. S., Ullah, F., Qayyum, S., & Shahzad, D. (2022) · Big Data and Cognitive Computing · doi:10.3390/bdcc6010018 · Cited by 117
Machine learning in project analytics: a data-driven framework and case study
Uddin, S., Ong, S., & Lu, H. (2022) · Scientific Reports · doi:10.1038/s41598-022-19728-x · Cited by 116
“For instance, preceding research has incorporated a different combination of machine-learning algorithms in research of predicting construction delays 47 .”
BackgroundKhodabakhshian, A., Puolitaival, T., & Kestle, L. (2023) · Buildings · doi:10.3390/buildings13051312 · Cited by 119
“…in assessments Considering variables interdependencies on final output [87,107] Prediction precision Mid-high [108] Very high [25] Application scope Subjective and uncertain problems with limited data [109] Objective and complex problems with abundant data [83] Application in RM processes”
BackgroundMethodArtificial intelligence in infrastructure construction: A critical review
Chen, K., Zhou, X., Bao, Z., Skibniewski, M. J., & Fang, W. (2024) · Frontiers of Engineering Management · doi:10.1007/s42524-024-3128-5 · Cited by 97
“Gondia et al. (2020) identified 59 delay risk factors and used DT and naïve Bayes classifiers to predict project delay risks.”
Alsulamy, S. H. (2024) · Expert Systems with Applications · doi:10.1016/j.eswa.2024.126268 · Cited by 108
Srivastava, A., Jawaid, S., Singh, R., Gehlot, A., Akram, S. V., Priyadarshi, N., & Khan, B. (2022) · Advances in Civil Engineering · doi:10.1155/2022/6716987 · Cited by 111
Doukari, O., Seck, E. H. B., & Greenwood, D. J. (2022) · Buildings · doi:10.3390/buildings12081145 · Cited by 103
“Effective use of these data could enable valuable insights through a combination of Building Information Modelling (BIM), Artificial Intelligence (AI) and Machine Learning (ML) [13].”
BackgroundMethodInfluentialArtificial Intelligence Methods for the Construction and Management of Buildings
Ivanova, S. A., Kuznetsov, A., Евгеньевич, З. Р., & Rada, A. O. (2023) · Sensors · doi:10.3390/s23218740 · Cited by 112
“Gondia et al. [158] have developed a machine learning model that is able to accurately predict the risk of delay of construction projects using objective data sources.”
BackgroundEgwim, C. N., Alaka, H., Demir, E., Balogun, H., Olu-Ajayi, R., Sulaimon, I. A., Wusu, G. E., Yusuf, W., & Adegoke, M. (2023) · Energies · doi:10.3390/en17010182 · Cited by 101
“Furthermore, as illustrated in Hong’s [105] AI framework for clustering construction schedules in UK-based construction projects, Gondia’s [19] AI-based model lacks the use of real construction project schedule information for their construction project delay risk prediction implementation in Egypt.”
BackgroundAdamantiadou, D. S., & Tsironis, L. K. (2025) · Computers · doi:10.3390/computers14020066 · Cited by 108
Tian, K., Zhu, Z., Mbachu, J., Ghanbaripour, A. N., & Moorhead, M. (2025) · Journal of Innovation & Knowledge · doi:10.1016/j.jik.2025.100711 · Cited by 89
Machine learning model for delay risk assessment in tall building projects
Sanni-Anibire, M. O., Zin, R. M., & Olatunji, S. O. (2022) · International Journal of Construction Management · doi:10.1080/15623599.2020.1768326 · Cited by 69
Saurav, K. R. H., & Shafi, A. (2022) · doi:10.63125/dn8nkm85 · Cited by 75
Khalef, R., & El-adaway, I. H. (2021) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000959 · Cited by 81
Gondia, A., Ezzeldin, M., & El-Dakhakhni, W. W. (2020) · Journal of Structural Engineering · doi:10.1061/(asce)st.1943-541x.0002734 · Cited by 68
Self-citationSobieraj, J., & Metelski, D. (2022) · Applied Sciences · doi:10.3390/app12031044 · Cited by 75
Construction risk management research: intellectual structure and emerging themes
Zhao, X. (2023) · International Journal of Construction Management · doi:10.1080/15623599.2023.2167303 · Cited by 92
“Gondia et al. (2020) developed machine learning models to predict construction delay risk sources, whilst Shan et al. (2018) adopted artificial neural network (ANN), as one of machine learning models, to assess collusion risk in construction projects.”
Machine learning-based construction site dynamic risk models
Gondia, A., Moussa, A., Ezzeldin, M., & El-Dakhakhni, W. W. (2023) · Technological Forecasting and Social Change · doi:10.1016/j.techfore.2023.122347 · Cited by 73
Self-citationData-Driven Machine Learning Approach to Integrate Field Submittals in Project Scheduling
Awada, M., Srour, F. J., & Srour, I. (2020) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000873 · Cited by 77
Exploring the adoption of technology against delays in construction projects
Gürgün, A. P., Koç, K., & Kunkcu, H. (2022) · Engineering Construction & Architectural Management · doi:10.1108/ecam-06-2022-0566 · Cited by 79
Ashtari, M. A., Ansari, R., Hassannayebi, E., & Jeong, J. (2022) · Buildings · doi:10.3390/buildings12101660 · Cited by 65
“Before proceeding to model performance metrics, a few key terms for each class need to be clarified first [22]: 1.”
BackgroundMethodInfluentialExtraction of underlying factors causing construction projects delay in Nigeria
Egwim, C. N., Alaka, H., Toriola-Coker, L. O., Balogun, H., Ajayi, S. O., & Oseghale, R. O. (2021) · Journal of Engineering Design and Technology · doi:10.1108/jedt-04-2021-0211 · Cited by 82
Decentralizing construction AI applications using blockchain technology
Adel, K., Elhakeem, A., & Marzouk, M. M. (2022) · Expert Systems with Applications · doi:10.1016/j.eswa.2022.116548 · Cited by 73
Predictive risk modeling for major transportation projects using historical data
Erfani, A., & Cui, Q. (2022) · Automation in Construction · doi:10.1016/j.autcon.2022.104301 · Cited by 63
An Application of Data Envelopment Analysis and Machine Learning Approach to Risk Management
Jomthanachai, S., Wong, W.-P., & Lim, C. P. (2021) · IEEE Access · doi:10.1109/access.2021.3087623 · Cited by 84
“For the construction area, the predictive power of ML enables evidence-based decision-making, utilizing interdependent, active, and dynamic risk factors for formulating appropriate strategies in proactive project risk management [44].”
MethodGenerative AI, Large Language Models, and ChatGPT in Construction Education, Training, and Practice
Jelodar, M. B. (2025) · Buildings · doi:10.3390/buildings15060933 · Cited by 65
Kassem, M., Mahamedi, E., Rogage, K., Duffy, K., & Huntingdon, J. (2021) · Automation in Construction · doi:10.1016/j.autcon.2020.103532 · Cited by 55
Causes of time and cost overruns in construction projects: a scoping review
Cabrera, A. G., Gutierrez-Bucheli, L. A., & Muñoz, S. (2023) · International Journal of Construction Management · doi:10.1080/15623599.2023.2252288 · Cited by 79
“For example, Gondia et al. (2020) developed machine learning models to predict project delays using data from 51 projects.”
MethodComparing Natural Language Processing Methods to Cluster Construction Schedules
Hong, Y., Xie, H. S., Bhumbra, G. S., & Brilakis, I. K. (2021) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0002165 · Cited by 52
A comparative study of machine learning regression models for predicting construction duration
Zhang, S., & Li, X. (2023) · Journal of Asian Architecture and Building Engineering · doi:10.1080/13467581.2023.2278887 · Cited by 59
“On the basis of 51 construction projects, Gondia and Siam (Gondia et al. 2020) developed an effective predictive data analytics tool based on decision tree and naive Bayesian classification algorithms.”
Dynamic networks for resilience-driven management of infrastructure projects
Gondia, A., Ezzeldin, M., & El-Dakhakhni, W. W. (2022) · Automation in Construction · doi:10.1016/j.autcon.2022.104149 · Cited by 50
Self-citationApplications of Bayesian approaches in construction management research: a systematic review
Hon, C. K. H., Sun, C., Xia, B., Jimmieson, N. L., Way, K. A., & Wu, P. P. (2021) · Engineering Construction & Architectural Management · doi:10.1108/ecam-10-2020-0817 · Cited by 55
Opabola, E. A., & Galasso, C. (2023) · Reliability Engineering & System Safety · doi:10.1016/j.ress.2023.109679 · Cited by 48
Su, S., Zang, Z., Yuan, J., Pan, X., & Shan, M. (2024) · Case Studies in Construction Materials · doi:10.1016/j.cscm.2024.e02887 · Cited by 70
Ye, X., Zhang, X., Zhang, H.-Q., Ding, Y., & Chen, Y. (2023) · Transportation Geotechnics · doi:10.1016/j.trgeo.2023.101002 · Cited by 50
Construction schedule risk analysis – a hybrid machine learning approach
Fitzsimmons, J., Lu, R., Hong, Y., & Brilakis, I. (2022) · Journal of Information Technology in Construction · doi:10.36680/j.itcon.2022.004 · Cited by 46
“For example, (Gondia et al., 2020) used a number of risk factors to predict the level of project time overrun (i.e., low (< 30%), medium (30% - 60%), and high (> 60%)).”
BackgroundA Review on Significant Factors Causing Delays in Saudi Arabia Construction Projects
Alajmi, A. M., & Memon, Z. A. (2022) · Smart Cities · doi:10.3390/smartcities5040075 · Cited by 45
The Last State of Artificial Intelligence in Project ManagementPreprint
Davahli, M. R. (2020) · arXiv (Cornell University) · doi:10.48550/arxiv.2012.12262 · Cited by 58
“The authors reported that the naïve Bayesian classification outperformed the decision tree in terms of the prediction performance [64].”
BackgroundMethodExploring the Nature and Impact of Client-Related Delays on Contemporary Saudi Construction Projects
Alenazi, E., Adamu, Z. A., & Al-Otaibi, A. (2022) · Buildings · doi:10.3390/buildings12070880 · Cited by 55
BIM-based integrated solution for analysis and management of mismatches during construction
Jafari, K. G., Sharyatpanahi, N. S. G., & Noorzai, E. (2020) · Journal of Engineering Design and Technology · doi:10.1108/jedt-02-2020-0044 · Cited by 44
Zeng, T., Wang, J., Cui, B., Wang, X., Wang, D., & Zhang, Y. (2021) · Construction and Building Materials · doi:10.1016/j.conbuildmat.2021.123268 · Cited by 44
Integrated Approach to Construction Risk Management: Cost Implications
Sadeh, H., Mirarchi, C., & Pavan, A. (2021) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0002140 · Cited by 44
Araba, A. M., Memon, Z. A., Alhawat, M., Ali, M., & Milad, A. A. (2021) · Knowledge-Based Engineering and Sciences · doi:10.51526/kbes.2021.2.2.1-12 · Cited by 41
“Further, future studies trend should be implemented as a real-time application on other construction projects for a practical recognition of its contribution [70], [71].”
Research Trends on Machine Learning in Construction Management: A Scientometric Analysis
Tâm, N. V., & Toản, N. Q. (2021) · Journal of Applied Science and Technology Trends · doi:10.38094/jastt203105 · Cited by 41
“Therefore, many studies were undertaken to apply machine learning to predict and assess risks of construction projects [8-18].”
BackgroundPredicting construction schedule performance with last planner system and machine learning
Lagos, C. I., Herrera, R. F., Cawley, A. F. M., & Alarcón, L. F. (2024) · Automation in Construction · doi:10.1016/j.autcon.2024.105716 · Cited by 39
Deep Multilayer Perceptron Neural Network for the Prediction of Iranian Dam Project Delay Risks
Shirazi, D. H., & Toosi, H. (2023) · Journal of Construction Engineering and Management · doi:10.1061/jcemd4.coeng-12367 · Cited by 42
Machine learning - based framework for construction delay mitigation
Sanni-Anibire, M. O., Zin, R. M., & Olatunji, S. O. (2021) · Journal of Information Technology in Construction · doi:10.36680/j.itcon.2021.017 · Cited by 42
Estimating labor resource requirements in construction projects using machine learning
Golabchi, H., & Hammad, A. (2023) · Construction Innovation · doi:10.1108/ci-11-2021-0211 · Cited by 36
Enhancing cyber risk identification in the construction industry using language models
Yao, D., & de Soto, B. G. (2024) · Automation in Construction · doi:10.1016/j.autcon.2024.105565 · Cited by 37
Gündüz, M., & Al-Naimi, N. H. (2021) · Engineering Construction & Architectural Management · doi:10.1108/ecam-12-2020-1082 · Cited by 34
Lin, C., Fan, C., & Chen, B.-K. (2022) · Applied Sciences · doi:10.3390/app12157790 · Cited by 39
“[24] used decision tree and Naïve Bayes classifiers to predict the delay risks of a construction project.”
MethodErfani, A., Cui, Q., Baecher, G. B., & Kwak, Y. H. (2023) · IEEE Transactions on Engineering Management · doi:10.1109/tem.2023.3279237 · Cited by 35
“Limiting historical data, failing to learn from past lessons learned, and relying solely on expert opinions prevent proper risk management practices [16], [17], [18], [19].”
BackgroundMachine learning and deep learning in project analytics: methods, applications and research trends
Uddin, S., Yan, S., & Lu, H. (2024) · Production Planning & Control · doi:10.1080/09537287.2024.2320790 · Cited by 45
“Meanwhile, Gondia et al. (2020) demonstrated the effectiveness of ML, particularly the NB model, in predicting delays in construction projects by analysing the complex interplay of various risk factors, aiding in proactive project management and risk mitigation strategies.”
Conceptual estimation of construction duration and cost of public highway projects
Mohamed, B., & Moselhi, O. (2022) · Journal of Information Technology in Construction · doi:10.36680/j.itcon.2022.029 · Cited by 43
“This can be traced back to the uncertain, complex, and dynamic nature of construction activities as well as the interdependency between various risk factors (Gondia et al, 2020).”
BackgroundMethodInfluentialGao, B., Ma, Z., Gu, J., Han, X., Xiang, P., & Lv, X. (2023) · Knowledge-Based Systems · doi:10.1016/j.knosys.2023.111223 · Cited by 32
Gondia, A., Ezzeldin, M., & El-Dakhakhni, W. W. (2022) · ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems Part A Civil Engineering · doi:10.1061/ajrua6.0001239 · Cited by 39
Self-citationCyber Risk Assessment Framework for the Construction Industry Using Machine Learning Techniques
Yao, D., & de Soto, B. G. (2024) · Buildings · doi:10.3390/buildings14061561 · Cited by 36
Research on the Influence of Risk on Construction Project Performance: A Systematic Review
Guiliang, S., & Khallaf, R. (2022) · Sustainability · doi:10.3390/su14116412 · Cited by 34
Kazemi, M. H., & Alvanchi, A. (2024) · Expert Systems with Applications · doi:10.1016/j.eswa.2024.125296 · Cited by 30
Erfani, A., Cui, Q., & Cavanaugh, I. (2021) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0002206 · Cited by 34
Data-Driven Community Flood Resilience Prediction
Abdel-Mooty, M. N., El-Dakhakhni, W. W., & Coulibaly, P. (2022) · Water · doi:10.3390/w14132120 · Cited by 33
Self-citationReal-estate price prediction with deep neural network and principal component analysis
Mostofi, F., Toğan, V., & Başağa, H. B. (2022) · Organization Technology and Management in Construction An International Journal · doi:10.2478/otmcj-2022-0016 · Cited by 37
Al-Fadhali, N. (2022) · Engineering Construction & Architectural Management · doi:10.1108/ecam-09-2021-0780 · Cited by 33
Hamdan, M. M., Thneibat, M., & Hyari, K. H. (2025) · Engineering Construction & Architectural Management · doi:10.1108/ecam-09-2024-1209 · Cited by 31
Zaman, U., Flórez, L., Abbasi, S., Nawaz, S., Farías, P., & Pradana, M. (2022) · Sustainability · doi:10.3390/su14042091 · Cited by 28
Development of Risk Quantification Models in Road Infrastructure Projects
Senić, A., Đobrodolac, M., & Stojadinović, Z. (2024) · Sustainability · doi:10.3390/su16177694 · Cited by 26
Wu, L., Li, Z., & AbouRizk, S. (2021) · Journal of Computing in Civil Engineering · doi:10.1061/(asce)cp.1943-5487.0001001 · Cited by 27
Ex Post Project Risk Assessment: Method and Empirical Study
Erfani, A., Ma, Z., Cui, Q., & Baecher, G. B. (2022) · Journal of Construction Engineering and Management · doi:10.1061/jcemd4.coeng-12588 · Cited by 27
Lee, S., Jang, Y., Yi, J.-S., & Son, J. (2023) · Journal of Management in Engineering · doi:10.1061/jmenea.meeng-5310 · Cited by 26
Artificial Neural Network Model to Predict Final Construction Contract Duration
Alsugair, A. M., Al-Gahtani, K. S., Alsanabani, N. M., Alabduljabbar, A. A., & Almohsen, A. S. (2023) · Applied Sciences · doi:10.3390/app13148078 · Cited by 26
“However, Jin et al. [22] established a CBR model that can correctly predict the FCCD at the planning stage.”
BackgroundSenić, A., Simić, N., Đobrodolac, M., & Stojadinović, Z. (2025) · Applied Sciences · doi:10.3390/app15052736 · Cited by 25
Innovative Use of Low-Cost Digitisation for Smart Information Systems in Construction Projects
Jelodar, M. B., & Shu, F. (2021) · Buildings · doi:10.3390/buildings11070270 · Cited by 25
Assafi, M. N., Hoque, M. I., & Hossain, M. M. (2022) · International Journal of Building Pathology and Adaptation · doi:10.1108/ijbpa-10-2021-0137 · Cited by 30
Kusonkhum, W., Srinavin, K., & Chaitongrat, T. (2023) · Sustainability · doi:10.3390/su151712836 · Cited by 26
“Building a confusion matrix and using the following Equations (1)–(3) allowed the ANN model’s accuracy, precision, and recall to be checked [65] where true positives (TP), true negatives (TN), false positives (FP), and false negatives (FN) represent the true, false, positive, and negative states, as shown in Figure 5.”
MethodGo/No-Go Decision Model for Owners Using Exhaustive CHAID and QUEST Decision Tree Algorithms
Gündüz, M., & Lutfi, H. M. A. (2021) · Sustainability · doi:10.3390/su13020815 · Cited by 24
Turkyilmaz, A. H., & Polat, G. (2024) · Buildings · doi:10.3390/buildings14113541 · Cited by 24
Tian, K., Zhu, Z., Mbachu, J., Moorhead, M., & Ghanbaripour, A. N. (2025) · Journal of Risk Research · doi:10.1080/13669877.2025.2512080 · Cited by 29
“Analysis of historical data using ML algorithms facilitates the forecasting of potential risks, including schedule delays, cost overruns, and safety hazards, enabling proactive risk management (Shoar, Chileshe, and Edwards 2022; Abedsoltan, Abedsoltan, and Zoghi 2024; Gondia et al. 2020).”
Large Language Models for Construction Risk Classification: A Comparative Study
Erfani, A., & Khanjar, H. (2025) · Buildings · doi:10.3390/buildings15183379 · Cited by 26
Aziz, M., Osabel, D. M., Kim, Y., Kim, S.-H., Bae, J., & Tsavdaridis, K. D. (2025) · Results in Engineering · doi:10.1016/j.rineng.2025.107882 · Cited by 27
Gao, Y., Antwi‐Afari, M. F., Huang, Y., Chen, Z., & Manzoor, B. (2026) · Buildings · doi:10.3390/buildings16051061 · Cited by 30
Uddin, S., Ong, S., Lu, H., & Matouš, P. (2023) · Production Planning & Control · doi:10.1080/09537287.2023.2196256 · Cited by 26
“The introduction of newer and more complex algorithms will only continue to expand the repertoire and capabilities of machine learning (Bilal and Oyedele 2020; Bilal et al. 2019; Egwim et al. 2021; Gondia et al. 2020).”
InfluentialShihadeh, J., Al-Shaibie, G., Bisharah, M. M., Alshami, D., Alkhadrawi, S., & Al-Bdour, H. (2024) · Asian Journal of Civil Engineering · doi:10.1007/s42107-023-00936-3 · Cited by 23
“…as the quotient of the Mean Absolute Error (MAE) for the specific model under consideration and the MAE of a baseline naive model, as described by Gondia et al. (2020): Each of these indicators provides a nuanced perspective for evaluating the predictions made by the model, so assuring a…”
InfluentialElsayed, A. M., Rixon, S., Levison, J. K., Binns, A. D., & Goel, P. (2024) · Journal of Environmental Management · doi:10.1016/j.jenvman.2024.123305 · Cited by 26
Hsu, M., Dacre, N., & Senyo, P. K. (2021) · SSRN Electronic Journal · doi:10.31235/osf.io/6hfje · Cited by 23
Predicting Serious Injury and Fatality Exposure Using Machine Learning in Construction Projects
Erkal, E. D. O., Hallowell, M. R., Ghriss, A., & Bhandari, S. (2023) · Journal of Construction Engineering and Management · doi:10.1061/jcemd4.coeng-13741 · Cited by 29
“Inaddition to utilizing regression analyses, machine learning pipelines have been used for safety prediction, especially to analyze intricate empirical data (Gondia et al. 2020; Liu and Tian 2019; Shin 2019).”
MethodBuilding a Next Generation AI Platform for AEC: A Review and Research Challenges
Wang, Z., He, B., Yu, Y., Shen, C., & Pena-Mora, F. A. (2020) · CIB W78 conference series · doi:10.46421/2706-6568.37.2020.paper003 · Cited by 23
BIM-Supported Knowledge Collaboration: A Case Study of a Highway Project in China
Miao, C., Wang, H., Meng, X., Hou, X., Yan, Y., Liu, S., & He, Y. (2024) · Sustainability · doi:10.3390/su16209074 · Cited by 24
“Large-scale projects like highway construction are defined by protracted construction times, a large number of stakeholders, a substantial financial commitment, uncertainty, and risk [33–35].”
BackgroundUtilizing synthetic images to enhance the automated recognition of small-sized construction tools
Han, S., Park, W., Jeong, K., Hong, T., & Koo, C. (2024) · Automation in Construction · doi:10.1016/j.autcon.2024.105415 · Cited by 24
Zaneldin, E. K., & Ahmed, W. K. (2024) · Buildings · doi:10.3390/buildings14071918 · Cited by 24
Secundo, G., Mele, G., Passıante, G., & Ligorio, A. (2023) · European Journal of Innovation Management · doi:10.1108/ejim-11-2022-0656 · Cited by 23
Peiman, F., Khalilzadeh, M., Shahsavari-Pour, N., & Ravanshadnia, M. (2023) · Engineering Construction & Architectural Management · doi:10.1108/ecam-12-2022-1170 · Cited by 25
An analytical model for budget allocation in risk prevention and risk protection
Guan, X., Servranckx, T., & Vanhoucke, M. (2021) · Computers & Industrial Engineering · doi:10.1016/j.cie.2021.107657 · Cited by 20
“approach falls short and more complex techniques, such as artificial intelligence and machine learning, are required (Afzal and Bhatti, 2021; Gondia et al., 2020).”
BackgroundGoforth, E., Yosri, A., El-Dakhakhni, W. W., & Wiebe, L. D. A. (2022) · Journal of Energy Engineering · doi:10.1061/(asce)ey.1943-7897.0000836 · Cited by 20
Self-citationHatami, M., Franz, B. W., Paneru, S., & Flood, I. (2022) · ASCE International Conference on Computing in Civil Engineering (i3CE) · doi:10.1061/9780784483893.143 · Cited by 19
Metadata
- Authors
- Gondia, A., Siam, A., El-Dakhakhni, W., & Nassar, A. H.
- Affiliations
- McMaster University (CA)
- German University in Cairo (EG)
- Corresponding author
- Gondia, Ahmed
- Venue
- Journal of Construction Engineering and Management
- Published
- 2020-01
- Volume
- 146
- Issue
- 1
- ISSN
- 0733-9364 (ISSN-L)
- 1943-7862
- OpenAlex
- W2982358567
- Semantic Scholar
- f377710bec5c1ae3454e26eb951728250b2d2cb2
- Cited by
- 327
- References
- 61
- Citations by year
- 2026: 52 · 2025: 72 · 2024: 58 · 2023: 50 · 2022: 54 · 2021: 28 · 2020: 13
- FWCI
- 16.94
- Type
- journal article
- Language
- en
- Open access
- closed
- Locations
- Journal of Construction Engineering and Management (publishedVersion)
- Topics
- Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
- Physical Sciences › Engineering › Building and Construction › BIM and Construction Integration
- Social Sciences › Economics, Econometrics and Finance › Finance › Capital Investment and Risk Analysis
- Keywords
- construction delays, decision tree, naive Bayesian classification, project time performance, project risk management
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.