How common and how large are cost overruns in transport infrastructure projects?
The DOI matches its Crossref record; 17 of the 17 references it cites were found in a registry or an index.
Abstract
Despite the hundreds of billions of dollars being spent on infrastructure development -- from roads, rail and airports to energy extraction and power networks to the Internet -- surprisingly little reliable knowledge exists about the performance of these investments in terms of actual costs, benefits and risks. This paper presents results from the first statistically significant study of cost performance in transport infrastructure projects. The sample used is the largest of its kind, covering 258 projects in 20 nations worth approximately US$90 billion (constant 1995 prices). The paper shows with overwhelming statistical significance that in terms of costs transport infrastructure projects do not perform as promised. The conclusion is tested for different project types, different geographical regions and different historical periods. Substantial cost escalation is the rule rather than the exception. For rail, average cost escalation is 45% (SD=38), for fixed links (tunnels and bridges) it is 34% (62) and for roads 20% (30). Cost escalation appears a global phenomenon, existing across 20 nations on five continents. Cost estimates have not improved and cost escalation not decreased over the past 70 years. Cost estimates used in decision-making for transport infrastructure development are highly, systematically and significantly misleading. Large cost escalations combined with large standard deviations translate into large financial risks. However, such risks are typically ignored or underplayed in decision-making, to the detriment of social and economic welfare.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Globalization: The Human Consequences
Bauman, Z. (1998) · Medical Entomology and Zoology · Cited by 3,914
Megaprojects and Risk: An Anatomy of Ambition
Flyvbjerg, B., Bruzelius, N., & Rothengatter, W. (2003) · Cambridge University Press eBooks · doi:10.1017/cbo9781107050891 · Cited by 2,415
Self-citationRationality and Power: Democracy in Practice.
Jasper, J. M., & Flyvbjerg, B. (1999) · Social Forces · doi:10.2307/3005579 · Cited by 1,531
Self-citationThe Death of Distance: How the Communications Revolution Will Change Our Lives
Cohen, E. A., & Cairncross, F. (1997) · Foreign Affairs · doi:10.2307/20048298 · Cited by 1,462
Underestimating Costs in Public Works Projects:Error or Lie?
Flyvbjerg, B., Holm, M. S., & Buhl, S. (2002) · Journal of the American Planning Association · doi:10.1080/01944360208976273 · Cited by 1,046
Self-citationWorld development report 1994 : infrastructure for development
Lanjouw, P., Besant-Jones, J. E., Estache, A., Kessides, C., Pritchett, L. H., Mody, A., & Ingram, G. K. (1994) · Dépôt institutionnel de l'Université libre de Bruxelles (Université Libre de Bruxelles) · Cited by 937
Bank, W. (1994) · doi:10.1596/978-0-1952-0992-1 · Cited by 643
Hall, P. (1980) · Futures · doi:10.1016/s0016-3287(80)80006-1 · Cited by 580
The Death of Distance ‐ How the Communications Revolution will Change Our Lives
(1998) · International Marketing Review · doi:10.1108/imr.1998.15.4.309.1 · Cited by 346
A Desire Named Streetcar Fantasy and Fact in Rail Transit Planning
Pickrell, D. H. (1992) · Journal of the American Planning Association · doi:10.1080/01944369208975791 · Cited by 321
Cited by
How (In)accurate Are Demand Forecasts in Public Works Projects?: The Case of Transportation
Flyvbjerg, B., Skamris Holm, M. K., & Buhl, S. L. (2005) · Journal of the American Planning Association · doi:10.1080/01944360508976688 · Cited by 731
Self-citationOlawale, Y. A., & Sun, M. (2010) · Construction Management and Economics · doi:10.1080/01446191003674519 · Cited by 478
What Causes Cost Overrun in Transport Infrastructure Projects?
FLYVBJERG, B., SKAMRIS HOLM, M. K., & BUHL, S. L. (2004) · Transport Reviews · doi:10.1080/0144164032000080494a · Cited by 455
Self-citationFactors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects
Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2016) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000391 · Cited by 365
Recent Developments in Bus Rapid Transit: A Review of the Literature
Deng, T., & Nelson, J. D. (2011) · Transport Reviews · doi:10.1080/01441647.2010.492455 · Cited by 311
Denicol, J., Davies, A., & Krystallis, I. (2020) · Project Management Journal · doi:10.1177/8756972819896113 · Cited by 266
Cantarelli, C. C., Flyvbjerg, B., Molin, E. J. E., & Wee, B. V. (2010) · European Journal of Transport and Infrastructure Research · doi:10.18757/ejtir.2010.10.1.2864 · Cited by 251
“Finally, one of the leading pieces of research in the field of cost overruns in large transportation infrastructure projects is by Flyvbjerg et al. (2003a).”
Self-citationPublic Procurement in Law and Practice
Bosio, E., Djankov, S., Glaeser, E., & Shleifer, A. (2022) · American Economic Review · doi:10.1257/aer.20200738 · Cited by 237
RETRACTED: Inaccuracy in Traffic Forecasts
Flyvbjerg, B., Skamris Holm, M. K., & Buhl, S. L. (2006) · Transport Reviews · doi:10.1080/01441640500124779 · Cited by 220
Self-citationRetractedCost overrun in the Malaysian construction industry projects: A deeper insight
Shehu, Z., Endut, I. R., Akintoye, A., & Holt, G. D. (2014) · International Journal of Project Management · doi:10.1016/j.ijproman.2014.04.004 · Cited by 210
“Approximately 45% of projects were completed at or below contract sum; the remainder overran — supporting extant literature stating that negative variance is more common than positive variance (Flyvbjerg et al., 2003; Morris and Hough, 1987; Skamris and Flyvbjerg, 1997).”
BackgroundSignificant Factors Causing Cost Overruns in Large Construction Projects in Malaysia
Rahman, I. A., Hameed Mem, A., & Abd. Karim, A. T. (2013) · Journal of Applied Sciences · doi:10.3923/jas.2013.286.293 · Cited by 193
Giezen, M. (2012) · International Journal of Project Management · doi:10.1016/j.ijproman.2012.01.010 · Cited by 188
“Cost escalations happen in almost nine out of ten projects with a cost increase of 28 per cent on average (Flyvbjerg et al., 2003).”
BackgroundPark, Y., & Papadopoulou, T. C. (2012) · Built Environment Project and Asset Management · doi:10.1108/20441241211280873 · Cited by 91
The cost performance and causes of overruns in infrastructure development projects in Asia
Andrić, J. M., Mahamadu, A.-M., Wang, J., Zou, P. X. W., & Zhong, R. (2019) · Journal of Civil Engineering and Management · doi:10.3846/jcem.2019.8646 · Cited by 61
A Quantitative Analysis of the Performance of Transportation Projects in Developing Countries
Gamez, E. A., & Touran, A. (2010) · Transport Reviews · doi:10.1080/01441640903034070 · Cited by 11
“Touran been a concern in the past when project data has been collected from questionnaires or surveys and not from their original sources (Flyvbjerg et al., 2003).”
BackgroundInfluential
Metadata
- Authors
- Flyvbjerg, B., Skamris holm, M. K., & Buhl, S. L.
- Venue
- Transport Reviews
- Publisher
- Informa UK Limited
- Published
- 2003-01
- Volume
- 23
- Issue
- 1
- Pages
- 71-88
- ISSN
- 0144-1647 (ISSN-L)
- 1464-5327
- OpenAlex
- W2104091263
- Cited by
- 783
- References
- 17
- FWCI
- 11.10
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.