Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries
Open accessAbstract
In-planned duration and cost at project closing are the two of criteria of successful project and successful project management. In Vietnam, regularly, construction projects have met delays and cost overruns. This research has employed a questionnaire survey to elicit the causes of this situation by interviewing 87 Vietnamese construction experts. Twenty one causes of delay and cost overruns appropriate with building and industrial construction project were inferred and ranked with respect to frequency, severity and importance indices. Spearman’s rank correlation tests showed that there are no differences in the viewpoints between three principal parties in the project. A comparison of causes of time and cost overruns was done with various selected construction industries in Asia and Africa. Factor analysis technique was applied to categorize the causes, which yielded 7 factors: Slowness and Lack of constraint; Incompetence; Design; Market and Estimate; Financial capability; Government; and Worker. These findings might encourage practitioners to focus on delay and cost overruns problem that might have existed in their present or future projects.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Research methods for business: A skill building approach
(1993) · Long Range Planning · doi:10.1016/0024-6301(93)90168-f · Cited by 16,985
Sekaran, U., & Bougie, R. (2008) · Cited by 2,383
Causes of delay in large construction projects
Assaf, S. A., & Al-Hejji, S. (2006) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.11.010 · Cited by 1,705
Causes and effects of delays in Malaysian construction industry
Sambasivan, M., & Soon, Y. W. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.11.007 · Cited by 1,422
Causes of construction delay: traditional contracts
Odeh, A. M., & Battaineh, H. T. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00037-5 · Cited by 810
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00055-8 · Cited by 796
Factors influencing construction time and cost overruns on high-rise projects in Indonesia
Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997) · Construction Management and Economics · doi:10.1080/014461997373132 · Cited by 698
Significant factors causing delay in the UAE construction industry
Faridi, A. S., & El‐Sayegh, S. M. (2006) · Construction Management and Economics · doi:10.1080/01446190600827033 · Cited by 551
Delays in construction projects: The case of Jordan
Sweis, G., Sweis, R., Abu Hammad, A., & Shboul, A. (2008) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.09.009 · Cited by 534
Causes of delay and cost overruns in Nigerian construction projects
Mansfield, N., Ugwu, O., & Doran, T. (1994) · International Journal of Project Management · doi:10.1016/0263-7863(94)90050-7 · Cited by 457
Delays and cost increases in the construction of private residential projects in Kuwait
Koushki, P. A., Al‐Rashid, K., & Kartam, N. (2005) · Construction Management and Economics · doi:10.1080/0144619042000326710 · Cited by 456
A study on project success factors in large construction projects in Vietnam
Duy Nguyen, L., Ogunlana, S. O., & Thi Xuan Lan, D. (2004) · Engineering, Construction and Architectural Management · doi:10.1108/09699980410570166 · Cited by 415
Construction delays in a fast-growing economy: Comparing Thailand with other economies
Ogunlana, S. O., Promkuntong, K., & Jearkjirm, V. (1996) · International Journal of Project Management · doi:10.1016/0263-7863(95)00052-6 · Cited by 390
Large construction projects in developing countries: a case study from Vietnam
Long, N. D., Ogunlana, S. O., Quang, T., & Lam, K. C. (2004) · International Journal of Project Management · doi:10.1016/j.ijproman.2004.03.004 · Cited by 362
Construction Delays and Their Causative Factors in Nigeria
Aibinu, A. A., & Odeyinka, H. A. (2006) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2006)132:7(667 · Cited by 348
Bowley, A. L. (2010) · Cited by 287
Contributors to construction delays
Kumaraswamy, M. M., & Chan, D. W. M. (1998) · Construction Management and Economics · doi:10.1080/014461998372556 · Cited by 239
An evaluation of construction time performance in the building industry
Chan, D. W. M., & Kumaraswamy, M. M. (1996) · Building and Environment · doi:10.1016/0360-1323(96)00031-5 · Cited by 205
Reasons for Cost and Schedule Increase for Engineering Design Projects
Chang, A. S.-T. (2002) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(2002)18:1(29 · Cited by 133
Cited by
A fuzzy synthetic evaluation approach for risk assessment: a case of Singapore's green projects
Zhao, X., Hwang, B.-G., & Gao, Y. (2016) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2015.11.042 · Cited by 279
Park, Y., & Papadopoulou, T. C. (2012) · Built Environment Project and Asset Management · doi:10.1108/20441241211280873 · Cited by 91
Ghazal, M. M., & Hammad, A. (2022) · International Journal of Construction Management · doi:10.1080/15623599.2020.1738205 · Cited by 52
Construction delays in privately funded large building projects in Bangladesh
Islam, M. S., & Suhariadi, B. T. (2018) · Asian Journal of Civil Engineering · doi:10.1007/s42107-018-0034-3 · Cited by 44
Metadata
- Authors
- Le-Hoai, L., Lee, Y. D., & Lee, J. Y.
- Venue
- KSCE Journal of Civil Engineering
- Publisher
- Elsevier BV
- Published
- 2008-11
- Volume
- 12
- Issue
- 6
- Pages
- 367-377
- ISSN
- 1226-7988 (ISSN-L)
- OpenAlex
- W2005071274
- Cited by
- 560
- References
- 19
- FWCI
- 7.69
- Type
- journal article
- Language
- en
- Open access
- hybrid
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.