Identification of Risk Paths in International Construction Projects Using Structural Equation Modeling
Open accessThe DOI matches its Crossref record; 56 of the 57 references it cites were found in a registry or an index.
Abstract
The major aim of this research is to demonstrate that causal relationships exist among various risk factors that necessitate identification of risk paths, rather than individual risk factors, during risk assessment of construction projects. International construction projects have more complex risk-emergence patterns because they are affected by global and foreign country conditions and project-related factors. Identification of a network of interactive risk paths, each of which initiated from diverse vulnerabilities of the project system, is considered to be a better reflection of the real conditions of construction projects than the use of generic risk checklists. In this study, using the data from 166 projects carried out by Turkish contractors in international markets and utilizing structural equation modeling (SEM) techniques, 36 interrelated risk paths were identified and the total effects of each vulnerability factor and risk path on cost overrun were assessed. SEM findings demonstrate that every risk path is initiated from a specific vulnerability factor related to project environment, and that contractor-specific vulnerabilities have the most effect on project cost overrun. Risk identification using SEM helps decision makers in answering what-if questions in the early stages of a project, tracing the effects of interdependent risks throughout the life cycle of the project and evaluating the influence of alternative mitigation strategies, not only on specific risks but also on the whole network of interrelated risk factors.
Overview
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
Claims other papers make about this one
Each is checked against this paper’s own text: does it say what the citing paper says it does?
In the citing paper
“Cost overrun risks are declared to be dynamic and interdependent.”
From Cost Overrun Risk Assessment and Prediction in Construction Projects: A Bayesian Network Classifier Approach (2022) · cites this paper as [45]
In the citing paper
“Similarly, cost overrun risks are said to be dynamic, interdependent, complicated, uncertain, subjective, and fuzzy due to their large size, higher complexity, and unique project contexts and environment [45].”
From Cost Overrun Risk Assessment and Prediction in Construction Projects: A Bayesian Network Classifier Approach (2022) · cites this paper as [45]
Citations
Cites
Structural equation modeling in practice: A review and recommended two-step approach
Anderson, J. C., & Gerbing, D. W. (1988) · Psychological Bulletin · doi:10.1037/0033-2909.103.3.411 · Cited by 41,941
Principles and Practice of Structural Equation Modeling
Tabri, N., & Elliott, C. M. (2012) · Canadian Graduate Journal of Sociology and Criminology · doi:10.15353/cgjsc-rcessc.v1i1.25 · Cited by 38,891
(1998) · Cited by 36,049
Alternative Ways of Assessing Model Fit
Browne, M. W., & Cudeck, R. (1992) · Sociological Methods & Research · doi:10.1177/0049124192021002005 · Cited by 27,200
Qu, X. (2007) · Technometrics · doi:10.1198/tech.2007.s455 · Cited by 14,705
Testing Structural Equation Models.
Mueller, C. W., Bollen, K. A., & Long, J. S. (1994) · Contemporary Sociology · doi:10.2307/2074955 · Cited by 14,120
EQS : structural equations program manual
Bentler, P. M. (1989) · Medical Entomology and Zoology · Cited by 9,669
(2005) · Cited by 6,097
Structural Equation Modeling With AMOS: Basic Concepts, Applications, and Programming, Third Edition
Byrne, B. M. (2016) · doi:10.4324/9781315757421 · Cited by 4,653
Byrne, B. M. (2013) · doi:10.4324/9780203805534 · Cited by 4,016
Research works printed but not linked: 5
- Byrne B. M., 2006, Structural equation modeling with EQS: Basic concepts, applications, and programming
- Dikmen I. Birgonul M. T. and Fidan G. (2008b). “Assessment of project vulnerability as a part of risk management in construction.” Proc. Joint CIB W065/W055 Symp. Conseil International du Bâtiment (CIB) Rotterdam Netherlands.
- Dikmen I., 2009, A risk and vulnerability ontology for construction projects, Int. J. Eng. Manage., 1, 63
- Garson G. D., 2008, Structural equation modeling
- Nunally J., 1978, Psychometric theory
Cited by
A critical review of structural equation modeling applications in construction research
Xiong, B., Skitmore, M., & Xia, B. (2015) · Automation in Construction · doi:10.1016/j.autcon.2014.09.006 · Cited by 427
Qazi, A., Quigley, J., Dickson, A., & Kirytopoulos, K. (2016) · International Journal of Project Management · doi:10.1016/j.ijproman.2016.05.008 · Cited by 294
“Following the same ontology, Yildiz et al. (2014) developed a knowledge-based risk mapping tool for cost estimation of international construction projects and Eybpoosh et al. (2011) introduced the concept of identifying risk paths in international construction projects using SEM.”
MethodA fuzzy synthetic evaluation approach for risk assessment: a case of Singapore's green projects
Zhao, X., Hwang, B.-G., & Gao, Y. (2016) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2015.11.042 · Cited by 279
“…equipment and plants √ √ √ √ √ √ √ Project team risk R24 Project teams without relevant knowledge √ √ R25 Inefficient communication and coordination √ √ √ R26 Unfavorable sub-contractors √ √ √ √ √ Cost overrun risk R27 Inaccurate cost estimation √ √ R28 Labor and materials price…”
Modelling stakeholder-associated risk networks in green building projects
Yang, R. J., Zou, P. X. W., & Wang, J. (2016) · International Journal of Project Management · doi:10.1016/j.ijproman.2015.09.010 · Cited by 207
Risk paths in international construction projects: Case study from Chinese contractors
Liu, J., Zhao, X., & Yan, P. (2016) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001116 · Cited by 203
Analysing the organizational factors of project complexity using structural equation modelling
Qureshi, S. M., & Kang, C. (2015) · International Journal of Project Management · doi:10.1016/j.ijproman.2014.04.006 · Cited by 189
Afzal, F., Yunfei, S., Nazir, M., & Bhatti, S. M. (2021) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-02-2019-0047 · Cited by 172
Ahmadabadi, A. A., & Heravi, G. (2019) · Transport Policy · doi:10.1016/j.tranpol.2018.07.004 · Cited by 166
Islam, M. S., Nepal, M. P., Skitmore, M., & Attarzadeh, M. (2017) · Advanced Engineering Informatics · doi:10.1016/j.aei.2017.06.001 · Cited by 163
A knowledge-based risk management tool for construction projects using case-based reasoning
Okudan, O., Budayan, C., & Dikmen, I. (2021) · Expert Systems with Applications · doi:10.1016/j.eswa.2021.114776 · Cited by 160
Self-citationReducing Hindrances to Enterprise Risk Management Implementation in Construction Firms
Zhao, X., Hwang, B., Low, S. P., & Wu, P. (2014) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000945 · Cited by 158
Critical success factors for enterprise risk management in Chinese construction companies
Zhao, X., Hwang, B., & Low, S. P. (2013) · Construction Management and Economics · doi:10.1080/01446193.2013.867521 · Cited by 164
“The structural equation modelling (SEM) method has been seen as one of the most suitable techniques for analysing the possible relationships among variables (Eybpoosh et al., 2011).”
MethodA knowledge-based risk mapping tool for cost estimation of international construction projects
Yildiz, A. E., Dikmen, I., Birgonul, M. T., Ercoskun, K., & Alten, S. (2014) · Automation in Construction · doi:10.1016/j.autcon.2014.03.010 · Cited by 126
Self-citationMeasuring Project Management Performance: Case of Construction Industry
Demirkesen, S., & Özorhon, B. (2017) · Engineering Management Journal · doi:10.1080/10429247.2017.1380579 · Cited by 140
“…Almeida, and Dias (2014); Zou, Chen, and Chan (2010); Zhao et al. (2013); Hwang et al. (2014) Risk Analysis Bakker, Boonstra, and Wortmann (2010); Eybpoosh, Dikmen, and Birgonul (2011); Liu et al. (2009); Zhi (1995); Zou et al. (2010) Risk Allocation Hwang et al. (2014); Sousa et al. (2014);…”
Determinants of voluntary carbon disclosure in the corporate real estate sector of Malaysia
Ufere, K. J., Alias, B., & Aliagha, G. U. (2016) · Journal of Environmental Management · doi:10.1016/j.jenvman.2016.08.011 · Cited by 124
Fuzzy based risk assessment module for metropolitan construction project: An empirical study
Samantra, C., Datta, S., & Mahapatra, S. S. (2017) · Engineering Applications of Artificial Intelligence · doi:10.1016/j.engappai.2017.04.019 · Cited by 116
“…pipelines and facilities (F23) Kou and Lu (2013); Zayed et al. (2008) Unstable supply of critical construction materials (F24) Tah and Carr (2000); Eybpoosh et al. (2011); Zayed et al. (2008) Construction Safety-Related (D3) Insufficient protection of adjacent buildings and facilities (F31) Carr…”
BackgroundKhodabakhshian, A., Puolitaival, T., & Kestle, L. (2023) · Buildings · doi:10.3390/buildings13051312 · Cited by 119
From Risk Matrices to Risk Networks in Construction Projects
Qazi, A. J., & Dikmen, İ. (2019) · IEEE Transactions on Engineering Management · doi:10.1109/tem.2019.2907787 · Cited by 109
“That is why managers must realize the importance of modeling risk paths rather than assessing risks in silo [14].”
BackgroundMethodSelf-citationRisk assessment framework of PPP-megaprojects focusing on risk interaction and project success
Ahmadabadi, A. A., & Heravi, G. (2019) · Transportation Research Part A Policy and Practice · doi:10.1016/j.tra.2019.03.011 · Cited by 107
Tavakolan, M., & Etemadinia, H. (2017) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001395 · Cited by 103
A knowledge-based expert system to assess power plant project cost overrun risks
Islam, M. S., Nepal, M. P., Skitmore, M., & Kabir, G. (2019) · Expert Systems with Applications · doi:10.1016/j.eswa.2019.06.030 · Cited by 97
“Structural equation modeling (SEM) can help handle situations involving a large number of risk networks (Lowry & Gaskin, 2014) and has also been used for the risk assessment of power plant projects (Eybpoosh et al., 2011; J. Liu, Xie, Xia, & Bridge, 2017).”
BackgroundKim, S.-Y., & Nguyen, V. T. (2017) · Production Planning & Control · doi:10.1080/09537287.2017.1398846 · Cited by 88
Analysis of interactions among barriers in project risk management
Dandage, R. V., Mantha, S. S., Rane, S. B., & Bhoola, V. (2018) · Journal of Industrial Engineering International · doi:10.1007/s40092-017-0215-9 · Cited by 74
“…(2007); Shuying (2009) 3 Subcontractor Failure of contractor Lam et al. (2007) 4 Operational Low labour and equipment productivity Anderson (2000); Eybpoosh et al. (2011); Ghosh and Jintanapakanont (2004); Ke et al. (2010); Gupta and Sravat (1998) 5 Safety and social (i) Lack of safety…”
BackgroundInfluentialRisk paths in BIM adoption: empirical study of China
Zhao, X., Wu, P., & Wang, X. (2018) · Engineering Construction & Architectural Management · doi:10.1108/ecam-08-2017-0169 · Cited by 85
Methods for Modeling and Evaluating Construction Disputes: A Critical Review
Naji, K. K., Mansour, M. M., & Gündüz, M. (2020) · IEEE Access · doi:10.1109/access.2020.2976109 · Cited by 75
Impact of Design Risk on the Performance of Design-Build Projects
Liu, J., Xie, Q., Xia, B., & Bridge, A. (2017) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001299 · Cited by 84
Zhao, X., & Singhaputtangkul, N. (2016) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000434 · Cited by 71
Agent-based modeling and simulation in architecture
Stieler, D., Schwinn, T., Leder, S., Maierhofer, M., Kannenberg, F., & Menges, A. (2022) · Automation in Construction · doi:10.1016/j.autcon.2022.104426 · Cited by 78
Research on the phenomenon of asymmetric information in construction projects — The case of China
Xiang, P., Huo, X., & Shen, L. (2014) · International Journal of Project Management · doi:10.1016/j.ijproman.2014.10.007 · Cited by 70
Construction risk management research: intellectual structure and emerging themes
Zhao, X. (2023) · International Journal of Construction Management · doi:10.1080/15623599.2023.2167303 · Cited by 92
“SEM was also used to analyze interactions among risks in the form of a risk network (Eybpoosh et al. 2011).”
MethodHwang, B., Zhao, X., & Chin, E. W. Y. (2017) · Engineering Construction & Architectural Management · doi:10.1108/ecam-03-2015-0035 · Cited by 68
Ganbat, T., Chong, H., Liao, P., & Wu, Y.-D. (2018) · Advances in Civil Engineering · doi:10.1155/2018/8351679 · Cited by 72
Dandage, R. V., Mantha, S. S., & Rane, S. B. (2019) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-07-2018-0128 · Cited by 62
Viswanathan, S. K., Tripathi, K. K., & Jha, K. N. (2019) · Construction Management and Economics · doi:10.1080/01446193.2019.1577987 · Cited by 67
Jokar, E., Aminnejad, B., & Lork, A. (2021) · Operations Research Perspectives · doi:10.1016/j.orp.2021.100190 · Cited by 70
Ashtari, M. A., Ansari, R., Hassannayebi, E., & Jeong, J. (2022) · Buildings · doi:10.3390/buildings12101660 · Cited by 65
Theoretical review on critical risk factors in oil and gas construction projects in Yemen
Kassem, M. A., Khoiry, M. A., & Hamzah, N. (2020) · Engineering Construction & Architectural Management · doi:10.1108/ecam-03-2019-0123 · Cited by 64
A simulation-based risk interdependency network model for project risk assessment
Guan, L., Abbasi, A., & Ryan, M. J. (2021) · Decision Support Systems · doi:10.1016/j.dss.2021.113602 · Cited by 65
Ebrat, M., & Ghodsi, R. (2014) · KSCE Journal of Civil Engineering · doi:10.1007/s12205-014-0139-5 · Cited by 58
“17 Eybpoosh et al. (2011) Shortage of materials, Poor contract management, Time and cost overrun, Market-level risks, Project characteristics and contractual Conditions, Change orders 18 Fu-zhou and Hong-yuan (2011) Economic risk, Political risk, Construction risk, Other risks”
BackgroundAssessing project portfolio risk via an enhanced GA-BPNN combined with PCA
Bai, L., Song, C., Zhou, X., Tian, Y., & Wei, L. X. (2023) · Engineering Applications of Artificial Intelligence · doi:10.1016/j.engappai.2023.106779 · Cited by 61
Zhao, X., Feng, Y., Pienaar, J., & O’Brien, D. (2017) · Architectural Science Review · doi:10.1080/00038628.2017.1373628 · Cited by 68
Islam, M. S., Nepal, M. P., & Skitmore, M. (2019) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001593 · Cited by 60
Liu, J., Li, H., Skitmore, M., & Zhang, Y. (2018) · Automation in Construction · doi:10.1016/j.autcon.2018.11.006 · Cited by 64
Ma, G., Wu, Z., Jia, J., & Shang, S. (2021) · Safety Science · doi:10.1016/j.ssci.2021.105410 · Cited by 63
Critical risk factors in international construction projects: An Indian perspective
Viswanathan, S. K., & Jha, K. N. (2020) · Engineering Construction & Architectural Management · doi:10.1108/ecam-04-2019-0220 · Cited by 59
Dikmen, İ., Budayan, C., Birgönül, M. T., & Hayat, E. (2018) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000643 · Cited by 56
Self-citationChen, L., Lu, Q., & Han, D. (2022) · Expert Systems with Applications · doi:10.1016/j.eswa.2022.118810 · Cited by 54
Exploring the Relationship between Complexity and Risk in Megaconstruction Projects
Erol, H., Dikmen, İ., Atasoy, G., & Birgönül, M. T. (2020) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001946 · Cited by 57
Self-citationGebrehiwet, T., & Luo, H. (2018) · Symmetry · doi:10.3390/sym11010012 · Cited by 53
“A26 Inadequate experience of the contractor [19,22,25]”
BackgroundMethodInfluentialAlamdari, A. M., Jabarzadeh, Y., Samson, D., & Sanoubar, N. (2021) · Engineering Construction & Architectural Management · doi:10.1108/ecam-07-2021-0663 · Cited by 61
An analytic network process model for risk quantification of mega construction projects
Erol, H., Dikmen, İ., Atasoy, G., & Birgönül, M. T. (2021) · Expert Systems with Applications · doi:10.1016/j.eswa.2021.116215 · Cited by 52
“that account for the interactions between risk-related concepts (Eybpoosh et al., 2011; Qazi et al., 2016).”
BackgroundSelf-citationBack Analysis of Slope Failure Using Finite Element with Point Estimate Method (FEM-PEM)
Renuka, S. M., Umarani, C., & Kamal, S. (2014) · Journal of Civil Engineering Research · Cited by 54
Mapping Uncertainty for Risk and Opportunity Assessment in Projects
Qazi, A. J., Dikmen, İ., & Birgönül, M. T. (2019) · Engineering Management Journal · doi:10.1080/10429247.2019.1664249 · Cited by 51
Self-citationA Fuzzy-bayesian Model for Risk Assessment in Power Plant Projects
Islam, M. S., & Nepal, M. (2016) · Procedia Computer Science · doi:10.1016/j.procs.2016.09.259 · Cited by 46
Fan, C., Binchao, D., & Yin, Y. (2022) · Engineering Construction & Architectural Management · doi:10.1108/ecam-09-2021-0785 · Cited by 44
A Hybrid Fuzzy TOPSIS – Best Worst Method for Risk Prioritization in Megaprojects
Norouzi, A., & Namin, H. G. (2019) · Civil Engineering Journal · doi:10.28991/cej-2019-03091330 · Cited by 49
“1260 T1 Ambiguity of project scope and its creep during implementation [25, 29, 31-32, 37, 40-41, 42, 48] T2 Delays in design and regulatory approvals [31] T3 Changes in project specifications [31, 40-41, 42] T4 Defective design [29, 31, 34, 37] T5 Engineering and design changes [31, 25] T6 Inappropriate planning and…”
BackgroundAdabre, M. A., Chan, A. P. C., & Darko, A. (2021) · Building and Environment · doi:10.1016/j.buildenv.2021.108487 · Cited by 50
Zhu, F., Hu, H., & Xu, F. (2022) · PLoS ONE · doi:10.1371/journal.pone.0265972 · Cited by 46
Li, G., Zhang, G., Chen, C., & Martek, I. (2020) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001830 · Cited by 41
Risk induced contingency cost modeling for power plant projects
Islam, M. S., Nepal, M. P., Skitmore, M., & Drogemuller, R. (2020) · Automation in Construction · doi:10.1016/j.autcon.2020.103519 · Cited by 41
Afzal, F., Yunfei, S., Junaid, D., & Hanif, M. S. (2020) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-07-2019-0175 · Cited by 46
Factors Influencing Cost Overruns in Construction Projects of International Contractors in Vietnam
Vu, T. Q., Pham, C. P., Nguyen, T. A., Nguyen, P. T., Phan, P. T., & Nguyen, Q. L. H. T. T. (2020) · Journal of Asian Finance Economics and Business · doi:10.13106/jafeb.2020.vol7.no9.389 · Cited by 38
“Eybpoosh, Dikmen, and Birgonul (2011) surveyed 166 projects implemented by Turkish contractors on international mayors with SEM.”
BackgroundMeta-Modeling of Complexity-Uncertainty-Performance Triad in Construction Projects
Dikmen, İ., Qazi, A. J., Erol, H., & Birgönül, M. T. (2020) · Engineering Management Journal · doi:10.1080/10429247.2020.1772698 · Cited by 37
Self-citationZhao, X. (2022) · Engineering Construction & Architectural Management · doi:10.1108/ecam-09-2022-0853 · Cited by 40
Computing Sobol indices in probabilistic graphical models
Ballester‐Ripoll, R., & Leonelli, M. (2022) · Reliability Engineering & System Safety · doi:10.1016/j.ress.2022.108573 · Cited by 36
Dynamic assessment of project portfolio risks from the life cycle perspective
Zhang, B., Bai, L., Zhang, K., Kang, S., & Zhou, X. (2022) · Computers & Industrial Engineering · doi:10.1016/j.cie.2022.108922 · Cited by 36
Project portfolio risk analysis with the consideration of project interdependencies
Bai, L., Shi, H., Kang, S., & Zhang, B. (2021) · Engineering Construction & Architectural Management · doi:10.1108/ecam-06-2021-0555 · Cited by 41
Ganbat, T., Chong, H., Liao, P., & Lee, C.-Y. (2018) · Archives of Computational Methods in Engineering · doi:10.1007/s11831-018-9265-4 · Cited by 36
“Contractual risks are mainly triggered by unclear or unfair contract clauses and conditions [42].”
BackgroundErfani, A., Cui, Q., Baecher, G. B., & Kwak, Y. H. (2023) · IEEE Transactions on Engineering Management · doi:10.1109/tem.2023.3279237 · Cited by 35
Gao, R., Chan, A. P. C., Lyu, S., Zahoor, H., & Utama, W. P. (2018) · Safety Science · doi:10.1016/j.ssci.2018.04.018 · Cited by 34
Yildiz, A. E., Dikmen, İ., & Birgönül, M. T. (2014) · Procedia - Social and Behavioral Sciences · doi:10.1016/j.sbspro.2014.03.058 · Cited by 34
Self-citationMoussa, A., Ezzeldin, M., & El-Dakhakhni, W. W. (2024) · Automation in Construction · doi:10.1016/j.autcon.2024.105836 · Cited by 33
Li, G., Chen, C., Zhang, G., & Martek, I. (2019) · Engineering Construction & Architectural Management · doi:10.1108/ecam-11-2018-0526 · Cited by 33
Utama, W. P., Chan, A. P. C., Zahoor, H., Gao, R., & Jumas, D. Y. (2019) · Engineering Construction & Architectural Management · doi:10.1108/ecam-01-2018-0016 · Cited by 32
Woyessa, A. H., Teshome, M., Mulatu, B., Abadiga, M., Hiko, N., & Kebede, B. (2020) · Open Access Emergency Medicine · doi:10.2147/oaem.s260314 · Cited by 32
Research on the Influence of Risk on Construction Project Performance: A Systematic Review
Guiliang, S., & Khallaf, R. (2022) · Sustainability · doi:10.3390/su14116412 · Cited by 34
Lifecycle cost risk analysis for infrastructure projects with modified Bayesian networks
Xia, N., Wang, X., Wang, Y., Yang, Q., & Liu, X. (2017) · Journal of Engineering Design and Technology · doi:10.1108/jedt-05-2015-0033 · Cited by 34
Zhang, Y., Gu, J., Shan, M., Xiao, Y., & Darko, A. (2018) · Sustainability · doi:10.3390/su10082692 · Cited by 36
“Structural equation modeling (SEM), a multivariate statistical analysis technique that can simultaneously carry out confirmatory factor analysis and path analysis within a single structural equation model, was considered to be one of the most appropriate methods to analyze relationships between latent variables [112,1…”
MethodMultiagent System to Simulate Risk-Allocation and Cost-Sharing Processes in Construction Projects
Karakas, K., Dikmen, İ., & Birgönül, M. T. (2012) · Journal of Computing in Civil Engineering · doi:10.1061/(asce)cp.1943-5487.0000218 · Cited by 28
Self-citationManaging Safety Hazards in Metro Subway Projects under Complex Environmental Conditions
Li, X., Liao, F., Chen, W., & Alashwal, A. M. (2021) · ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems Part A Civil Engineering · doi:10.1061/ajrua6.0001212 · Cited by 29
Wang, T., Gao, S., Liao, P., Ganbat, T., & Chen, J. (2019) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-08-2018-0166 · Cited by 27
Chang, T., Deng, X., & Hwang, B. (2019) · Sustainability · doi:10.3390/su11154157 · Cited by 25
Integrated priority decision index for risk assessment in chaos: cost overruns in transport projects
Afzal, F., Yunfei, S., Sajid, M., & Afzal, F. (2019) · Engineering Construction & Architectural Management · doi:10.1108/ecam-02-2019-0079 · Cited by 27
Shwedeh, F., Yas, N., Abdijabar, Z. G., Flayyih, N., Fadli, A., Yas, H., & Allouzi, A. S. (2024) · Journal of Infrastructure Policy and Development · doi:10.24294/jipd.v8i8.6303 · Cited by 24
“The average extracted variance (AVE) was used to evaluate convergent validity including all dormant structures, reflectors predictors, as well as variable loading requirements (Eybpoosh et al., 2011).”
MethodOdediran, S. J., & Windapo, A. O. (2016) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000485 · Cited by 24
Altuncan, İ. Ü., & Vanhoucke, M. (2024) · European Journal of Operational Research · doi:10.1016/j.ejor.2023.12.029 · Cited by 24
Ogbu, C. P., & Adindu, C. C. (2019) · Journal of Engineering Design and Technology · doi:10.1108/jedt-05-2019-0121 · Cited by 31
Predicting the Impact of Country-Related Risks on Cost Overrun for Overseas Infrastructure Projects
Zhu, F., Hu, H., Xu, F., & Tang, N. (2020) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001959 · Cited by 22
Madihi, M. H., Javid, A. A. S., & Nasirzadeh, F. (2023) · Engineering Construction & Architectural Management · doi:10.1108/ecam-07-2023-0774 · Cited by 21
Ali, Z., Zhu, F., & Hussain, S. (2018) · Sustainability · doi:10.3390/su10114017 · Cited by 21
“In the literature, various studies have applied PLS-SEM to address the risks in projects [45,52,53].”
BackgroundModelling human resource dimension of international project risk management
Dandage, R. V., Rane, S. B., & Mantha, S. S. (2021) · Journal of Global Operations and Strategic Sourcing · doi:10.1108/jgoss-11-2019-0065 · Cited by 21
Chen, Y., Hu, Z., & Liu, Q. (2019) · Journal of Civil Engineering and Management · doi:10.3846/jcem.2019.7462 · Cited by 20
Prioritization of interdependent uncertainties in projects
Qazi, A. J., Dikmen, İ., & Birgönül, M. T. (2020) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-10-2019-0253 · Cited by 21
Self-citationJin, C., Li, B., Ye, Z., & Xiang, P. (2021) · International Journal of Environmental Research and Public Health · doi:10.3390/ijerph18041990 · Cited by 20
“The former can be evaluated explicitly, while the latter is abstract or theoretical constructs derived from the observed variables [51].”
BackgroundResultInfluentialGanbat, T., Chong, H., Liao, P., & Leroy, J. (2019) · Canadian Journal of Civil Engineering · doi:10.1139/cjce-2019-0549 · Cited by 19
“…sources on risk identification that 337 focus on risk management in international construction and EPC projects (Al Maian et al. 2016; 338 Eybpoosh et al. 2011; Pícha et al. 2015; Shen et al. 2017a; and Thweatt and Long 2017), and 339 another study proposes dividing the associate risks…”
BackgroundSafety and security of hospitals during natural disasters: Challenges of disaster managers
Nia, S. P. S., & Kulatunga, U. (2017) · International Journal of Safety and Security Engineering · doi:10.2495/safe-v7-n2-234-246 · Cited by 18
“When facing disaster, health facilities at all levels deserve special attention, in that they must continue to provide patient treatment for those staying in their facilities whilst also treat persons injured by the event [17].”
BackgroundExploring the design risks affecting operation performance of green commercial buildings in China
Li, Y., Fan, L., Zhang, Z., Wei, Z., & Qin, Z. (2022) · Journal of Building Engineering · doi:10.1016/j.jobe.2022.105711 · Cited by 17
Mathew, S. A., Tran, D. Q., & Nguyen, P. H. D. (2021) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0002078 · Cited by 17
Chi, S., Moon, S., & Kim, D. Y. (2021) · KSCE Journal of Civil Engineering · doi:10.1007/s12205-021-0483-1 · Cited by 21
OPEN INNOVATION: SYSTEMATISATION OF KNOWLEDGE EXPLORATION AND EXPLOITATION FOR COMMERCIALISATION
Amponsah, C. T., & Adams, S. (2016) · International Journal of Innovation Management · doi:10.1142/s136391961750027x · Cited by 16
Metadata
- Authors
- Eybpoosh, M., Dikmen, I., & Talat Birgonul, M.
- Affiliations
- Middle East Technical University (TR)
- Research Assistant, Dept. of Civil Engineering, Middle East Technical Univ., 06531, Ankara, Turkey (corresponding author).
- Venue
- Journal of Construction Engineering and Management
- Published
- 2011-12
- Volume
- 137
- Issue
- 12
- Pages
- 1164-1175
- ISSN
- 0733-9364 (ISSN-L)
- 1943-7862
- OpenAlex
- W2085400663
- Semantic Scholar
- 93f3ab82a6bd250cd8b17fed1cf3bd547d09d5e6
- Cited by
- 217
- References
- 57
- Citations by year
- 2026: 9 · 2025: 20 · 2024: 14 · 2023: 16 · 2022: 29 · 2021: 20 · 2020: 17 · 2019: 24 · 2018: 18 · 2017: 17 · 2016: 10 · 2015: 6 · 2014: 10 · 2013: 2 · 2012: 4
- FWCI
- 7.38
- Type
- journal article
- Language
- en
- Open access
- green
- hdl.handle.net
- Licence
- cc-by-nc-nd
- Locations
- Journal of Construction Engineering and Management (publishedVersion)
- OpenMETU (Middle East Technical University) (submittedVersion, cc-by-nc-nd)
- Funders
- Türkiye Bilimsel ve Teknolojik Araştırma Kurumu
- Türkiye Bilimler Akademisi
- Topics
- Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
- Social Sciences › Business, Management and Accounting › Strategy and Management › Value Engineering and Management
- Physical Sciences › Engineering › Building and Construction › BIM and Construction Integration
- Keywords
- construction risk management, international construction projects, risk assessment, cost overruns, vulnerability factors, project environment, risk mitigation strategies
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.