Elucidation of IS project success factors: an interpretive structural modelling approach

Open access
Hughes, D. Laurie, Rana, Nripendra P., Dwivedi, Yogesh K. · 2020 · Annals of Operations Research
Cited by 92

The DOI matches its Crossref record; 4 of the 4 references it cites were found in a registry or an index.

Abstract

This study extends the debate surrounding the components of IS project success by reviewing success factors from the perspective of their interdependency and influence on each other. This research utilises interpretive structural modelling as the methodology and framework to develop the relationships between the selected factors. This approach is presented as a mechanism that can provide greater insight to the underlying causal interrelationships associated with IS project success and the successful transition to operations. The findings identify a number of key outcomes that have significant driving influence on other interconnected factors in the final model. This study highlights the benefits of an interpretive approach where IS factor interrelationships can be modelled to demonstrate potential influence on other connected factors thereby, increasing the chances of project success.

Overview

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.1007/s10479-019-03146-w

Cites

4 of 4 references verified0 citation errors · 0 not checkable

Statistics

Verification

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

Citations

Cites

Show all 4 references

Research works printed but not linked: 113

  1. Agarwal, A., & Shankar, R. (2003). On-line trust building in e-enabled supply chain. Supply Chain Management: An International Journal,8(4), 324–334. · DOI
  2. Agarwal, A., Shankar, R., & Tiwari, M. K. (2007). Modeling agility of supply chain. Industrial Marketing Management,36(4), 443–457. · DOI · Paper page
  3. Ash, C. (2007). Convergence of IT project management and change management: A comparative study. In Proceedings of the European and mediterranean conference on information systems, EMCIS 2007, Valencia, Spain (pp. 1–8).
  4. Avison, D., & Wilson, D. (2002). IT failure and the collapse of One. Tel. In Proceedings of the IFIP 17th world computer congress: TC8 stream on information systems—The e-business challenge (pp. 31–46).
  5. Barker, T., & Frolick, M. (2003). ERP implementation failure a case study. Information systems management, Fall. · DOI · Paper page
  6. Bartis, E., & Mitev, N. (2008). A multiple narrative approach to information systems failure: A successful system that failed. In Proceedings of the 15th European conference on information systems, San Francisco (pp. 1421–1433). · DOI
  7. Belassi, W., & Tukel, O. I. (1996). A new framework for determining critical success/failure factors in projects. International Journal of Project Management,14(3), 141–151. · DOI · Paper page
  8. Belout, A., & Gauvreau, C. (2004). Factors influencing project success: The impact of human resource management. International Journal of Project Management,22(1), 1–11. · DOI · Paper page
  9. Bendavid, I., & Golany, B. (2009). Setting gates for activities in the stochastic project scheduling problem through the cross entropy methodology. Annals of Operations Research,172(1), 259–276. · doi:10.1007/s10479-009-0579-3
  10. Beynon-Davies, P. (1995). Information systems failure: The case of the London ambulance services computer aided despatch project. European Journal of Information Systems,4(3), 171–184. · DOI · Paper page
  11. Brown, A., & Jones, M. (1998). Doomed to failure: Narratives of inevitability and conspiracy in a failed IS project. Organisation Studies,19(1), 73–88. · DOI · Paper page
  12. Castejón-Limas, M., Ordieres-Meré, J., González-Marcos, A., & González-Castro, V. (2011). Effort estimates through project complexity. Annals of Operations Research,186(1), 395–406. · doi:10.1007/s10479-010-0776-0
  13. Chander, M., Jain, S. K., & Shankar, R. (2013). Modeling of information security management parameters in Indian organisations using ISM and MICMAC approach. Journal of Modelling in Management,8(2), 171–189. · DOI
  14. Cherrafi, A., Elfezazi, S., Garza-Reyes, J. A., Benhida, K., & Mokhlis, A. (2017). Barriers in Green Lean implementation: A combined systematic literature review and interpretive structural modelling approach. Production Planning & Control,28, 829–842. · DOI · Paper page
  15. Christianson, D., & Walker, D. (2004). Understanding the role of “vision” in project success. IEEE Engineering Management Review,32(4), 57–73. · doi:10.1109/emr.2004.25137
  16. Cooke-Davies, T. (2002). The ‘real’ success factors on projects. International Journal of Project Management,20(3), 185–190. · DOI · Paper page
  17. Creasy, T., & Anantatmula, V. S. (2013). From every direction: How personality traits and dimensions of project managers can conceptually affect project success. Project Management Journal,44(6), 36–51. · DOI
  18. Dan, J., Broome, A., & Joyce, W. (1998). Human barriers to project success. Computer Bulletin,40(3), 24–25. · doi:10.1093/combul/40.3.24
  19. de Bakker, K., Boonstra, A., & Wortmann, H. (2010). Does risk management contribute to IT project success? A meta-analysis of empirical evidence. International Journal of Project Management,28(5), 493–503. · DOI · Paper page
  20. de Miranda Mota, C. M., & de Almeida, A. T. (2012). A multicriteria decision model for assigning priority classes to activities in project management. Annals of Operations Research,199(1), 361–372. · DOI
  21. de Wit, A. (1988). Measurement of project success. International Journal of Project Management,6(3), 164–170. · DOI · Paper page
  22. Dekkers, C., & Forselius, P. (2007). Increase ICT project success with concrete scope management. In EUROMICRO 2007: Proceedings of the 33rd EUROMICRO conference on software engineering and advanced applications SEAA 2007, Lübeck, Germany (pp. 385–392).
  23. DeLone, W. J., & McLean, E. R. (1992). Information systems success: The quest for the dependent variable. Information Systems Research,3(1), 60–95. · DOI · Paper page
  24. Duperrin, J. C., & Godet, M. (1973). Methode de hierarchisation des elements d’un systeme. Rapport economique du CEA,1(2), 49–51.
  25. Dwivedi, Y. K., Janssen, M., Slade, E. L., Rana, N. P., Weerakkody, V., Millard, J., et al. (2017). Driving innovation through big open linked data (BOLD): Exploring antecedents using interpretive structural modelling. Information Systems Frontiers,19(2), 197–212. · DOI · Paper page
  26. El Emam, K., & Koru, A. (2008). A replicated survey of IT software project failures. IEEE Software,25(5), 84–90. · DOI · Paper page
  27. Esa, M., & Samad, Z. (2014). Preparing project managers to achieve project success-human related factor. International Journal Research Management Technology,4(2), 104–110.
  28. Ewusi-Mensah, K., & Przasnyski, Z. (1995). Learning from abandoned information systems development projects. Journal of Information Technology,10, 3–14. · doi:10.1177/026839629501000102
  29. Fitzgerald, G., & Russo, N. R. (2005). The turnaround of the London ambulance service computer-aided dispatch system (LASCAD). European Journal of Information Systems,14(3), 244–257. · DOI · Paper page
  30. Fortune, J., & White, D. (2006). Framing of project critical success factors by systems model. International Journal of Project Management,24(1), 53–65. · DOI · Paper page
  31. Gauld, R. (2007). Public sector information system failures: Lessons from a New Zealand hospital organisation. Government Information Quarterly,24, 102–114. · DOI
  32. Gopal, P. R. C., & Thakkar, J. (2016). Analysing critical success factors to implement sustainable supply chain practices in Indian automobile industry: A case study. Production Planning & Control,27(12), 1005–1018. · DOI
  33. Gray, R. J. (2001). Organisational climate and project success. International Journal of Project Management,19(2), 103–109. · DOI
  34. Haggerty, N. (2000). Understanding the link between IT project manager skills and project success research in progress. In Proceedings of the 2000 ACM SIGCPR conference on computer personnel research (pp. 192–195). ACM. · DOI
  35. Haleem, A., Sushil, Qadri, M. A., & Kumar, S. (2012). Analysis of critical success factors of world-class manufacturing practices: An application of interpretative structural modelling and interpretative ranking process. Production Planning & Control,23(10–11), 722–734. · DOI · Paper page
  36. Hiatt, J. M., & Creasey, T. M. (2012). Change management: The people side of change. Loveland, CO: Prosci Inc.
  37. Hornstein, H. (2015). The integration of project management and organizational change management is now a necessity. International Journal of Project Management,33(2), 291–298. · DOI · Paper page
  38. Hughes, D. L., Dwivedi, Y. K., & Rana, N. P. (2017). Mapping IS failure factors on PRINCE2® stages: An application of interpretive ranking process (IRP). Production Planning & Control,28(9), 776–790. · DOI · Paper page
  39. Hughes, D. L., Dwivedi, Y. K., Simintiras, A. C., & Rana, N. P. (2015). Success and failure of IS projects: A state of the art analysis and future directions. Dordrecht: Springer.
  40. Hyvari, I. (2006). Success of projects in different organizational conditions. Project Management Journal,37(4), 31–42. · DOI · Paper page
  41. Janes, F. R. (1988). Interpretive structural modelling: A methodology for structuring complex issues. Transactions of the Institute of Measurement and Control,10(3), 145–154. · DOI · Paper page
  42. Janssen, M., Rana, N. P., Slade, E. L., & Dwivedi, Y. K. (2018). Trustworthiness of digital government services: Deriving a comprehensive theory through interpretive structural modelling. Public Management Review,20(5), 647–671. · DOI · Paper page
  43. Jarocki, T. L. (2014). One solution for project success: Project and change management in the PMBOK ®guide. Project Management Institute: Newtown Square.
  44. Jones, C. (2006). Social and technical reasons for software project failures. CrossTalk,19(6), 4–9.
  45. Kearns, G. (2007). How the internal environment impacts information systems project success: An investigation of exploitative and explorative firms. Journal of Computer Information Systems,38(1), 63–75.
  46. Keil, M., Cule, P. E., Lyytinen, K., & Schmidt, R. C. (1998). A framework for identifying software project risks. Communications of the ACM,41(11), 76–83. · DOI · Paper page
  47. Kerzner, H. (2013). Project management. A systems approach to planning, scheduling and controlling (5th ed.). Hoboken, New Jersey: Wiley.
  48. Kerzner, H. (2015). Project management. 2.0 (1st ed.). Hoboken, New Jersey: Wiley. · doi:10.1002/9781119020042
  49. Klaus, T., & Blanton, J. E. (2010). User resistance determinants and the psychological contract in enterprise system implementations. European Journal of Information Systems,19(6), 625–636. · DOI · Paper page
  50. Kumar, S., Luthra, S., Govindan, K., Kumar, N., & Haleem, A. (2016). Barriers in green lean six sigma product development process: An ISM approach. Production Planning & Control,27(7–8), 604–620.
  51. Lambrechts, O., Demeulemeester, E., & Herroelen, W. (2011). Time slack-based techniques for robust project scheduling subject to resource uncertainty. Annals of Operations Research,186(1), 443–464. · doi:10.1007/s10479-010-0777-z
  52. Lechler, T. G., & Dvir, D. (2010). An alternative taxonomy of project management structures: Linking project management structures and project success. IEEE Transactions on Engineering Management,57(2), 198–210. · DOI
  53. Lemon, W. F., Liebowitz, J., Burn, J., & Hackney, R. (2002). Information systems project failure: A comparative study of two countries. Journal of Global Information Management,10(2), 28–39. · DOI
  54. Lepmets, M. (2010). Which process model practices support project success? Systems, software and services process improvement (pp. 119–129). Berlin: Springer. · doi:10.1007/978-3-642-15666-3_11
  55. Letavec, C. (2014). Strategic benefits realization: Optimizing value through programs, portfolios, and organisational change management. Plantation: J. Ross.
  56. Leyland, M., Hunter, D., & Dietrich, J. (2009). Integrating change management into clinical health information technology project practice. In World congress on privacy, security, trust and the management of e-business, 2009. CONGRESS’09 (pp. 89–99). · DOI
  57. Lim, M. K., Tseng, M. L., Tan, K. H., & Bui, T. D. (2017). Knowledge management in sustainable supply chain management: Improving performance through an interpretive structural modelling approach. Journal of Cleaner Production,162, 806–816. · DOI · Paper page
  58. Mandal, A., & Deshmukh, S. G. (1994). Vendor selection using interpretive structural modelling (ISM). International Journal of Operations & Production Management,14(6), 52–59. · DOI · Paper page
  59. Marnewick, C. (2012). A longitudinal analysis of ICT project success. In ACM international conference proceeding series, SAICSIT, SA (pp. 326–334). · DOI
  60. McGrath, K. (2002). The golden circle: A way of arguing and acting about technology in the London ambulance service. European Journal of Information Systems,11(4), 251–266. · DOI · Paper page
  61. Meade, L. M., & Sarkis, J. (1999). Analyzing organisational project alternatives for agile manufacturing processes: An analytical network approach. International Journal of Production Research,37(2), 241–261. · DOI · Paper page
  62. Milosevic, D., & Patanakul, P. (2005). Standardised project management may increase development projects success. International Journal of Project Management,23(3), 181–192. · DOI · Paper page
  63. Mir, F., & Pinnington, A. (2014). Exploring the value of project management: Linking project management performance and project success. International Journal of Project Management,32(2), 202–217. · DOI · Paper page
  64. Mitev, N. N. (1996). More than a failure? The computerized reservation systems at French Railways. Information Technology & People,9(4), 8–19. · DOI
  65. Morris, P. W., & Hough, G. (1987). The anatomy of major projects: A study of the reality of project management. Oxford: Major Projects Association.
  66. Muller, R., & Jugdev, K. (2012). Critical success factors in projects: Pinto, Slevin and Prescott—The elucidation of project success. International Journal of Managing Projects in Business,5(4), 757–775. · DOI · Paper page
  67. Muriithi, N., & Crawford, L. (2003). Approaches to project management in Africa: Implications for international development projects. International Journal of Project Management,21(5), 309–319. · DOI
  68. Niekerk, S., & Steyn, H. (2011). Defining’ project success’ for a complex project: The case of a nuclear engineering development. Journal of Industrial Engineering,22(1), 123–136.
  69. Nixon, P., Harrington, M., & Parker, D. (2012). Leadership performance is significant to project success or failure: A critical analysis. International Journal of Productivity and Performance Management,61(2), 204–216. · DOI · Paper page
  70. OGC Group. (2013). Managing successful projects with PRINCE2. London: TSO.
  71. Pan, G., Hackney, R., & Pan, S. L. (2008). Information Systems implementation failure: Insights from prism. International Journal of Information Management,28(4), 259–269. · DOI
  72. Papke-Shields, K. E., Beise, C., & Quan, J. (2010). Do project managers practice what they preach, and does it matter to project success? International Journal of Project Management,28(7), 650–662. · DOI · Paper page
  73. Parker, D., Charlton, J., Ribeiro, A., & Pathak, R. D. (2013). Integration of project-based management and change management: Intervention methodology. International Journal of Productivity and Performance Management,62(5), 534–544. · DOI
  74. Parsons-Hann, H., & Liu, K. (2005). Measuring requirements complexity to increase the probability of project success. ICEIS,3, 434–438.
  75. Patton, N., & Shechet, A. (2007). Wisdom for building the project manager/project sponsor relationship: Partnership for project success. The Journal of Defense Engineering,20(11), 4–9.
  76. Philip, T., Schwabe, G., & Ewusi-Mensah, K. (2009). Critical issues of offshore software development project failures. In ICIS 2009 Proceedings: Thirtieth international conference on information systems. Phoenix, AZ.
  77. Pinto, J. K., & Mantel, S. J. (1990). The causes of project failure. IEEE Transactions on Engineering Management,37(4), 269–276. · DOI · Paper page
  78. Pinto, J. K., & Prescott, J. (1988). Variations in critical success factors over the stages in the project life cycle. Journal of Management,14(1), 5–18. · DOI · Paper page
  79. Pinto, J. K., & Slevin, D. P. (1987). Critical factors in successful project implementation. IEEE Transactions on Engineering Management,34(1), 22–27. · DOI · Paper page
  80. Pinto, J. K., & Slevin, D. P. (1988). Project success: Definitions and measurement techniques. Project Management Journal,19(1), 67–72.
  81. Poon, S. K., Young, R., Irandoost, S., & Land, L. (2011). Re-assessing the importance of necessary or sufficient conditions of critical success factors in IT project success: A fuzzy set-theoretic approach. In 9th European conference on information systems, ECIS 2011.
  82. Procaccino, J. D., Verner, J. M., Shelfer, K. M., & Gefen, D. (2005). What do software practitioners really think about project success: An exploratory study. Journal of Systems and Software,78(2), 194–203. · DOI
  83. Project Management Institute (PMI). (2014). A guide to the project management body of knowledge (PMBOK ®guide) (5th ed.). Newtown Square, PA: PMI Publications.
  84. Purohit, J. K., Mittal, M. L., Mittal, S., & Sharma, M. K. (2016). Interpretive structural modeling-based framework for mass customisation enablers: An Indian footwear case. Production Planning & Control,27(9), 774–786. · DOI · Paper page
  85. Rana, N. P., Dwivedi, Y. K., Williams, M. D., & Weerakkody, V. (2015). Investigating success of an e-government initiative: Validation of an integrated IS success model. Information Systems Frontiers,17, 127–142. · DOI · Paper page
  86. Ravi, V., & Shankar, R. (2005). Analysis of interactions among the barriers of reverse logistics. Technological Forecasting and Social Change,72(8), 011–1029. · DOI · Paper page
  87. Raymond, L., & Bergeron, F. (2008). Project management information systems: An empirical study of their impact on project managers and project success. International Journal of Project Management,26(2), 213–220. · DOI · Paper page
  88. Sage, A. P. (1977). Methodology for large-scale systems. New York: McGraw-Hill College.
  89. Salimifard, K., Abbaszadeh, M. A., & Ghorbanpur, A. (2010). Interpretive structural modeling of critical success factors in banking process re-engineering. International Review of Business Research Papers,6(2), 95–103.
  90. Samantra, C., Datta, S., Sankar Mahapatra, S., & Ranjan, B. (2016). Interpretive structural modelling of critical risk factors in software engineering project. Benchmarking: An International Journal,23(1), 2–24. · DOI
  91. Sauer, C. (1993). Why information systems fail: A case study approach. London: Alfred Waller Ltd.
  92. Schmidt, R., Lyytinen, K., Keil, M., & Cule, P. (2001). Identifying software project risks: An international Delphi study. Journal of Management Information Systems,17(4), 5–36. · DOI · Paper page
  93. Scott, J., & Vessey, I. (2000). Implementing enterprise resource planning systems: The role of learning from failure. Information Systems Frontiers,2(2), 213–232. · DOI · Paper page
  94. Sharma, H. D., & Gupta, A. D. (1995). The objectives of waste management in India: A futures inquiry. Technological Forecasting and Social Change,48(3), 285–309. · DOI · Paper page
  95. Singh, R. K. (2011). Developing the framework for coordination in supply chain of SMEs. Business Process Management Journal,17(4), 619–638. · DOI · Paper page
  96. Singh, M. D., Shankar, R., Narain, R., & Agarwal, A. (2003). An interpretive structural modeling of knowledge management in engineering industries. Journal of Advances in Management Research,1(1), 28–40. · DOI · Paper page
  97. Söderlund, J. (2004). Building theories of project management: Past research, questions for the future. International Journal of Project Management,28(2), 130–141. · DOI
  98. Sumner, M., Bock, D., & Giamartino, G. (2006). Exploring the linkage between the characteristics of it project leaders and project success. Information Systems Management,23(4), 43–49. · DOI
  99. Sumner, M., & Molka-Danielsen, J. (2010). Global IT teams and project success. In Proceedings of the 2010 special interest group on management information system’s 48th annual conference on computer personnel research on computer personnel research (pp. 34–42). ACM. · DOI
  100. Tamai, T., & Kamata, M. I. (2009). Impact of requirements quality on project success or failure. Design requirements engineering: A ten-year perspective (pp. 258–275). Berlin: Springer. · doi:10.1007/978-3-540-92966-6_15
  101. Thakkar, J., Kanda, A., & Deshmukh, S. G. (2007). Evaluation of buyer-supplier relationships using an integrated mathematical approach of interpretive structural modeling (ISM) and graph theoretic matrix: The case study of Indian automotive SMEs. Journal of Manufacturing Technology Management,19(1), 92–124. · DOI
  102. Thamsatitdej, P. (2017). Eco-design practices towards sustainable supply chain management: Interpretive structural modelling (ISM) approach. International Journal of Sustainable Engineering,10(6), 326–338. · DOI
  103. Tiwana, A., & McLean, E. R. (2003). The tightrope to e-business project success. Communications of the ACM,46(12), 345–350. · doi:10.1145/953460.953520
  104. Turner, J. R. (2009). The handbook of project-based management: Leading strategic change in organisations (3rd ed.). London, UK: McGraw-Hill.
  105. Turner, J., & Müller, R. (2005). The project manager’s leadership style as a success factor on projects: A literature review. Project Management Journal,36(2), 49–61. · DOI · Paper page
  106. Tzeng, G. H., & Huang, C. Y. (2012). Combined DEMATEL technique with hybrid MCDM methods for creating the aspired intelligent global manufacturing & logistics systems. Annals of Operations Research,197(1), 159–190. · DOI
  107. Verner, J. M., & Abdullah, L. M. (2012). Exploratory case study research: Outsourced project failure. Information and Software Technology,54(8), 866–886. · DOI
  108. Verner, J., Sampson, J., & Cerpa, N. (2008). What factors lead to software project failure? In Proceedings of the 2nd international conference on research challenges in information science, RCIS 2008 (pp. 71–79).
  109. Warfield, J. N. (1974). Developing subsystem matrices in structural modeling. Systems, Man and Cybernetics, IEEE Transactions on,1, 74–80. · DOI · Paper page
  110. Wateridge, J. (1995). IT projects: A basis for success. International Journal of Project Management,13(3), 169–172. · DOI · Paper page
  111. Wu, F., Li, H. Z., Chu, L. K., Sculli, D., & Gao, K. (2009). An approach to the valuation and decision of ERP investment projects based on real options. Annals of Operations Research,168(1), 181. · doi:10.1007/s10479-008-0365-7
  112. Yeo, K. T. (2002). Critical failure factors in information system projects. International Journal of Project Management,20(3), 241–246. · DOI · Paper page
  113. Young, R. (2005). An example of relevant IS research for top managers on IT project failure. In ACIS 2005 proceedings: 16th Australasian conference on information systems.

Cited by

See all 92

Metadata

Authors
Hughes, D. L., Rana, N. P., & Dwivedi, Y. K.
Venue
Annals of Operations Research
Published
2019-01-19
Volume
285
Issue
1-2
Pages
35-66
ISSN
  • 0254-5330 (ISSN-L)
  • 1572-9338
OpenAlex
W2909250895
Cited by
92
References
4
FWCI
24.74
Type
journal article
Language
en
Open access
hybrid
Licence
creativecommons.org/licenses/by/4.0 (tdm)

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review

How to cite

Cite CoChat for the checks on this page, and the paper for its own findings.

This page
CoChat. (2026). Citation check: Elucidation of IS project success factors: an interpretive structural modelling approach. https://app.cochat.ai/papers/10.1007/s10479-019-03146-w
The paper
Hughes, D. L., Rana, N. P., & Dwivedi, Y. K. (2020). Elucidation of IS project success factors: an interpretive structural modelling approach. Annals of Operations Research. https://doi.org/10.1007/s10479-019-03146-w

Data sources

Bibliographic data: Semantic Scholar, OpenAlex, Crossref.

Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).

Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.