Delays and cost increases in the construction of private residential projects in Kuwait
The DOI matches its Crossref record; 8 of the 8 references it cites were found in a registry or an index.
Abstract
Time‐delays and cost‐increases associated with the construction of private residential projects in the State of Kuwait are determined. A person‐interview survey of 450 randomly selected private residential project owners and developers in 27 representative districts in metropolitan Kuwait formed the database for the study. The socio‐economic traits of the owners/developers, and the pre‐construction family planning, the design, and the construction phases of the sample projects are presented. Estimates of time‐delays and cost‐increases are made, and their causes identified. The three main causes of time‐delays included changing orders, owners' financial constraints and owners' lack of experience in the construction business. Regarding cost overruns, the three main causes were identified as contractor‐related problems, material‐related problems and, again, owners' financial constraints. A number of recommendations end the paper. The minimization of time delays and cost overruns in private residential projects would require: the availability of adequate funds, allocation of sufficient time and money at the design phase, and selection of a competent consultant and a reliable contractor to carry out the work.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Journal of Construction Engineering and Management
de la Garza, J., Jahren, C. T., Jaselskis, E. J., Rowings, J. E., & Harris, R. B. (1983) · Cited by 969
The effects of construction delays on project delivery in Nigerian construction industry
Aibinu, A. A., & Jagboro, G. O. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00028-5 · Cited by 597
Causes of Delay in Large Building Construction Projects
Assaf, S. A., Al-Khalil, M., & Al-Hazmi, M. (1995) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(1995)11:2(45 · Cited by 544
Construction delays in a fast-growing economy: Comparing Thailand with other economies
Ogunlana, S. O., Promkuntong, K., & Jearkjirm, V. (1996) · International Journal of Project Management · doi:10.1016/0263-7863(95)00052-6 · Cited by 390
Morris, P. W. G., & Hough, G. (1987) · UCL Discovery (University College London) · Cited by 300
Compressing construction durations: lessons learned from Hong Kong building projects
W.M. Chan, D., & M. Kumaraswamy, M. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00032-6 · Cited by 209
Reasons for delays in public projects in Turkey
Arditi, D., Akan, G. T., & Gurdamar, S. (1985) · Construction Management and Economics · doi:10.1080/01446198500000013 · Cited by 198
Contractor project risks contingency allocation using linguistic approximation
Tah, J. H. M., Thorpe, A., & McCaffer, R. (1993) · Computing Systems in Engineering · doi:10.1016/0956-0521(93)90052-x · Cited by 119
Cited by
Le-Hoai, L., Lee, Y. D., & Lee, J. Y. (2008) · KSCE Journal of Civil Engineering · doi:10.1007/s12205-008-0367-7 · Cited by 560
Delays in construction projects: The case of Jordan
Sweis, G., Sweis, R., Abu Hammad, A., & Shboul, A. (2008) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.09.009 · Cited by 534
Applying lean thinking in construction and performance improvement
Aziz, R. F., & Hafez, S. M. (2013) · Alexandria Engineering Journal · doi:10.1016/j.aej.2013.04.008 · Cited by 513
Olawale, Y. A., & Sun, M. (2010) · Construction Management and Economics · doi:10.1080/01446191003674519 · Cited by 478
“For example Lee et al. (2005) identified project change management as a critical practice that has important impacts on both cost and schedule performance of projects. Ling et al. (2009) in the study of key project management practices affecting project performance found that the most important practices that are sign…”
BackgroundMethodInfluentialFactors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects
Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2016) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000391 · Cited by 365
Problems causing delays in major construction projects in Thailand
Toor, S.-U.-R., & Ogunlana, S. (2008) · Construction Management and Economics · doi:10.1080/01446190801905406 · Cited by 307
Delays and cost overruns in the construction projects in the Gaza Strip
Enshassi, A., Al‐Najjar, J., & Kumaraswamy, M. (2009) · Journal of Financial Management of Property and Construction · doi:10.1108/13664380910977592 · Cited by 278
Causes of delays on construction projects: a comprehensive list
Durdyev, S., & Hosseini, M. R. (2019) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-09-2018-0178 · Cited by 245
Cost overrun in the Malaysian construction industry projects: A deeper insight
Shehu, Z., Endut, I. R., Akintoye, A., & Holt, G. D. (2014) · International Journal of Project Management · doi:10.1016/j.ijproman.2014.04.004 · Cited by 210
“, 2013) and the significance of this, has attracted much research over recent decades (Arditi et al., 1985; Creedy, 2004; Dawood, 1998; Dlakwa and Culpin, 1990; Doloi, 2013; Frimpong et al., 2003; Kaming et al., 1997; Koushki et al., 2005; Mansfield et al., 1994).”
BackgroundRanking of delay factors in construction projects after Egyptian revolution
Aziz, R. F. (2013) · Alexandria Engineering Journal · doi:10.1016/j.aej.2013.03.002 · Cited by 209
Time and cost overruns in the UAE construction industry: a critical analysis
Johnson, R. M., & Babu, R. I. I. (2020) · International Journal of Construction Management · doi:10.1080/15623599.2018.1484864 · Cited by 173
Causes of delay in the global construction industry: a meta analytical review
Sanni-Anibire, M. O., Mohamad Zin, R., & Olatunji, S. O. (2022) · International Journal of Construction Management · doi:10.1080/15623599.2020.1716132 · Cited by 173
Park, Y., & Papadopoulou, T. C. (2012) · Built Environment Project and Asset Management · doi:10.1108/20441241211280873 · Cited by 91
Ghazal, M. M., & Hammad, A. (2022) · International Journal of Construction Management · doi:10.1080/15623599.2020.1738205 · Cited by 52
Kwon, H., & Kang, C. W. (2019) · Project Management Journal · doi:10.1177/8756972818810963 · Cited by 50
“According to Koushki et al. (2005), delays and cost overruns increased in the construction of a private residential project in Kuwait due to three main causes: contractor-related problems, materialrelated problems, and owners’ financial constraints.”
BackgroundConstruction delays in privately funded large building projects in Bangladesh
Islam, M. S., & Suhariadi, B. T. (2018) · Asian Journal of Civil Engineering · doi:10.1007/s42107-018-0034-3 · Cited by 44
Estimation of the Escalation Factor in Construction Projects Using Value at Risk
Joukar, A., & Nahmens, I. (2016) · Construction Research Congress 2016 · doi:10.1061/9780784479827.234 · Cited by 6
Metadata
- Authors
- Koushki, P. A., Al‐Rashid, K., & Kartam, N.
- Venue
- Construction Management and Economics
- Publisher
- Informa UK Limited
- Published
- 2005-03
- Volume
- 23
- Issue
- 3
- Pages
- 285-294
- ISSN
- 0144-6193 (ISSN-L)
- 1466-433X
- OpenAlex
- W2096275307
- Cited by
- 456
- References
- 8
- FWCI
- 12.56
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.