Causes of delays in Saudi Arabian public sector construction projects

Open access
Al‐Kharashi, Adel, Skitmore, Martin · 2009 · Construction Management and Economics

Abstract

Many public construction projects have been undertaken throughout the Kingdom of Saudi Arabia as part of the government's national development plans in the past three decades, with significant public expenditure involved. One of the critical problems concerning these projects is the frequent and lengthy delays that occur. In order to improve the situation, it is first necessary to identify the major causes involved. Several studies have already been reported which do this but all use different sets of variables. Also, none has attempted to identify the extent to which improvements are possible in practice. A new survey is reported that uses all the variables from the previous work and measures for both current degree of effect on delays and the extent to which each can be practically improved. These are contained in seven groupings: client, contractor, consultant, materials, labour, contract and relationship‐related causes. The survey covers a sample of 86 clients, contractors and consultants working in the Saudi construction industry. The analysis reveals some considerable heterogeneity between the cause groupings and respondent groupings in terms of means and correlations, apparently partly due to lack of knowledge of respondents and a tendency for the consultants to blame the contractors for the delays and vice versa. The main results, therefore, are disaggregated to reflect the views of each respondent group concerning each group of causes. In general however, it is found that the most influencing current cause of delay is the lack of qualified and experienced personnel—attributed to the considerable amount of large, innovative, construction projects and associated current undersupply of manpower in the industry.

Overview

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.1080/01446190802541457

Cites

7 of 7 references verified0 citation errors · 0 not checkable

Statistics

Verification

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

Citations

Cites

Show all 7 references

Cited by

See all 327

Metadata

Authors
Al‐Kharashi, A., & Skitmore, M.
Venue
Construction Management and Economics
Published
2009-01
Volume
27
Issue
1
Pages
3-23
ISSN
  • 0144-6193 (ISSN-L)
  • 1466-433X
OpenAlex
W2098819826
Cited by
327
References
7
FWCI
8.12
Type
journal article
Language
en
Open access
bronze

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review

How to cite

Cite CoChat for the checks on this page, and the paper for its own findings.

This page
CoChat. (2026). Citation check: Causes of delays in Saudi Arabian public sector construction projects. https://app.cochat.ai/papers/10.1080/01446190802541457
The paper
Al‐Kharashi, A., & Skitmore, M. (2009). Causes of delays in Saudi Arabian public sector construction projects. Construction Management and Economics. https://doi.org/10.1080/01446190802541457

Data sources

Bibliographic data: Semantic Scholar, OpenAlex, Crossref.

Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).

Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.