Moving Beyond Optimism Bias and Strategic Misrepresentation: An Explanation for Social Infrastructure Project Cost Overruns
The DOI matches its Crossref record; 28 of the 28 references it cites were found in a registry or an index.
Abstract
Infrastructure projects regularly experience cost and schedule overruns. Research led by Flyvbjerg has suggested that misrepresentation and optimism bias are primary causes for overruns. While Flyvbjerg's research has made a significant contribution to ameliorating understanding as to why economic infrastructure projects experience overruns, it does not adequately explain why this is the case for such social infrastructure. In addressing this shortcoming, case studies are used to determine the intermediary events and actions that contributed to project cost overruns. The pathogens, events, and actions that contributed to overruns are identified and analyzed. The analysis of the cases' findings led to the propagation of a nomological framework for social infrastructure project overruns. Acknowledgment of the systemic pathogenic influences has enabled the establishment of an orthodoxy, which provides an impetus for addressing the issues needed to improve the performance of social infrastructure projects.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
(1984) · Cited by 81,983
Content Analysis: An Introduction to its Methodology.
Shelley, M., & Krippendorff, K. (1984) · Journal of the American Statistical Association · doi:10.2307/2288384 · Cited by 24,312
Content Analysis: An Introduction to Its Methodology
Krippendorff, K. (2019) · doi:10.4135/9781071878781 · Cited by 15,448 · cited 1×
“In its simplest form, this technique can be used to extract and categorize information from documents [15].”
MethodFive misunderstandings about case-study research
Flyvbjerg, B. (2006) · Qualitative Inquiry · doi:10.1177/1077800405284363 · Cited by 14,266 · cited 2×
“This methodology should be used to investigate the technical aspects of a contemporary phenomenon within a real life context [39], particularly, in critical and unique circumstances [10].”
BackgroundMethodInterViews: An introduction to qualitative research interviewing
Flinders, D. J. (1997) · Evaluation and Program Planning · doi:10.1016/s0149-7189(97)89858-8 · Cited by 7,238
Human error: models and management
Reason, J. (2000) · BMJ · doi:10.1136/bmj.320.7237.768 · Cited by 5,665
Quality Is Free: The Art of Making Quality Certain
Crosby, P. B. (1979) · Andalas University Repository (Andalas University) · Cited by 3,719
Lewis, D. (1973) · The Journal of Philosophy · doi:10.2307/2025310 · Cited by 1,914
Porter, M. E. (1997) · Measuring Business Excellence · doi:10.1108/eb025476 · Cited by 779
How (In)accurate Are Demand Forecasts in Public Works Projects?: The Case of Transportation
Flyvbjerg, B., Skamris Holm, M. K., & Buhl, S. L. (2005) · Journal of the American Planning Association · doi:10.1080/01944360508976688 · Cited by 731 · cited 2×
“[9] focused on magprojects with contract values in excess of US$ 1 billion whereas the contract values reported in Love et al.”
BackgroundLathlean, J., Denicolo, P., & Denicolo, P. (2022) · Collecting, Analyzing, and Interpreting Qualitative Data · doi:10.4135/9781071885765 · Cited by 603
The Intransitivity of Causation Revealed in Equations and Graphs
Hitchcock, C. (2001) · The Journal of Philosophy · doi:10.2307/2678432 · Cited by 603 · cited 1×
“The relationship between strategic misrepresentation and optimism bias with cost overruns implicitly assumes causality in terms of counterfactual dependence of the effect on the cause: the cause is rendered counterfactually necessary for the effect [18], [14], [2].”
BackgroundTowards a Comprehensive Understanding of Public Private Partnerships for Infrastructure Development
Kwak, Y. H., Chih, Y., & Ibbs, C. W. (2009) · California Management Review · doi:10.2307/41166480 · Cited by 582 · cited 1×
“Traditionally, however, derivatives’ of build-own-operate transfer (BOOT) and design-build-own-transfer have been used to fund high-profile economic infrastructure such as roads, bridges, and tunnels [17].”
BackgroundFlyvbjerg, B., Garbuio, M., & Lovallo, D. P. (2009) · California Management Review · doi:10.2307/41166485 · Cited by 551 · cited 1×
“[12], there are two rudimentary reasons why projects experience cost overruns.”
BackgroundConstructing Social Research: The Unity and Diversity of Method
Ragin, C. C., & Amoroso, L. M. (2019) · Sage eBooks · doi:10.4135/9781071878798 · Cited by 546
What Causes Cost Overrun in Transport Infrastructure Projects?
FLYVBJERG, B., SKAMRIS HOLM, M. K., & BUHL, S. L. (2004) · Transport Reviews · doi:10.1080/0144164032000080494a · Cited by 455
Flyvbjerg, B. (2008) · European Planning Studies · doi:10.1080/09654310701747936 · Cited by 438 · cited 1×
“Second, optimism bias that encapsulates the systematic tendency for decision makers to be overoptimistic about the outcome of planned actions [11].”
BackgroundMare, R. D., & Schuessler, K. F. (1980) · Contemporary Sociology · doi:10.2307/2065290 · Cited by 347
Are Construction Disputes Inevitable?
Cheung, S. O., & Yiu, T. W. (2006) · IEEE Transactions on Engineering Management · doi:10.1109/tem.2006.877445 · Cited by 235
Managing Maintenance Error: A Practical Guide
Hobbs, A. N. (2003) · Cited by 229
MANAGING THE KNOWLEDGE‐BASED ORGANIZATION: THE CASE OF ARCHITECTURAL PRACTICE
Winch, G., & Schneider, E. (1993) · Journal of Management Studies · doi:10.1111/j.1467-6486.1993.tb00472.x · Cited by 216 · cited 2×
“Most other firms, however, earn average fees and are unable to differentiate themselves [37].”
BackgroundProject Pathogens: The Anatomy of Omission Errors in Construction and Resource Engineering Project
Love, P. E. D., Edwards, D. J., Irani, Z., & Walker, D. H. T. (2009) · IEEE Transactions on Engineering Management · doi:10.1109/tem.2008.927774 · Cited by 190 · cited 3×
“the consequences may be significant [23].”
BackgroundSelf-citationLove, P. E. D., Edwards, D. J., & Irani, Z. (2008) · IEEE Transactions on Engineering Management · doi:10.1109/tem.2008.919677 · Cited by 188
Self-citationAndi, & Minato, T. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00083-2 · Cited by 168 · cited 2×
“Juxtaposed with reduced fee levels are the excessive and unrealistic demands that are often imposed upon design consultants by the public sector to document projects [1].”
BackgroundDendrochronology raises questions about the nature of the AD 536 dust-veil event
Baillie, M. G. L. (1994) · The Holocene · doi:10.1177/095968369400400211 · Cited by 122
Projects, pathogens and incubation periods
Busby, J. S., & Hughes, E. J. (2003) · International Journal of Project Management · doi:10.1016/j.ijproman.2003.09.002 · Cited by 91 · cited 5×
“connected to the error and are identifiable as principal causes of the error once discovered [4].”
BackgroundInfluentialDivergence or Congruence? A Path Model of Rework for Building and Civil Engineering Projects
Love, P. E. D., Edwards, D. J., Smith, J., & Walker, D. H. T. (2009) · Journal of Performance of Constructed Facilities · doi:10.1061/(asce)cf.1943-5509.0000054 · Cited by 90
Self-citationDesign for manufacture: A strategy for successful application to buildings
Fox, S., Marsh, L., & Cockerham, G. (2001) · Construction Management and Economics · doi:10.1080/01446193.2001.9709625 · Cited by 40 · cited 1×
“subsequently, requires changes to be made [13].”
Cited by
A conceptual framework for integrating building information modeling with augmented reality
Wang, X., Love, P. E. D., Kim, M. J., Park, C.-S., Sing, C.-P., & Hou, L. (2013) · Automation in Construction · doi:10.1016/j.autcon.2012.10.012 · Cited by 263
“Project control Schedule growth is common in construction and engineering projects [38].”
Self-citationDetermining the Probability of Project Cost Overruns
Love, P. E. D., Wang, X., Sing, C.-P., & Tiong, R. L. K. (2013) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000575 · Cited by 169
Self-citationLove, P. E. D., Ahiaga-Dagbui, D. D., & Irani, Z. (2016) · Transportation Research Part A: Policy and Practice · doi:10.1016/j.tra.2016.08.007 · Cited by 138
“While on face value there may be grounds for this argument, the evidence presented lacks credibility and is unscientific; no proof of any causal relationship is provided (Love et al ., 2012; Love et al ., 2015a).”
Self-citationBig data-driven fuzzy cognitive map for prioritising IT service procurement in the public sector
Choi, Y., Lee, H., & Irani, Z. (2018) · Annals of Operations Research · doi:10.1007/s10479-016-2281-6 · Cited by 76
Self-citation
Metadata
- Authors
- Love, P. E. D., Edwards, D. J., & Irani, Z.
- Venue
- IEEE Transactions on Engineering Management
- Published
- 2012-11
- Volume
- 59
- Issue
- 4
- Pages
- 560-571
- ISSN
- 0018-9391 (ISSN-L)
- 1558-0040
- OpenAlex
- W2075560996
- Cited by
- 167
- References
- 28
- FWCI
- 8.67
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.