The DOI matches its Crossref record; 10 of the 10 references it cites were found in a registry or an index.
The significant factors causing delay of building construction projects in Malaysia
Abstract
Purpose: The paper seeks to identify the major factors causing delay in building construction projects in Malaysia. Design/methodology/approach: A questionnaire survey was used to carry out the study. The questionnaire consisted of 31 factors which were grouped into four major categories by responsibility – contractor factors, owner factors, consultant factors and external factors. The level of importance of the categories was measured and the relative importance of weights was ranked. Findings: The study finds that financial problems are the main factor and coordination problems are the second most important factor causing delay in construction projects in Malaysia. The results were analyzed to rank the causes of delay and further classify the types of delay. Research limitations/implications: The scope of this study is limited to building projects in the Klang Valley area, where major Malaysian cities such as Kuala Lumpur, Putrajaya, Petaling Jaya, Shah Alam and Seremban are located. The data for this study was gathered through a detailed questionnaire survey. Originality/value: Based on the analysis of the ranking and intensity of causes of delay, this paper suggests possible improvements that could be made in order to reduce delays in the construction industry.
Overview
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Causes of construction delay: traditional contracts
Odeh, A. M., & Battaineh, H. T. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00037-5 · Cited by 810
Construction delay: a quantitative analysis
Al-Momani, A. H. (2000) · International Journal of Project Management · doi:10.1016/s0263-7863(98)00060-x · Cited by 553
Causes of Delay in Large Building Construction Projects
Assaf, S. A., Al-Khalil, M., & Al-Hazmi, M. (1995) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(1995)11:2(45 · Cited by 544
Causes of delay and cost overruns in Nigerian construction projects
Mansfield, N., Ugwu, O., & Doran, T. (1994) · International Journal of Project Management · doi:10.1016/0263-7863(94)90050-7 · Cited by 457
Construction delays in a fast-growing economy: Comparing Thailand with other economies
Ogunlana, S. O., Promkuntong, K., & Jearkjirm, V. (1996) · International Journal of Project Management · doi:10.1016/0263-7863(95)00052-6 · Cited by 390
Contributors to construction delays
Kumaraswamy, M. M., & Chan, D. W. M. (1998) · Construction Management and Economics · doi:10.1080/014461998372556 · Cited by 239
An evaluation of construction time performance in the building industry
Chan, D. W. M., & Kumaraswamy, M. M. (1996) · Building and Environment · doi:10.1016/0360-1323(96)00031-5 · Cited by 205
Causes of delays in the construction industry in Lebanon
Mezher, T. M., & Tawil, W. (1998) · Engineering Construction and Architectural Management · doi:10.1046/j.1365-232x.1998.00049.x · Cited by 201
Industrialized Building Systems Construction in Malaysia
Badir, Y. F., Kadir, M. R. A., & Hashim, A. H. (2002) · Journal of Architectural Engineering · doi:10.1061/(asce)1076-0431(2002)8:1(19 · Cited by 140
Industrialized and Automated Building Systems: A Managerial Approach
Warszawski, A. (1999) · Cited by 119
Cited by
Adeleke, A. Q., Bahaudin, A. Y., Kamaruddeen, A. M., Bamgbade, J. A., Salimon, M. G., Khan, M. W. A., & Sorooshian, S. (2018) · Safety and Health at Work · doi:10.1016/j.shaw.2017.05.004 · Cited by 107
Effect of lean tools to control external environment risks of construction projects
Ansah, R. H., & Sorooshian, S. (2017) · Sustainable Cities and Society · doi:10.1016/j.scs.2017.03.027 · Cited by 92
Construction delays in privately funded large building projects in Bangladesh
Islam, M. S., & Suhariadi, B. T. (2018) · Asian Journal of Civil Engineering · doi:10.1007/s42107-018-0034-3 · Cited by 44
Metadata
- Authors
- Alaghbari, W., Razali A. Kadir, M., Salim, A., & Ernawati
- Venue
- Engineering, Construction and Architectural Management
- Publisher
- Emerald
- Published
- 2007-03-06
- Volume
- 14
- Issue
- 2
- Pages
- 192-206
- ISSN
- 0969-9988 (ISSN-L)
- OpenAlex
- W2048789755
- Cited by
- 489
- References
- 10
- FWCI
- 6.20
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
How to cite
Cite CoChat for the checks on this page, and the paper for its own findings.
- This page
- CoChat. (2026). Citation check: The significant factors causing delay of building construction projects in Malaysia. https://app.cochat.ai/papers/10.1108/09699980710731308
- The paper
- Alaghbari, W., Razali A. Kadir, M., Salim, A., & Ernawati. (2007). The significant factors causing delay of building construction projects in Malaysia. Engineering, Construction and Architectural Management. https://doi.org/10.1108/09699980710731308
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.