Análisis cuantitativo de riesgos utilizando "MCSimulRisk" como herramienta didáctica

Open access
Acebes Senovilla, Fernando, Curto Lorenzo, David, De Antón Heredero, Juan, Villafáñez Cardeñoso, Félix·2024·Dirección y Organización

Abstract

Practical classes are an ideal and essential complement to theoretical classes. Risk Management, taught in the Master's Degree in Project Management at the University of Valladolid, mainly focuses on project uncertainty and quantitative risk analysis. To transmit the knowledge tangibly to the students, the theoretical classes are complemented with practical classes, where the students carry out exercises related to the subject taught, reinforcing the knowledge acquired. Quantitative risk analysis involves Monte Carlo simulation as the most appropriate method for dealing with project uncertainty. Our experience as teachers, teaching Monte Carlo simulation applied to quantitative risk analysis in projects for several years, helped us detect students' difficulties when using specific commercial software tools during the project modelling process. This fact motivated us to look for a solution to facilitate the student's work in class and help increase their learning. This led us to create the teaching software application called ‘MCSimulRisk’. In this article, we present the didactic tool 'MCSimulRisk' that we will use as a teaching tool to carry out Monte Carlo simulation and project control. ‘MCSimulRisk' was developed to solve the problems encountered by the students during the laboratory exercises after the experience acquired when using other commercial tools. The use of this tool is intended to (1) allow students to efficiently carry out Monte Carlo simulation for any project network, regardless of its complexity; (2) easily integrate into the model different types of uncertainty (aleatoric, stochastic, and epistemic one) that may affect the project objectives. In addition to the above, this tool should help research efforts by extending lines of research yet to be addressed in the literature to integrate different types of uncertainty.

Overview

The claims and statistics of this paper haven’t been checked yet.

Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.37610/dyo.v0i82.662

Cites

Statistics

Verification

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.

A few free checks a day · papers already verified open instantly · results are public

Claims other papers make about this one

Each is checked against this paper’s own text: does it say what the citing paper says it does?

  • With the MCSimulRisk software, the impact of each risk on project duration objectives (quantified in time units) and cost objectives (quantified in monetary units) is determined.

    “With the help of the 'MCSimulRisk' simulation software (Acebes et al. 2024;Acebes et al. 2023), this paper determines the impact of each risk on project duration objectives (quantified in time units) and cost objectives (quantified in monetary units).”

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

Citations

Cites

No references could be resolved yet.

Research works printed but not linked: 27

  1. Acebes, F., Pajares, J., Galán, J.M., López-Paredes, A., 2014. A new approach for project control under uncertainty. Going back to the basics. International Journal of Project Management 32, 423-434. https://doi.org/10.1016/j.ijproman.2013.08.003 · DOI · Paper page
  2. Acebes, F., Pajares, J., Galán, J.M., López-Paredes, A., 2013. Beyond Earned Value Management: A Graphical Framework for Integrated Cost, Schedule and Risk Monitoring. Procedia-Social and Behavioral Sciences 74, 181-189. https://doi.org/10.1016/j.sbspro.2013.03.027 · DOI
  3. Acebes, F., Pajares, J., González-Varona, J.M., López- Paredes, A., 2021a. Project risk management from the bottom-up: Activity Risk Index. Central European Journal of Operations Research 29, 1375-1396. https://doi.org/10.1007/s10100-020-00703-8 · DOI
  4. Acebes, F., Pereda, M., Poza, D., Pajares, J., Galán, J.M., 2015. Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques. International Journal of Project Management 33, 1597- 1609. https://doi.org/10.1016/j.ijproman.2015.06.012 · DOI · Paper page
  5. Acebes, F., Poza, D., González-Varona, J.M., Pajares, J., López-Paredes, A., 2021b. On the project risk baseline: Integrating aleatory uncertainty into project scheduling. Computers & Industrial Engineering 160, 107537. https://doi.org/10.1016/j.cie.2021.107537 · DOI
  6. Anbari, F.T., 2003. Earned Value Project Management method and extensions. Project Management Journal 34, 12-23. https://doi.org/10.1177/875697280303400403 · DOI
  7. Axelos, 2017. Managing Successful Projects with PRINCE2®, 6th Edition. ed. TSO (The Stationery Office).
  8. Barraza, G.A., Bueno, R.A., 2007. Cost Contingency Management. Journal of management in engineering 140-146. https://doi.org/10.1061/(ASCE)0742-597X(2007)23:3(140) · DOI
  9. Colin, J., Martens, A., Vanhoucke, M., Wauters, M., 2015. A multivariate approach for top-down project control using earned value management. Decision Support Systems 79, 65-76. https://doi.org/10.1016/j.dss.2015.08.002 · DOI
  10. Curto, D., Acebes, F., González-Varona, J.M., Poza, D., 2022. Impact of aleatoric, stochastic and epistemic uncertainties on project cost contingency reserves. International Journal of Production Economics 253, 108626. https://doi.org/10.1016/j.ijpe.2022.108626 · DOI · Paper page
  11. International Organization for Standardization, 2019. ISO/ IEC 31010:2019 Risk management -Risk assessment techniques. International Project Management Association, 2015. Individual Competence Baseline for Project, Programme & Portfolio Management. Version 4.0, International Project Management Association. https://doi.org/10.1002/ejoc.201200111 International Standards Organisation, 2018. ISO31000:2018 Risk management -Guidelines. Iso 31000. · DOI
  12. Islam, M.S., Nepal, M.P., Skitmore, M., Drogemuller, R., 2021. Risk induced contingency cost modeling for power plant projects. Automation in Construction 123, 103519. https://doi.org/10.1016/j.autcon.2020.103519 · DOI
  13. Kwak, Y.H., Ingall, L., 2007. Exploring Monte Carlo Simulation Applications for Project Management. Risk Management 9, 44-57. https://doi.org/10.1057/palgrave.rm.8250017 · DOI
  14. Kwon, H., Kang, C.W., 2019. Improving Project Budget Estimation Accuracy and Precision by Analyzing Reserves for Both Identified and Unidentified Risks. Project Management Journal 50, 86-100. https://doi.org/10.1177/8756972818810963 · DOI · Paper page
  15. Liu, J., Jin, F., Xie, Q., Skitmore, M., 2017. Improving risk assessment in financial feasibility of international engineering projects: A risk driver perspective. International Journal of Project Management 35, 204- 211. https://doi.org/10.1016/j.ijproman.2016.11.004 · DOI
  16. Martin, J.J., 1965. Distribution of the Time Through a Directed, Acyclic Network. Operations Research 13, 4- 66. https://doi.org/10.1287/opre.13.1.46 · DOI
  17. Pajares, J., López-Paredes, A., 2011. An extension of the EVM analysis for project monitoring: The Cost Control Index and the Schedule Control Index. International Journal of Project Management 29, 615-621. https://doi.org/10.1016/j.ijproman.2010.04.005 · DOI
  18. Project Management Institute, 2017. A Guide to the Project Management Body of Knowledge: PMBoK(R) Guide. Sixth Edition, 6th ed. Project Management Institute Inc., Pennsylvania -USA.
  19. Project Management Institute, 2004. A Guide to the Project Management Body of Knowledge: PMBoK Guide. Third Edition.
  20. Rozenes, S., Vitner, G., Spraggett, S., 2006. Project control: literature review. Project Management Journal 37, 5-14. https://doi.org/10.1177/875697280603700402 · DOI
  21. Rozenes, S., Vitner, G., Spraggett, S., 2004. MPCS: Multidimensional Project Control System. International Journal of Project Management 22, 109-118. https://doi.org/10.1016/S0263-7863(03)00002-4 · DOI
  22. Vanhoucke, M., 2011. On the dynamic use of project performance and schedule risk information during project tracking. Omega 39, 416-426. https://doi.org/10.1016/j.omega.2010.09.006 · DOI
  23. Vanhoucke, M., 2010. Using activity sensitivity and network topology information to monitor project time performance. Omega 38, 359-370. https://doi.org/10.1016/j.omega.2009.10.001 · DOI
  24. Vose, D., 2008. Risk Analysis: a Quantitative Guide, 3rd ed. ed. Wiley, Chichester, U.K. Acebes-Senovilla et al / Dirección y Organización 82 (2024) 87-99 https://doi.org/10.37610/dyo.v0i82.662
  25. Wauters, M., Vanhoucke, M., 2014. Support Vector Machine Regression for project control forecasting. Automation in Construction 47, 92-106. https://doi.org/10.1016/j.autcon.2014.07.014 · DOI
  26. White, D., Fortune, J., 2002. Current practice in project management -an empirical study. International Journal of Project Management 20. https://doi.org/10.1016/S0263-7863(00)00029-6 · DOI
  27. Williams, T.M., 1992. Criticality in Stochastic Networks. Journal of the Operational Research Society 43, 353- 357. https://doi.org/10.2307/2583158 · DOI

Cited by

Sorted by citations

Metadata

Authors
Acebes Senovilla, F., Curto Lorenzo, D., De Antón Heredero, J., & Villafáñez Cardeñoso, F.
Venue
Dirección y Organización
Published
2024-04-01
Pages
87-99
ISSN
  • 1132-175X (ISSN-L)
  • 2171-6323
OpenAlex
W4396836581
Cited by
5
References
0
Citations by year
2026: 4 · 2024: 1
FWCI
1.13
Type
journal article
Language
es
Open access
Locations
  • Dirección y Organización (publishedVersion, cc-by-nc-sa)
  • RePEc: Research Papers in Economics (submittedVersion)
  • arXiv (Cornell University) (submittedVersion, cc-by-nc-nd)
  • UVaDOC UVaDOC University of Valladolid Documentary Repository (University of Valladolid) (submittedVersion, cc-by-nc-nd)
  • arXiv (Cornell University)
Topics
  • Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
  • Social Sciences › Economics, Econometrics and Finance › Finance › Capital Investment and Risk Analysis
  • Social Sciences › Education › Experimental Learning in Engineering
Keywords
quantitative risk analysis, Monte Carlo simulation, educational software, project uncertainty, project risk management, project control, aleatoric uncertainty, epistemic uncertainty, project management education

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review