Determining the causal structure of rework influences in construction
The DOI matches its Crossref record; 33 of the 33 references it cites were found in a registry or an index.
Abstract
One of the most perplexing issues facing organizations in the construction industry is their inability to become quality focused. As a result sub-standard products and services often emanate, which inadvertently result in rework. Typically, rework is caused by errors made during the design process. These errors appear downstream in the procurement process and therefore have a negative impact on a project's performance. The lack of attention to quality, especially during the design process, has meant that rework has become an inevitable feature of the procurement process, and the costs have been found to be as high as 12.4% of total project costs. Such costs could be even higher because they do not represent schedule delays, litigation costs and other intangible costs of poor quality. To reduce the cost and effect of rework, an understanding of its causal structure is needed so that effective prevention strategies can be identified and the effects of rework reduced or eliminated. A case study approach based upon deductive and inductive reasoning is used to identify the major factors that influence rework in projects. From the findings and with reference to recent literature, the concept of system dynamics is used to develop a series of influence diagrams, which are then integrated to develop a conceptual causal loop model that is used to determine the overall causal structure of rework. Once an understanding of the causal structure of rework events has been acquired, effective strategies for rework prevention can be designed and implemented in order to improve project performance. This paper contributes to study of quality in construction by capturing the complexity and dynamism of those factors that influence rework and project performance in a holistic manner.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
(1984) · Cited by 81,983
The Discovery of Grounded Theory: Strategies for Qualitative Research.
Wagner, H. R., Glaser, B. G., & Strauss, A. L. (1968) · Social Forces · doi:10.2307/2575405 · Cited by 46,361
The Discovery of Grounded Theory: Strategies for Qualitative Research
Glaser, B. G., & Strauss, A. L. (2017) · Aldine (Routledge reprint) · doi:10.4324/9780203793206 · Cited by 25,789
The fifth discipline, the art and practice of the learning organization
Senge, P. M. (1991) · Performance + Instruction · doi:10.1002/pfi.4170300510 · Cited by 20,060
Building Theories from Case Study Research
Eisenhardt, K. M. (1989) · The Academy of Management Review · doi:10.2307/258557 · Cited by 17,455
Qualitative Data Analysis: A Sourcebook of New Methods
Lotto, L. S., Miles, M. B., & Huberman, A. M. (1986) · Educational Evaluation and Policy Analysis · doi:10.2307/1163741 · Cited by 10,315
Deming, W. E. (1982) · Medical Entomology and Zoology · Cited by 7,297
Mixing Qualitative and Quantitative Methods: Triangulation in Action.
Jick, T. D. (1979) · Administrative Science Quarterly · doi:10.2307/2392366 · Cited by 7,103
Systems Thinking, Systems Practice
Checkland, P. B. (1981) · Cumulative Index of Computer Aided Architectural Design · Cited by 6,256
Systems thinking, systems practice
(1982) · European Journal of Operational Research · doi:10.1016/0377-2217(82)90206-5 · Cited by 3,545
Cited by
Simulation in manufacturing and business: A review
Jahangirian, M., Eldabi, T., Naseer, A., Stergioulas, L. K., & Young, T. (2010) · European Journal of Operational Research · doi:10.1016/j.ejor.2009.06.004 · Cited by 598
Quantifying the causes and costs of rework in construction
Love, P. E. D., & Li, H. (2000) · Construction Management and Economics · doi:10.1080/01446190050024897 · Cited by 486
Self-citationInfluence of Project Type and Procurement Method on Rework Costs in Building Construction Projects
Love, P. E. D. (2002) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2002)128:1(18 · Cited by 463
Self-citationMeasuring the Impact of Rework on Construction Cost Performance
Hwang, B.-G., Thomas, S. R., Haas, C. T., & Caldas, C. H. (2009) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2009)135:3(187 · Cited by 352
Taxonomy for change causes and effects in construction projects
Sun, M., & Meng, X. (2009) · International Journal of Project Management · doi:10.1016/j.ijproman.2008.10.005 · Cited by 331
Love, P. E. D., Holt, G. D., Shen, L. Y., Li, H., & Irani, Z. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(01)00039-4 · Cited by 316
Self-citationA fuzzy synthetic evaluation approach for risk assessment: a case of Singapore's green projects
Zhao, X., Hwang, B.-G., & Gao, Y. (2016) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2015.11.042 · Cited by 279
Perspectives on iteration in design and development
Wynn, D. C., & Eckert, C. M. (2017) · Research in Engineering Design · doi:10.1007/s00163-016-0226-3 · Cited by 222
Illustrative Benchmarking Rework and Rework Costs in Swedish Construction Industry
Josephson, P.-E., Larsson, B., & Li, H. (2002) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(2002)18:2(76 · Cited by 214
Self-citationRelationship between Construction Safety and Quality Performance
Wanberg, J., Harper, C., Hallowell, M. R., & Rajendran, S. (2013) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000732 · Cited by 196
“In summary, rework can result from errors, omissions, failures, damage, and change orders throughout the procurement process (Love et al. 1999; Love and Li 2000).”
BackgroundHan, S., Saba, F., Lee, S., Mohamed, Y., & Peña-Mora, F. (2014) · Accident Analysis & Prevention · doi:10.1016/j.aap.2013.10.007 · Cited by 182
“The rework-schedule delay loop (R1) in turn indicates how ework leads to schedule delays, which causes production presure (Rodrigues and Williams, 1998; Love et al., 1999; Park and eña-Mora, 2003) that leads to an increase in errors (Mitropoulos nd Cupido, 2009) and produces further rework.”
BackgroundInfluentialTotal quality management and the learning organization: a dialogue for change in construction
Love, P. E. D., Li, H., Irani, Z., & Faniran, O. (2000) · Construction Management and Economics · doi:10.1080/014461900370681 · Cited by 182
“However, research undertaken by Love et al. (1999a) found that the factors that caused these errors were interrelated, and that a low design fee was simply a symptom of poor management practices.”
BackgroundMethodSelf-citationAnalyzing Causes for Reworks in Construction Projects in China
Ye, G., Jin, Z., Xia, B., & Skitmore, M. (2015) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000347 · Cited by 178
Metadata
- Authors
- LOVE, P. E. D., MANDAL, P., & LI, H.
- Venue
- Construction Management and Economics
- Publisher
- Informa UK Limited
- Published
- 1999-07
- Volume
- 17
- Issue
- 4
- Pages
- 505-517
- ISSN
- 0144-6193 (ISSN-L)
- 1466-433X
- OpenAlex
- W1967311507
- Cited by
- 211
- References
- 33
- FWCI
- 8.80
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.