Identification of Risk Paths in International Construction Projects Using Structural Equation Modeling
Open accessThe DOI matches its Crossref record; 56 of the 57 references it cites were found in a registry or an index.
Abstract
The major aim of this research is to demonstrate that causal relationships exist among various risk factors that necessitate identification of risk paths, rather than individual risk factors, during risk assessment of construction projects. International construction projects have more complex risk-emergence patterns because they are affected by global and foreign country conditions and project-related factors. Identification of a network of interactive risk paths, each of which initiated from diverse vulnerabilities of the project system, is considered to be a better reflection of the real conditions of construction projects than the use of generic risk checklists. In this study, using the data from 166 projects carried out by Turkish contractors in international markets and utilizing structural equation modeling (SEM) techniques, 36 interrelated risk paths were identified and the total effects of each vulnerability factor and risk path on cost overrun were assessed. SEM findings demonstrate that every risk path is initiated from a specific vulnerability factor related to project environment, and that contractor-specific vulnerabilities have the most effect on project cost overrun. Risk identification using SEM helps decision makers in answering what-if questions in the early stages of a project, tracing the effects of interdependent risks throughout the life cycle of the project and evaluating the influence of alternative mitigation strategies, not only on specific risks but also on the whole network of interrelated risk factors.
Overview
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
Claims other papers make about this one
Each is checked against this paper’s own text: does it say what the citing paper says it does?
In the citing paper
“Cost overrun risks are declared to be dynamic and interdependent.”
From Cost Overrun Risk Assessment and Prediction in Construction Projects: A Bayesian Network Classifier Approach (2022) · cites this paper as [45]
In the citing paper
“Similarly, cost overrun risks are said to be dynamic, interdependent, complicated, uncertain, subjective, and fuzzy due to their large size, higher complexity, and unique project contexts and environment [45].”
From Cost Overrun Risk Assessment and Prediction in Construction Projects: A Bayesian Network Classifier Approach (2022) · cites this paper as [45]
Citations
Cites
Structural equation modeling in practice: A review and recommended two-step approach
Anderson, J. C., & Gerbing, D. W. (1988) · Psychological Bulletin · doi:10.1037/0033-2909.103.3.411 · Cited by 41,941
Principles and Practice of Structural Equation Modeling
Tabri, N., & Elliott, C. M. (2012) · Canadian Graduate Journal of Sociology and Criminology · doi:10.15353/cgjsc-rcessc.v1i1.25 · Cited by 38,891
(1998) · Cited by 36,049
Alternative Ways of Assessing Model Fit
Browne, M. W., & Cudeck, R. (1992) · Sociological Methods & Research · doi:10.1177/0049124192021002005 · Cited by 27,200
Qu, X. (2007) · Technometrics · doi:10.1198/tech.2007.s455 · Cited by 14,705
Testing Structural Equation Models.
Mueller, C. W., Bollen, K. A., & Long, J. S. (1994) · Contemporary Sociology · doi:10.2307/2074955 · Cited by 14,120
EQS : structural equations program manual
Bentler, P. M. (1989) · Medical Entomology and Zoology · Cited by 9,669
(2005) · Cited by 6,097
Structural Equation Modeling With AMOS: Basic Concepts, Applications, and Programming, Third Edition
Byrne, B. M. (2016) · doi:10.4324/9781315757421 · Cited by 4,653
Byrne, B. M. (2013) · doi:10.4324/9780203805534 · Cited by 4,016
Research works printed but not linked: 5
- Byrne B. M., 2006, Structural equation modeling with EQS: Basic concepts, applications, and programming
- Dikmen I. Birgonul M. T. and Fidan G. (2008b). “Assessment of project vulnerability as a part of risk management in construction.” Proc. Joint CIB W065/W055 Symp. Conseil International du Bâtiment (CIB) Rotterdam Netherlands.
- Dikmen I., 2009, A risk and vulnerability ontology for construction projects, Int. J. Eng. Manage., 1, 63
- Garson G. D., 2008, Structural equation modeling
- Nunally J., 1978, Psychometric theory
Cited by
Items 201–226 of 226
Causes of delay in power transmission projects in Bangladesh
Pall, G. K. (2021) · Queensland University of Technology · doi:10.5204/thesis.eprints.211479
(2018) · Elsevier eBooks · doi:10.1016/b978-0-12-815483-0.09996-8
Modelo de madurez de internacionalización de las empresas consultoras de ingeniería españolas
Lozano-Torró, A. (2022) · RiuNet (Universitat Politècnica de València) · doi:10.4995/thesis/10251/183870
Assessing Enablers and Barriers to Off-Grid Solar Electrification in Urban Ghana
McWilson, W. K., & Mensah, G. (2022) · Energy, climate and the environment · doi:10.1007/978-3-031-13825-6_10
Zeng, W., Xu, N., Di, K., Zhao, W., & Zhang, B. (2023) · Lecture notes in operations research · doi:10.1007/978-981-99-3626-7_62
AlQahtani, M. S., Ahmed, M., & Naveed, Q. N. (2024) · Algorithms for intelligent systems · doi:10.1007/978-981-97-0180-3_56
A Decision-Making Model for Fast-Track High-Rise Buildings Using Structural Equation Modelling
Sultan, I. H. M. (2024) · Power System Technology · doi:10.52783/pst.434
AI for Construction Risk Management
Cecconi, F. R., Khodabakhshian, A., & Rampini, L. (2025) · SpringerBriefs in applied sciences and technology · doi:10.1007/978-3-031-77197-2_4
Optimizing Perceptions of AI Technology in Risk Assessment Using Bayesian Approaches
Bhimavarapu, U. (2025) · Advances in computational intelligence and robotics book series · doi:10.4018/979-8-3693-8407-7.ch012
Pramudya, A. A., Wibowo, A., Santosa, W., & Permana, F. J. (2025) · Journal of Legal Affairs and Dispute Resolution in Engineering and Construction · doi:10.1061/jladah.ladr-1309
Anzagira, L. F., Duah, D. Y. A., Badu, E., & Simpeh, E. K. (2025) · Journal of Planning and Land Management · doi:10.36005/jplm.v4i1.178
“The computed Cronbach’s alpha value from the data set was 0.945 which is greater than the recommended value of 0.70 (Wong et al. 2016; Eybpoosh et al. 2011; Oyedele, 2013) suggesting a good internal consistency and the reliability of the data obtained from the field survey and as a result, the…”
InfluentialRisk Factors Affecting the Cost Performance of International Construction Projects
Maddah, R., Tripathi, K. K., & Jha, K. N. (2025) · Journal of Legal Affairs and Dispute Resolution in Engineering and Construction · doi:10.1061/jladah.ladr-1228
Luo, X., Sun, Y., Su, L., & Yan, H. H. (2025) · International Conference on Construction and Real Estate Management (ICCREM) · doi:10.1061/9780784486627.045
Dicks, E. P. (2023) · CU Scholar (University of Colorado Boulder)
Practical risk management in design phase of design-build powerplant projects in Vietnam
Bui, D. T., & Lin, S.-Y. (2026) · Journal of the Chinese Institute of Engineers · doi:10.1080/02533839.2026.2626276
“…DB projects, which usually involve international stakeholders, foreign contractors, or a design team that may not be familiar with the local country’s characteristics and relevant requirements, which can significantly affect project objectives (Eybpoosh, Dikmen, and Birgonul 2011; Zhi 1995).”
Nizam, S. (2025) · İstanbul Yeni Yüzyıl Üniversitesi Research Information System
Gao, Y., Zhang, D., Ma, P., Li, Z., & Zhang, S. (2026) · Journal of Construction Engineering and Management · doi:10.1061/jcemd4.coeng-17702
Gomez, F. P. Z. (2024) · LA Referencia (Red Federada de Repositorios Institucionales de Publicaciones Científicas)
Gomez, F. P. Z., & Aroquipa, H. (2025) · Universidad Nacional Autónoma de Tayacaja Daniel Hernández Morillo (UNAT) - Fondo Editorial. eBooks · doi:10.46908/ediunat.73
Akhrees, A. A. M., Abrabba, S. A., Abdulsamea, A. A. A., & Mahmoud, F. A. A. (2026) · Derna Academy Journal for Applied Sciences · doi:10.71147/v54qzj32
Alabdullatief, A., & Al-Otaibi, A. (2026) · SSRN Electronic Journal · doi:10.2139/ssrn.7455390
Liu, L., & Liu, Y. (2026) · Engineering Construction & Architectural Management · doi:10.1108/ecam-03-2026-0493
Okudan, O. (2021) · Yildiz Technical University - AVESIS
Integrated risk management framework for international civil engineering projects
Zirakian, T. (2026) · Proceedings of the Institution of Civil Engineers - Management Procurement and Law · doi:10.1680/jmapl.26.00082
Managing material cost overruns in industrial building projects using a system dynamics approach
Sihombing, L. B., Insja, D., & Ting, S. N. (2026) · Journal of Engineering Design and Technology · doi:10.1108/jedt-04-2026-0250
Metadata
- Authors
- Eybpoosh, M., Dikmen, I., & Talat Birgonul, M.
- Affiliations
- Middle East Technical University (TR)
- Research Assistant, Dept. of Civil Engineering, Middle East Technical Univ., 06531, Ankara, Turkey (corresponding author).
- Venue
- Journal of Construction Engineering and Management
- Published
- 2011-12
- Volume
- 137
- Issue
- 12
- Pages
- 1164-1175
- ISSN
- 0733-9364 (ISSN-L)
- 1943-7862
- OpenAlex
- W2085400663
- Semantic Scholar
- 93f3ab82a6bd250cd8b17fed1cf3bd547d09d5e6
- Cited by
- 217
- References
- 57
- Citations by year
- 2026: 9 · 2025: 20 · 2024: 14 · 2023: 16 · 2022: 29 · 2021: 20 · 2020: 17 · 2019: 24 · 2018: 18 · 2017: 17 · 2016: 10 · 2015: 6 · 2014: 10 · 2013: 2 · 2012: 4
- FWCI
- 7.38
- Type
- journal article
- Language
- en
- Open access
- green
- hdl.handle.net
- Licence
- cc-by-nc-nd
- Locations
- Journal of Construction Engineering and Management (publishedVersion)
- OpenMETU (Middle East Technical University) (submittedVersion, cc-by-nc-nd)
- Funders
- Türkiye Bilimsel ve Teknolojik Araştırma Kurumu
- Türkiye Bilimler Akademisi
- Topics
- Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
- Social Sciences › Business, Management and Accounting › Strategy and Management › Value Engineering and Management
- Physical Sciences › Engineering › Building and Construction › BIM and Construction Integration
- Keywords
- construction risk management, international construction projects, risk assessment, cost overruns, vulnerability factors, project environment, risk mitigation strategies
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.