Machine learning model for delay risk assessment in tall building projects

Sanni-Anibire, Muizz O., Zin, Rosli Mohamad, Olatunji, Sunday Olusanya · 2022 · International Journal of Construction Management
Cited by 69

The DOI matches its Crossref record; 5 of the 5 references it cites were found in a registry or an index.

Abstract

Risky projects such as tall buildings have suffered an alarming rate of increase in delays and total abandonment. Though numerous delay studies predominate, what is lacking is constructive research to develop tools and techniques to wrestle the inherent problem. Consequently, this paper presents the development of a machine learning model for delay risk assessment in tall building projects. Initially, 36 delay risk factors were identified from previous literature, and subsequently developed into surveys to determine the likelihood and consequence of the risk factors. Forty-eight useable responses obtained from subject matter experts were used to develop a dataset suitable for machine learning application. K-Nearest Neighbors (KNN), Artificial Neural Networks (ANN), Support Vector Machines (SVM) and Ensemble methods were considered. Feature subset selection revealed that the most relevant independent variables include “slowness in decision making”; “delay in sub-contractors work”; “architects’/structural engineers’ late issuance of instruction”; and “waiting for approval of shop drawings and material samples”. The final results showed that the best model for predicting the risk of delay was based on ANN with a classification accuracy of 93.75%. Ultimately, the model developed in this study could support construction professionals in project risk management of tall buildings.

Overview

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.1080/15623599.2020.1768326

Cites

5 of 5 references verified0 citation errors · 0 not checkable

Statistics

Verification

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

Citations

Cites

Show all 5 references

Research works printed but not linked: 51

  1. 10.1061/(ASCE)0733-9364(2008)134:11(831) · doi:10.1061/(asce)0733-9364(2008)134:11(831 · Paper page
  2. 10.1061/(ASCE)0733-9364(2006)132:7(667) · doi:10.1061/(asce)0733-9364(2006)132:7(667 · Paper page
  3. 10.1016/j.jngse.2015.01.007 · DOI
  4. AlSehaimi A, Koskela L, Tzortzopoulos P. 2013. Need for alternative research approaches in construction management: case of delay studies. J Manage Eng. 29(4):407–413. · DOI
  5. 10.1061/(ASCE)0742-597X(1995)11:2(45) · doi:10.1061/(asce)0742-597x(1995)11:2(45 · Paper page
  6. Attal A. 2010. Development of neural network models for prediction of highway construction cost and project duration [Doctoral dissertation]. Ohio University.
  7. 10.1016/j.aej.2016.03.006 · doi:10.1016/j.aej.2016.03.006
  8. 10.1007/s12205-016-0691-2 · doi:10.1007/s12205-016-0691-2
  9. Benzécri JP. 1973. L’analyse des données. Vol. 2. Paris: Dunod; p. l.
  10. 10.1007/s12205-018-0810-3 · DOI
  11. Choi S, 2016, 2016 IEEE/AIAA 35th Digital Avionics Systems Conference (DASC), 1
  12. CTBUH, 2014, CTBUH J, 4
  13. 10.32738/JEPPM.201401.0004 · doi:10.32738/jeppm.201401.0004
  14. 10.1016/j.autcon.2020.103081 · DOI · Paper page
  15. 10.1016/j.ijproman.2011.10.004 · DOI · Paper page
  16. El-Kholy AM., 2019, Int J Constr Manage, 1
  17. 10.1108/13664380910977592 · DOI · Paper page
  18. 10.1080/01446190600827033 · DOI · Paper page
  19. Fellows RF, 2015, Research methods for construction
  20. Fix E, Hodges J. 1951. Discriminatory analysis, nonparametric discrimination: Consistency properties. Texas: USAF School of Aviation Medicine, Randolph Field. Technical Report 4. · DOI · Paper page
  21. Fugar FD, 2010, CEB, 10, 103
  22. García de Soto B, 2019, Int J Constr Manage, 1
  23. 10.1061/(ASCE)ME.1943-5479.0000129 · DOI
  24. Gunduz M, Nielsen Y, Ozdemir M. 2015. Fuzzy assessment model to estimate the probability of delay in Turkish construction projects. J Manage Eng. 31(4):04014055. · DOI
  25. 10.1016/j.net.2014.12.019 · DOI
  26. International Organization for Standardization Technical Committee, 2018, Risk management-guidelines
  27. 10.1080/014461997373132 · DOI · Paper page
  28. 10.1016/j.ijproman.2008.03.003 · DOI
  29. Kim YJ, 2016, 2016 IEEE/AIAA 35th Digital Avionics Systems Conference (DASC), 1
  30. Kuncheva LI, Rodríguez JJ. 2014. A weighted voting framework for classifiers ensembles. Knowl Inform Syst. 38(2):259–275. · DOI · Paper page
  31. 10.1201/9781351128384 · DOI · Paper page
  32. Lek S, Guégan JF. 1999. Artificial neural networks as a tool in ecological modelling, an introduction. Ecol Model. 120(2–3):65–73. · DOI · Paper page
  33. 10.1061/(ASCE)0733-9364(2006)132:6(636) · doi:10.1061/(asce)0733-9364(2006)132:6(636
  34. Mahamid I, Bruland A, Dmaidi N. 2012. Causes of delay in road construction projects. J Manage Eng. 28(3):300–310. · DOI
  35. 10.3390/buildings5030814 · doi:10.3390/buildings5030814
  36. Muneeswaran G, 2018, Int J Constr Manage, 1
  37. 10.1016/0263-7863(95)00052-6 · DOI · Paper page
  38. Olatunji SO., 2017, Canadian Conference on Electrical and Computer Engineering, 1
  39. 10.1155/2017/2450370 · doi:10.1155/2017/2450370
  40. 10.1016/j.ijproman.2006.11.007 · DOI · Paper page
  41. Sanni-Anibire MO, Mohamad Zin R, Olatunji SO. 2020. Causes of delay in the global construction industry: a meta analytical review. Int J Constr Manage. 1–13. · DOI · Paper page
  42. Sethi H, Goraya A, Sharma V. 2017. Artificial intelligence based ensemble model for diagnosis of diabetes. Int J Adv Res Comp Sci. 8(5):1540–1548.
  43. 10.1016/j.ijproman.2007.09.009 · DOI · Paper page
  44. Takeichi N, 2017, AIAA Modeling and Simulation Technologies Conference, 1323
  45. Tharwat A., 2018, Appl Comput Inf, 1
  46. 10.1080/01446190801905406 · DOI · Paper page
  47. Tumi SAH, Omran A, Pakir AHK. 2009. Causes of delay in construction industry in Libya. In: The International Conference on Economics and Administration; p. 265–272.
  48. 10.1016/j.ejor.2016.11.018 · DOI
  49. Witten IH, Frank E, Hall MA. 2011. Data mining: practical machine learning tools and techniques. Burlington, Massachusetts, USA: Morgan Kaufmann Publishers.
  50. 10.1002/atr.193 · doi:10.1002/atr.193
  51. Yu B, Song X, Guan F, Yang Z, Yao B. 2016. k-Nearest neighbor model for multiple-time-step prediction of short-term traffic condition. J Transp Eng. 142(6):04016018. · DOI · Paper page

Cited by

See all 69

Metadata

Authors
Sanni-Anibire, M. O., Zin, R. M., & Olatunji, S. O.
Venue
International Journal of Construction Management
Published
2020-05-25
Volume
22
Issue
11
Pages
2134-2143
ISSN
  • 1562-3599 (ISSN-L)
  • 2331-2327
OpenAlex
W3027176846
Cited by
69
References
5
FWCI
4.46
Type
journal article
Language
en
Open access
closed

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review

How to cite

Cite CoChat for the checks on this page, and the paper for its own findings.

This page
CoChat. (2026). Citation check: Machine learning model for delay risk assessment in tall building projects. https://app.cochat.ai/papers/10.1080/15623599.2020.1768326
The paper
Sanni-Anibire, M. O., Zin, R. M., & Olatunji, S. O. (2022). Machine learning model for delay risk assessment in tall building projects. International Journal of Construction Management. https://doi.org/10.1080/15623599.2020.1768326

Data sources

Bibliographic data: Semantic Scholar, OpenAlex, Crossref.

Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).

Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.