Causes of delay in residential construction projects in Cambodia
Open accessThe DOI matches its Crossref record; 32 of the 32 references it cites were found in a registry or an index.
Abstract
Construction industry is one of the significant contributors to the economic growth and development of Cambodia. Two major challenges are limiting the performance of the construction industry in Cambodia, which are poor cost and schedule performance of the construction projects. Therefore, the aim of this study is to fill an important knowledge gap by identifying the various attributes for construction project delay, using the residential building projects as a starting point. Feedback from a survey administered to the contractors and consultants was analysed using Relative Importance Index (RII). Results showed that shortage of materials on site; unrealistic project scheduling; late delivery of material; shortage of skilled labour; complexity of project; labour absenteeism; late payment by the owner for the completed work; poor site management; delay by subcontractor; accidents due to poor site safety are ranked by the contractors and consultants as the main causes of project delays in Cambodia. Construction frontline players are recommended to put their efforts on the identified key factors in relation to their magnitudes of influence. By doing so, the causes of project delays in the Cambodia’s construction and real estate sector could be significantly reduced or controlled, which will ultimately lead to the on time project completion.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Making sense of cronbach’s alpha.
Tavakol, M., & Dennick, R. (2011) · International Journal of Medical Education · doi:10.5116/ijme.4dfb.8dfd · Cited by 15,126 · cited 1×
“However, even the pilot survey determines the data reliability or relevancy to the industry, it is mandatory to analyse the reliability of the data using the Cronbach’s alpha method based on internal consistency (Tavakol & Dennick, 2011).”
MethodSPSS for Windows Step by Step: A Simple Guide and Reference
Mallery, P., & George, D. (1998) · Cited by 10,394
Causes of delay in large construction projects
Assaf, S. A., & Al-Hejji, S. (2006) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.11.010 · Cited by 1,705 · cited 2×
“Delay is defined as a time overrun beyond the project completion date agreed by the parties (Assaf & Al-Hejji, 2006).”
BackgroundResearch methods for construction
Fellowa, R., & Liu, A. M. M. (2003) · Cited by 1,448
Causes and effects of delays in Malaysian construction industry
Sambasivan, M., & Soon, Y. W. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.11.007 · Cited by 1,422 · cited 3×
“Based on the review of relevant literature, it can be seen that several studies have identified and evaluated causes of project delay in other countries (Doloi et al., 2012; Haseeb et al., 2011; Lindhard & Wandahl, 2014; Sambasivan & Soon, 2007).”
BackgroundHandbook of Research Design and Social Measurement.
McLemore, D., & Miller, D. C. (1978) · Contemporary Sociology · doi:10.2307/2064762 · Cited by 1,269
Causes of construction delay: traditional contracts
Odeh, A. M., & Battaineh, H. T. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00037-5 · Cited by 810
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00055-8 · Cited by 796 · cited 1×
“This outcome substantiates the findings of Fugar and Agyakwah-Baah (2010), who ranked the aforementioned factors as one of the most influencing causes of construction project delay in Ghana.”
ResultAnalysing factors affecting delays in Indian construction projects
Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012) · International Journal of Project Management · doi:10.1016/j.ijproman.2011.10.004 · Cited by 745 · cited 4×
“Based on the review of relevant literature, it can be seen that several studies have identified and evaluated causes of project delay in other countries (Doloi et al., 2012; Haseeb et al., 2011; Lindhard & Wandahl, 2014; Sambasivan & Soon, 2007).”
BackgroundMethodInfluentialCost escalation and schedule delays in road construction projects in Zambia
Kaliba, C., Muya, M., & Mumba, K. (2009) · International Journal of Project Management · doi:10.1016/j.ijproman.2008.07.003 · Cited by 596
Identifying elements of poor construction safety management in China
Tam, C. M., Zeng, S. X., & Deng, Z. M. (2004) · Safety Science · doi:10.1016/j.ssci.2003.09.001 · Cited by 590
Research Methods for Construction (3rd ed.)
Fellows, R., & Liu, A. (2008) · Wiley-Blackwell eBooks · Cited by 510
Factors affecting cost performance: evidence from Indian construction projects
Iyer, K. C., & Jha, K. N. (2005) · International Journal of Project Management · doi:10.1016/j.ijproman.2004.10.003 · Cited by 504 · cited 1×
“However, in their studies conducted for the specific locations, Iyer and Jha (2005), Sambasivan and Soon (2007) and Abd El-Razek, Bassioni, and Mobarak (2008) reported the complexity of the delay analysis.”
BackgroundCauses of Delay in Building Construction Projects in Egypt
Abd El-Razek, M. E., Bassioni, H. A., & Mobarak, A. M. (2008) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2008)134:11(831 · Cited by 463 · cited 1×
“However, in their studies conducted for the specific locations, Iyer and Jha (2005), Sambasivan and Soon (2007) and Abd El-Razek, Bassioni, and Mobarak (2008) reported the complexity of the delay analysis.”
BackgroundConstruction delays in a fast-growing economy: Comparing Thailand with other economies
Ogunlana, S. O., Promkuntong, K., & Jearkjirm, V. (1996) · International Journal of Project Management · doi:10.1016/0263-7863(95)00052-6 · Cited by 390
Handbook of Research Design and Social Measurement
Davis, L. (1992) · The Nurse Practitioner · doi:10.1097/00006205-199202000-00029 · Cited by 345 · cited 1×
“By the cut-off date set for the survey, 48 usable responses were received; this represented approximately 64% usable response rate, which is perceived as adequate for analysis and reporting the findings of this research (Miller, 1991).”
MethodCauses of Delay in Road Construction Projects
Mahamid, I., Bruland, A., & Dmaidi, N. (2011) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000096 · Cited by 345
Causes of delays in Saudi Arabian public sector construction projects
Al‐Kharashi, A., & Skitmore, M. (2009) · Construction Management and Economics · doi:10.1080/01446190802541457 · Cited by 327 · cited 1×
“Al-Kharashi and Skitmore (2009) identify leading causes of construction project delay in Saudi Arabia by conducting a questionnaire survey administered to contractors, consultants and clients.”
BackgroundLove, P. E. D., Holt, G. D., Shen, L. Y., Li, H., & Irani, Z. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(01)00039-4 · Cited by 316
Causes and Effects of Delays and Disruptions in Construction Projects in Tanzania
Kikwasi, G. J. (2013) · Australasian Journal of Construction Economics and Building - Conference Series · doi:10.5130/ajceb-cs.v1i2.3166 · Cited by 290 · cited 1×
“Similarly, due to the poor schedule performance management, the construction projects in Cambodia are also experiencing project delays, which have to be controlled, as it will lead to a poor quality of work due to hurry (Kikwasi, 2012).”
BackgroundProject Characteristics for Successful Public-Sector Design-Build
Songer, A. D., & Molenaar, K. R. (1997) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(1997)123:1(34 · Cited by 254
CAUSES OF DELAYS IN CONSTRUCTION PROJECTS IN TURKEY
Kazaz, A., Ulubeyli, S., & Tuncbilekli, N. A. (2012) · Journal of Civil Engineering and Management · doi:10.3846/13923730.2012.698913 · Cited by 234
Handbook of Research Design and Social Measurement
Woodside, A. G., & Miller, D. C. (1993) · Journal of Marketing Research · doi:10.2307/3172834 · Cited by 228
PROBLEMS OF PROJECTS AND EFFECTS OF DELAYS IN THE CONSTRUCTION INDUSTRY OF PAKISTAN
Haseeb, M. A., Lu, X., Bibi, A., Dyian, M.-U., & Rabbani, W. (2012) · Australian Journal of Business and Management Research · doi:10.52283/nswrca.ajbmr.20110106a05 · Cited by 228 · cited 3×
“Haseeb et al. (2011) conduct a research on the causes of delay in large construction projects in Pakistan, where the following factors are reported to be the most influential: natural disaster; financial and payment problems; improper planning; poor site management; insufficient experience;…”
BackgroundResultDelays in Building Construction Projects in Ghana
Fugar, F. D., & Agyakwah-Baah, A. B. (1970) · Construction Economics and Building · doi:10.5130/ajceb.v10i1-2.1592 · Cited by 211 · cited 1×
“This outcome substantiates the findings of Fugar and Agyakwah-Baah (2010), who ranked the aforementioned factors as one of the most influencing causes of construction project delay in Ghana.”
ResultDurdyev, S., & Mbachu, J. (2011) · Construction Economics and Building · doi:10.5130/ajceb.v11i3.2120 · Cited by 211 · cited 1×
“Therefore, this study administered questionnaire surveys using web domain (Survey Monkey), which allows large number of participants in a wider geography or organization coverage (Durdyev & Mbachu, 2011).”
MethodSelf-citationAnalyzing Delays of Road Construction Projects in Cambodia: Causes and Effects
Santoso, D. S., & Soeng, S. (2016) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000467 · Cited by 178 · cited 2×
“The only study (Santoso & Soeng, 2016) has identified causes of project delay in Cambodia, which has analysed the delay factors in road construction projects.”
BackgroundJournal of Financial Management of Property and Construction
(2008) · Journal of Financial Management of Property and Construction · doi:10.1108/jfmpc.2008.37613aaa.002 · Cited by 156
Factors causing cost variation for constructing wastewater projects in Egypt
Aziz, R. F. (2012) · Alexandria Engineering Journal · doi:10.1016/j.aej.2012.11.004 · Cited by 91
ROOT CAUSES OF CONSTRUCTION PROJECT DELAYS IN DUBAI
Ren, Z., Atout, M. M., & Jones, J. V. (2008) · Cited by 70
Mbachu, J. (2011) · Construction Management and Economics · doi:10.1080/01446193.2011.623708 · Cited by 58 · cited 3×
“Therefore, this study administered questionnaire surveys using web domain (Survey Monkey), which allows large number of participants in a wider geography or organization coverage (Durdyev & Mbachu, 2011).”
BackgroundMethodLindhard, S. M., & Wandahl, S. (2014) · International Journal of Project Organisation and Management · doi:10.1504/ijpom.2014.065258 · Cited by 34 · cited 2×
“Based on the review of relevant literature, it can be seen that several studies have identified and evaluated causes of project delay in other countries (Doloi et al., 2012; Haseeb et al., 2011; Lindhard & Wandahl, 2014; Sambasivan & Soon, 2007).”
Background
Cited by
Causes of delays on construction projects: a comprehensive list
Durdyev, S., & Hosseini, M. R. (2019) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-09-2018-0178 · Cited by 245
Self-citationSustainable Construction Industry in Cambodia: Awareness, Drivers and Barriers
Durdyev, S., Zavadskas, E., Thurnell, D., Banaitis, A., & Ihtiyar, A. (2018) · Sustainability · doi:10.3390/su10020392 · Cited by 194
“6 (the minimum value of reliability coefficient) [50,51].”
BackgroundInfluentialSelf-citation
Metadata
- Authors
- Durdyev, S., Omarov, M., & Ismail, S.
- Venue
- Cogent Engineering
- Publisher
- Informa UK Limited
- Published
- 2017-01-01
- Volume
- 4
- Issue
- 1
- Pages
- 1291117
- ISSN
- 2331-1916 (ISSN-L)
- OpenAlex
- W2587141935
- Cited by
- 158
- References
- 32
- FWCI
- 14.03
- Type
- journal article
- Language
- en
- Open access
- gold
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.