Risk Paths in International Construction Projects: Case Study from Chinese Contractors
Open accessThe DOI matches its Crossref record; 76 of the 76 references it cites were found in a registry or an index.
Abstract
AbstractContracting in overseas construction markets involves not only the typical risks at home, but also the complex and diverse risks peculiar to international transactions. In addition, international construction project risks are highly interdependent. The objectives of this study are to (1) explore the risk paths in the international construction projects performed by Chinese contractors, and (2) examine the risk effects on the objectives of these projects. To achieve the research objectives, a total of 60 risks were identified from literature review and a questionnaire survey was conducted with 104 professionals from Chinese international contractors. Adopting the structural equation modeling technique, this study proposed a networking of 20 significant risk paths. Specifically, host government–related risk, contractor’s lack of experience, and contractors’ lack of managerial skills had significant effect on project cost, quality, and schedule objectives, respectively. Moreover, host government–rel...
Overview
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
Claims other papers make about this one
Each is checked against this paper’s own text: does it say what the citing paper says it does?
In the citing paper
“Ignoring the interdependence of risks can result in an ineffective reflection of the actual risk conditions associated with construction projects. It may provide less reliable risk assessment results for decision-making [4].”
From Cost Overrun Risk Assessment and Prediction in Construction Projects: A Bayesian Network Classifier Approach (2022) · cites this paper as [4]
Citations
Cites
Evaluating Structural Equation Models with Unobservable Variables and Measurement Error
Fornell, C., & Larcker, D. F. (1981) · Journal of Marketing Research · doi:10.2307/3151312 · Cited by 109,314 · cited 1×
“Social risk R20 Language barrier Zhi (1995), Hastak and Shaked (2000), and Han and Diekmann (2001b) R21 Differences in religious or culture tradition Zhi (1995), Han and Diekmann (2001a), Dikmen and Birgonul (2006), Dikmen et al.”
BackgroundEvaluating structural equation models with unobservable variables and measurement error
Fornell, C., & Larcker, D. F. (1981) · Journal of Marketing Research · doi:10.1177/002224378101800104 · Cited by 109,190
Pls-Sem: indeed a silver bullet
Hair, J. F., Ringle, C. M., & Sarstedt, M. (2011) · Journal of Marketing Theory and Practice · doi:10.2753/mtp1069-6679190202 · Cited by 21,631
中華人民共和国国家統計局 (1988) · Medical Entomology and Zoology · Cited by 12,443
Bootstrap Methods and their Application
Davison, A. C., & Hinkley, D. V. (1997) · doi:10.1017/cbo9780511802843 · Cited by 7,350
Modern Methods for Business Research
(1998) · doi:10.4324/9781410604385 · Cited by 6,534
Better Bootstrap Confidence Intervals
Efron, B. (1987) · Journal of the American Statistical Association · doi:10.1080/01621459.1987.10478410 · Cited by 3,364
Megaprojects and Risk: An Anatomy of Ambition
Flyvbjerg, B., Bruzelius, N., & Rothengatter, W. (2003) · Cambridge University Press eBooks · doi:10.1017/cbo9781107050891 · Cited by 2,415
Causes and effects of delays in Malaysian construction industry
Sambasivan, M., & Soon, Y. W. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.11.007 · Cited by 1,422
How to factor-analyze your data right: do’s, don’ts, and how-to’s.
Matsunaga, M. (2010) · International Journal of Psychological Research · doi:10.21500/20112084.854 · Cited by 1,419 · cited 2×
“Country level Macroeconomic risk R01 Fluctuation in currency exchange rates Wang et al. (2004), Dikmen and Birgonul (2006), Dikmen et al.”
Background
Research works printed but not linked: 3
- Cendrowski H., 2009, Enterprise risk management and COSO: A guide for directors, executives, and practitioners
- Patton M. Q., 2001, Qualitative research & evaluation components
- Zou P. X. Zhang G. and Wang J.-Y. (2006). “Identifying key risks in construction projects: Life cycle and stakeholder perspectives.” Pacific Rim Real Estate Society Conf. Univ. of Auckland Business School Auckland New Zealand.
Cited by
Key constraints and mitigation strategies for prefabricated prefinished volumetric construction
Hwang, B.-G., Shan, M., & Looi, K.-Y. (2018) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2018.02.136 · Cited by 318
Qazi, A., Quigley, J., Dickson, A., & Kirytopoulos, K. (2016) · International Journal of Project Management · doi:10.1016/j.ijproman.2016.05.008 · Cited by 294
“Using the same approach, Liu et al. (2016) explored risk paths in international construction projects performed by Chinese contractors and evaluated the impact of risks on project objectives.”
BackgroundZuo, J., Zhao, X., Nguyen, Q. B. M., Ma, T., & Gao, S. (2018) · Engineering, Construction and Architectural Management · doi:10.1108/ecam-01-2016-0016 · Cited by 172
Self-citationRisk Factors That Lead to Time and Cost Overruns of Building Projects in Saudi Arabia
Alshihri, S., Al-Gahtani, K. S., & Almohsen, A. S. (2022) · Buildings · doi:10.3390/buildings12070902 · Cited by 193
“Similar results may be identified in China [59], where client risks and contractor-related risks were identified to be the significant risks.”
ResultAhmadabadi, A. A., & Heravi, G. (2019) · Transport Policy · doi:10.1016/j.tranpol.2018.07.004 · Cited by 166
Afzal, F., Yunfei, S., Nazir, M., & Bhatti, S. M. (2021) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-02-2019-0047 · Cited by 172
Wang, K., Guo, F., Zhang, C., & Schaefer, D. (2022) · Engineering Construction & Architectural Management · doi:10.1108/ecam-05-2022-0383 · Cited by 168
Predicting Project Performance in the Construction Industry
Assaad, R. H., El-adaway, I. H., & Abotaleb, I. S. (2020) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001797 · Cited by 148
Green commercial building projects in Singapore: Critical risk factors and mitigation measures
Hwang, B., Shan, M., & Supa’at, N. N. B. (2017) · Sustainable Cities and Society · doi:10.1016/j.scs.2017.01.020 · Cited by 142
Understanding the Key Risks Affecting Cost and Schedule Performance of Modular Construction Projects
Nabi, M. A., & El-adaway, I. H. (2021) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000917 · Cited by 144
Liao, P., Xia, N., Wu, C., Zhang, X., & Yeh, J.-L. (2017) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2017.04.027 · Cited by 138
Relationship between Project’s Added Value and the Trust–Conflict Interaction among Project Teams
Wu, G., Zhao, X., & Zuo, J. (2017) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000525 · Cited by 121
Self-citationKhodabakhshian, A., Puolitaival, T., & Kestle, L. (2023) · Buildings · doi:10.3390/buildings13051312 · Cited by 119
Risk assessment framework of PPP-megaprojects focusing on risk interaction and project success
Ahmadabadi, A. A., & Heravi, G. (2019) · Transportation Research Part A Policy and Practice · doi:10.1016/j.tra.2019.03.011 · Cited by 107
What Hinders the Development of Green Building? An Investigation of China
Wu, Z., Jiang, M., Cai, Y., Wang, H., & Li, S. (2019) · International Journal of Environmental Research and Public Health · doi:10.3390/ijerph16173140 · Cited by 105
“The second step was to establish a structural equation model (SEM), which is considered to be one of the most suitable techniques for analyzing variables [48].”
MethodAbbasi, O., Noorzai, E., Jafari, K. G., & Golabchi, M. (2020) · Journal of Architectural Engineering · doi:10.1061/(asce)ae.1943-5568.0000431 · Cited by 97
A review of risk management process in construction projects of developing countries
Bahamid, R. A., & Doh, S. I. (2017) · IOP Conference Series Materials Science and Engineering · doi:10.1088/1757-899x/271/1/012042 · Cited by 123
“Risk identification Risk identification can be defined as the process of analytically and constantly identifying, assessing and categorizing the initial importance of the risks related to construction projects [19] and the interrelationships that exists among these risks[20].”
BackgroundPal, R., Wang, P., & Liang, X. (2017) · International Journal of Project Management · doi:10.1016/j.ijproman.2017.05.010 · Cited by 120
Tavakolan, M., & Etemadinia, H. (2017) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001395 · Cited by 103
Shan, M., Le, Y., Yiu, T. W., Chan, A. P. C., & Hu, Y. (2016) · Science and Engineering Ethics · doi:10.1007/s11948-016-9865-z · Cited by 90
“The structural equation modeling method has been deemed to be one of the most suitable techniques for analyzing the possible relationships among variables (Zhao et al. 2013; Liu et al. 2016).”
MethodEffects of inter-organizational conflicts on construction project added value in China
Wu, G., Zhao, X., & Zuo, J. (2017) · International Journal of Conflict Management · doi:10.1108/ijcma-03-2017-0025 · Cited by 94
Self-citationKassem, M. A., Khoiry, M. A., & Hamzah, N. (2020) · Engineering Construction & Architectural Management · doi:10.1108/ecam-10-2019-0573 · Cited by 92
Risk paths in BIM adoption: empirical study of China
Zhao, X., Wu, P., & Wang, X. (2018) · Engineering Construction & Architectural Management · doi:10.1108/ecam-08-2017-0169 · Cited by 85
Self-citationEffects of team diversity on project performance in construction projects
Wu, G., Zhao, X., Zuo, J., & Zillante, G. (2019) · Engineering Construction & Architectural Management · doi:10.1108/ecam-05-2018-0220 · Cited by 89
Self-citationImpact of Design Risk on the Performance of Design-Build Projects
Liu, J., Xie, Q., Xia, B., & Bridge, A. (2017) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001299 · Cited by 84
“From a risk-based perspective, project delivery methods are, at their core, vehicles for risk distribution 58 between contractual parties (Tran and Molenaar 2015; Liu et al. 2016a).”
BackgroundSelf-citationShan, M., Hwang, B., & Wong, K. S. N. (2017) · Tunnelling and Underground Space Technology · doi:10.1016/j.tust.2017.07.004 · Cited by 74
Understanding Collusive Practices in Chinese Construction Projects
Shan, M., Chan, A. P. C., Le, Y., Hu, Y., & Xia, B. (2016) · Journal of Professional Issues in Engineering Education and Practice · doi:10.1061/(asce)ei.1943-5541.0000314 · Cited by 70
“Therefore, this 203 study employed purposive sampling, a typical type of nonprobability sampling approach that 204 can also help obtain a representative sample (Liu et al. 2016; Trochim 2006; Zhao et al. 2015).”
MethodConstruction risk management research: intellectual structure and emerging themes
Zhao, X. (2023) · International Journal of Construction Management · doi:10.1080/15623599.2023.2167303 · Cited by 92
“The earliest document by Fornell and Larcker (1981) was focussed on structural equation modelling (SEM), which was used as a method for analyzing interdependencies among risks international construction projects (Liu et al. 2016).”
MethodSelf-citationGanbat, T., Chong, H., Liao, P., & Wu, Y.-D. (2018) · Advances in Civil Engineering · doi:10.1155/2018/8351679 · Cited by 72
Viswanathan, S. K., Tripathi, K. K., & Jha, K. N. (2019) · Construction Management and Economics · doi:10.1080/01446193.2019.1577987 · Cited by 67
“The sample size of 105 is comparable or larger than in previous similar studies by Liu et al. (2016), Ozorhon et al. (2008) and Wong and Cheung (2005).”
BackgroundResultInfluentialJokar, E., Aminnejad, B., & Lork, A. (2021) · Operations Research Perspectives · doi:10.1016/j.orp.2021.100190 · Cited by 70
Ashtari, M. A., Ansari, R., Hassannayebi, E., & Jeong, J. (2022) · Buildings · doi:10.3390/buildings12101660 · Cited by 65
Liu, J., Cui, Z., Feng, Y., Perera, S., & Han, J. H. (2020) · Engineering Construction & Architectural Management · doi:10.1108/ecam-02-2019-0111 · Cited by 85
Self-citationTheoretical review on critical risk factors in oil and gas construction projects in Yemen
Kassem, M. A., Khoiry, M. A., & Hamzah, N. (2020) · Engineering Construction & Architectural Management · doi:10.1108/ecam-03-2019-0123 · Cited by 64
Which Risk Management Is Most Crucial for Controlling Project Cost?
Jung, W., & Han, S. H. (2017) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000547 · Cited by 68
Zhao, X., Feng, Y., Pienaar, J., & O’Brien, D. (2017) · Architectural Science Review · doi:10.1080/00038628.2017.1373628 · Cited by 68
“The number of the practitioners was adequate, comparable to previous studies of a similar nature, such as Deng et al. (2014a) and Liu, Zhao, and Yan (2016a).”
ResultSelf-citationPrioritizing Construction Risks Using Fuzzy AHP in Brazilian Public Enterprises
Beltrão, L. M. P., & Carvalho, M. T. M. (2018) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001606 · Cited by 66
A statistical approach to assess the schedule delays and risks in Indian construction industry
Muneeswaran, G., Manoharan, P. D., Awoyera, P. O., & Adesina, A. (2018) · International Journal of Construction Management · doi:10.1080/15623599.2018.1484991 · Cited by 60
“In other related studies, risk assessment models were developed using factors that have been identified to influence the smooth completion of a project (Subramanyan et al. 2012; El-Sayegh and Mansour 2015; Liu et al. 2016).”
BackgroundLiu, J., Li, H., Skitmore, M., & Zhang, Y. (2018) · Automation in Construction · doi:10.1016/j.autcon.2018.11.006 · Cited by 64
Self-citationFuzzy Logic–Based Method for Risk Assessment of Belt and Road Infrastructure Projects
Andrić, J. M., Wang, J., Zou, P. X. W., Zhang, J., & Zhong, R. (2019) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001721 · Cited by 60
Critical risk factors in international construction projects: An Indian perspective
Viswanathan, S. K., & Jha, K. N. (2020) · Engineering Construction & Architectural Management · doi:10.1108/ecam-04-2019-0220 · Cited by 59
Ma, G., Wu, Z., Jia, J., & Shang, S. (2021) · Safety Science · doi:10.1016/j.ssci.2021.105410 · Cited by 63
Risk allocation in public construction projects: the case of Jordan
Hiyassat, M., Alkasagi, F., El-Mashaleh, M. S., & Sweis, G. J. (2020) · International Journal of Construction Management · doi:10.1080/15623599.2020.1728605 · Cited by 57
“…with unclear clauses and conditions, design error, and change in design were major risk factors reported by (El-adaway 2008; Heravi and Hajihosseini 2012; Goh et al. 2013; Zhang and Bai 2013; Sarvari et al. 2014; Bu-Qammaz, 2015; El-Sayegh and Mansour 2015; Liu et al. 2016; Wang et al. 2016).”
BackgroundInfluentialEtemadinia, H., & Tavakolan, M. (2018) · International Journal of Construction Management · doi:10.1080/15623599.2018.1511235 · Cited by 56
Identifying Political Risk Management Strategies in International Construction Projects
Chang, T., Hwang, B., Deng, X., & Zhao, X. (2018) · Advances in Civil Engineering · doi:10.1155/2018/1016384 · Cited by 64
Self-citationDikmen, İ., Budayan, C., Birgönül, M. T., & Hayat, E. (2018) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000643 · Cited by 56
Chen, L., Lu, Q., & Han, D. (2022) · Expert Systems with Applications · doi:10.1016/j.eswa.2022.118810 · Cited by 54
Yuan, T., Xiang, P., Huaiyin, L., & Zhang, L. (2020) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2020.122904 · Cited by 57
Exploring the Relationship between Complexity and Risk in Megaconstruction Projects
Erol, H., Dikmen, İ., Atasoy, G., & Birgönül, M. T. (2020) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001946 · Cited by 57
Human Safety Risks and Their Interactions in China’s Subways: Stakeholder Perspectives
Wang, X., Xia, N., Zhang, Z., Wu, C., & Liu, B. (2017) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000544 · Cited by 47
Chen, H., Zhang, L., & Wu, X. (2020) · Applied Soft Computing · doi:10.1016/j.asoc.2020.106413 · Cited by 47
Kumar, V., Pandey, A., & Singh, R. (2023) · Organization Technology and Management in Construction An International Journal · doi:10.2478/otmcj-2023-0001 · Cited by 55
“…Nguyen et al. 2004; Phua and Rowlinson 2004; Fortune and White 2006; Inayat et al. 2015; Kog and Loh 2012; Gupta et al. 2013; Hwang and Lim 2013; Liu et al. 2016; Maghsoodi and Khalilzadeh 2017; Asgari et al. 2018; Langston et al. 2018; Maqbool and Sudong 2018; Moradi et al. 2020; Negash and…”
Adabre, M. A., Chan, A. P. C., & Darko, A. (2021) · Building and Environment · doi:10.1016/j.buildenv.2021.108487 · Cited by 50
Zhu, F., Hu, H., & Xu, F. (2022) · PLoS ONE · doi:10.1371/journal.pone.0265972 · Cited by 46
Li, G., Zhang, G., Chen, C., & Martek, I. (2020) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001830 · Cited by 41
Liu, J., Yang, P., Xia, B., & Skitmore, M. (2017) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001350 · Cited by 43
“The final response rate of 27.11% is acceptable compared with the 20%–30% recovery rate for most construction industry questionnaire surveys of this kind (Akintoye, 2000, Liu et al., 2016).”
ResultSelf-citationAfzal, F., Yunfei, S., Junaid, D., & Hanif, M. S. (2020) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-07-2019-0175 · Cited by 46
Success factors for implementing Uganda’s public road construction projects
Mwelu, N., Davis, P. R., Ke, Y., Watundu, S., & Jefferies, M. C. (2019) · International Journal of Construction Management · doi:10.1080/15623599.2019.1573481 · Cited by 44
“Smart-PLS3 software has robust techniques in handling non-normal data, simultaneous analysis and suitable for small samples compared to Covariance Based Structural Equation Modeling (CBSEM) (Liu et al. 2016).”
MethodZhao, X. (2022) · Engineering Construction & Architectural Management · doi:10.1108/ecam-09-2022-0853 · Cited by 40
Self-citationGanbat, T., Chong, H., Liao, P., & Lee, C.-Y. (2018) · Archives of Computational Methods in Engineering · doi:10.1007/s11831-018-9265-4 · Cited by 36
Chang, T., Deng, X., Hwang, B., & Zhao, X. (2019) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001738 · Cited by 34
Self-citationDEVELOPING A COMPREHENSIVE RISK ASSESSMENT MODEL BASED ON FUZZY BAYESIAN BELIEF NETWORK (FBBN)
Guan, L., Liu, Q., Abbasi, A., & Ryan, M. J. (2020) · Journal of Civil Engineering and Management · doi:10.3846/jcem.2020.12322 · Cited by 34
“, 2016) and inadequate skill and expertise (Liu et al., 2016) in ICP contractors, the implementation of ICPs generally has a higher risk exposure and greater challenges than DCPs.”
BackgroundInfluentialMirpanahi, M. V., & Noorzai, E. (2021) · Journal of Architectural Engineering · doi:10.1061/(asce)ae.1943-5568.0000512 · Cited by 34
Amirtash, P., Jalal, M. P., & Jelodar, M. B. (2021) · Built Environment Project and Asset Management · doi:10.1108/bepam-06-2020-0106 · Cited by 32
Assessing the Impact of Construction Risks on Cost Overruns: A Risk Path Simulation–Driven Approach
Elbashbishy, T. S., Hosny, O. A., Waly, A. F., & Dorra, E. M. (2022) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0001090 · Cited by 32
Mapping BIM Uses for Risk Mitigation in International Construction Projects
Ganbat, T., Chong, H., & Liao, P. (2020) · Advances in Civil Engineering · doi:10.1155/2020/5143879 · Cited by 31
“[28] Santoso and soeng [31] F57 insufficient safety material and equipment Yildiz et al.”
BackgroundZhang, Y., Gu, J., Shan, M., Xiao, Y., & Darko, A. (2018) · Sustainability · doi:10.3390/su10082692 · Cited by 36
“It is noteworthy that the sample size and response rate were sufficient for conducting statistical analyses [70,110,111].”
Malek, M. S., & Bhatt, V. (2023) · Engineering Construction & Architectural Management · doi:10.1108/ecam-12-2022-1166 · Cited by 33
Understanding the CSR Awareness of Large Construction Enterprises in China
Xie, L., Xu, T., Le, Y., Chen, Q., Xia, B., & Skitmore, M. (2020) · Advances in Civil Engineering · doi:10.1155/2020/8866511 · Cited by 32
Wang, T., Gao, S., Liao, P., Ganbat, T., & Chen, J. (2019) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-08-2018-0166 · Cited by 27
Development of Risk Quantification Models in Road Infrastructure Projects
Senić, A., Đobrodolac, M., & Stojadinović, Z. (2024) · Sustainability · doi:10.3390/su16177694 · Cited by 26
The prediction of potential risk path in railway traffic events
Gu, S., Li, K., Feng, T., Yan, D., & Liu, Y. (2022) · Reliability Engineering & System Safety · doi:10.1016/j.ress.2022.108409 · Cited by 26
Entry Mode Taxonomy and Choice of Chinese International Construction Companies
Jia, R., Li, Q., Deng, X., Zhao, X., & Yuan, J. (2016) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000506 · Cited by 31
Self-citationIyer, K. C., Kumar, R., & Singh, S. P. (2019) · Construction Management and Economics · doi:10.1080/01446193.2019.1590614 · Cited by 30
“Papers published as a case study research but using only expert opinion (e.g. Liu et al. 2016) were excluded.”
BackgroundMethodChang, T., Deng, X., & Hwang, B. (2019) · Sustainability · doi:10.3390/su11154157 · Cited by 25
Integrated priority decision index for risk assessment in chaos: cost overruns in transport projects
Afzal, F., Yunfei, S., Sajid, M., & Afzal, F. (2019) · Engineering Construction & Architectural Management · doi:10.1108/ecam-02-2019-0079 · Cited by 27
Applying a new systematic fuzzy FMEA technique for risk management in light steel frame systems
Yeganeh, A., Heravi, M. Y., Razavian, S. B., Behzadian, K., & Shariatmadar, H. (2021) · Journal of Asian Architecture and Building Engineering · doi:10.1080/13467581.2021.1971994 · Cited by 24
“Therefore, a clear prerequisite for identifying project risks is a clear understanding of the project objectives (Liu, Zhao, and Yan 2016).”
BackgroundRisk Perception-Based Project Contingency Management Framework
Ottaviani, F. M., Castelblanco, G., Marco, A. D., & Rafele, C. (2024) · Systems · doi:10.3390/systems12030093 · Cited by 29
Modelling residual value risk through ontology to address vulnerability of PPP project system
Yuan, J., Li, X., Chen, K., & Skibniewski, M. J. (2018) · Advanced Engineering Informatics · doi:10.1016/j.aei.2018.10.009 · Cited by 24
“Liu et al. [33] analyzed risk paths for international engineering projects from the viewpoint of Chinese contractors and assessed the risk impacts through structural equation modelling (SEM).”
BackgroundMethodThe Drivers and Performance of Environmental Practices in the Chinese Construction Industry
Li, Y., Ding, R., & Sun, T. (2019) · Sustainability · doi:10.3390/su11030614 · Cited by 24
Go/No-Go Decision Model for Owners Using Exhaustive CHAID and QUEST Decision Tree Algorithms
Gündüz, M., & Lutfi, H. M. A. (2021) · Sustainability · doi:10.3390/su13020815 · Cited by 24
Abdalla, A., Li, X., & Yang, F. (2024) · Journal of Construction Engineering and Management · doi:10.1061/jcemd4.coeng-13912 · Cited by 24
Ashmawi, K., Hadidi, L. A., Assaf, S., Tuffaha, F. M., & Al-Ofi, K. A. (2018) · Cogent Engineering · doi:10.1080/23311916.2018.1490148 · Cited by 23
“Liu, Zhao, and Yan (2016) explored the risk paths in the international construction projects performed by Chinese contractors, and examined the risk effects on the objectives of these projects.”
BackgroundRisk response incorporating risk preferences in international construction projects
Peng, Y., Liu, J., Zhao, X., & Skitmore, M. (2021) · Engineering Construction & Architectural Management · doi:10.1108/ecam-03-2019-0132 · Cited by 23
Self-citationAltuncan, İ. Ü., & Vanhoucke, M. (2024) · European Journal of Operational Research · doi:10.1016/j.ejor.2023.12.029 · Cited by 24
Project risk analysis based on project characteristics
Shishodia, A., Dixit, V., & Verma, P. (2018) · Benchmarking An International Journal · doi:10.1108/bij-06-2017-0151 · Cited by 28
Identification of Risk in Green Building Projects based on the Perspective of Sustainability
Xiang, T., & Xiang-Yuan, S. (2018) · IOP Conference Series Materials Science and Engineering · doi:10.1088/1757-899x/439/3/032053 · Cited by 22
Predicting the Impact of Country-Related Risks on Cost Overrun for Overseas Infrastructure Projects
Zhu, F., Hu, H., Xu, F., & Tang, N. (2020) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001959 · Cited by 22
Askarifard, M., Abbasianjahromi, H., Sepehri, M., & Zeighami, E. (2021) · Environment Development and Sustainability · doi:10.1007/s10668-020-01123-z · Cited by 22
A data aggregation-based spatiotemporal model for rail transit risk path forecasting
Xue, G., Liu, S., Ren, L., & Gong, D. (2023) · Reliability Engineering & System Safety · doi:10.1016/j.ress.2023.109530 · Cited by 21
Madihi, M. H., Javid, A. A. S., & Nasirzadeh, F. (2023) · Engineering Construction & Architectural Management · doi:10.1108/ecam-07-2023-0774 · Cited by 21
Jin, C., Li, B., Ye, Z., & Xiang, P. (2021) · International Journal of Environmental Research and Public Health · doi:10.3390/ijerph18041990 · Cited by 20
“Previous research has pointed out that breaking risk chains in risk networks is an important tool for risk prevention [26].”
BackgroundResultKhalilzadeh, M., Banihashemi, S. A., & Božanić, D. I. (2024) · Decision Making Applications in Management and Engineering · doi:10.31181/dmame712024884 · Cited by 21
Ganbat, T., Chong, H., Liao, P., & Leroy, J. (2019) · Canadian Journal of Civil Engineering · doi:10.1139/cjce-2019-0549 · Cited by 19
“128 Risks should not be segmented and managed independently because of their dynamic and 129 highly interdependent nature (Liu et al. 2016b).”
BackgroundInfluentialRisk-Based Metanetwork Modeling for Sustainable Project Performance in International Construction
Liu, M., Chong, H., Liao, P., & Ganbat, T. (2021) · Journal of Infrastructure Systems · doi:10.1061/(asce)is.1943-555x.0000617 · Cited by 18
Guan, L., Abbasi, A., Ryan, M. J., & Merigó, J. M. (2025) · Computers & Industrial Engineering · doi:10.1016/j.cie.2025.110921 · Cited by 18
Auditing Construction Cost from an In-Process Perspective Based on a Bayesian Predictive Model
Wang, P., Wang, K., Huang, Y., Fenn, P., & Stewart, I. (2022) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0002253 · Cited by 17
Wang, P., Wang, K., Huang, Y., & Fenn, P. (2023) · Engineering Construction & Architectural Management · doi:10.1108/ecam-11-2022-1104 · Cited by 17
Muzafar, S. A., Ali, K., Kassem, M. A., & Khoiry, M. A. (2023) · Buildings · doi:10.3390/buildings13040963 · Cited by 11
A three-staged framework for measuring water supply resilience in rural China based on PLS-SEM
Zhou, W., Kalonji, G., Chen, C., Zheng, H., & Martek, I. (2022) · Scientific Reports · doi:10.1038/s41598-022-08112-4 · Cited by 16
Metadata
- Authors
- Liu, J., Zhao, X., & Yan, P.
- Affiliations
- Tianjin University (CN)
- Central Queensland University (AU)
- Ph.D. Candidate, Dept. of Construction Management, College of Management and Economics, Tianjin Univ., 92 Weijin Rd., Tianjin 300072, China (corresponding author).
- Venue
- Journal of Construction Engineering and Management
- Published
- 2016-06
- Volume
- 142
- Issue
- 6
- ISSN
- 0733-9364 (ISSN-L)
- 1943-7862
- OpenAlex
- W2238965708
- Semantic Scholar
- c0731e4b929c2d8301d2da4f89a0f833101295be
- Cited by
- 203
- References
- 74
- Citations by year
- 2026: 7 · 2025: 20 · 2024: 17 · 2023: 28 · 2022: 18 · 2021: 21 · 2020: 23 · 2019: 24 · 2018: 20 · 2017: 20 · 2016: 5
- FWCI
- 25.20
- Type
- journal article
- Language
- en
- Open access
- green
- figshare.com
- Licence
- cc-by
- Locations
- Journal of Construction Engineering and Management (publishedVersion)
- Acquire (CQUniversity) (submittedVersion)
- Figshare (submittedVersion, cc-by)
- Funders
- National Science Foundation
- Topics
- Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
- Physical Sciences › Engineering › Building and Construction › BIM and Construction Integration
- Social Sciences › Business, Management and Accounting › Strategy and Management › Public-Private Partnership Projects
- Keywords
- international construction projects, Chinese contractors, contractor experience, management skills, project cost performance, project quality, project schedule, productivity, risk interrelationships
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.