Taxonomy for change causes and effects in construction projects
Open accessThe DOI matches its Crossref record; 27 of the 27 references it cites were found in a registry or an index.
Abstract
During many construction projects frequent changes often result in time delays, cost overruns, quality defects and other negative impacts. In recent years, many researchers worldwide investigated the effects of project change and more importantly the common causes behind the changes from different perspectives. A large number of research papers have been published in this field. While most existing papers presented valuable empirical work, very few offered a comprehensive and systematic overview. There is also a certain degree of confusion in the terminology used by different authors. The objective of this paper is to fill this knowledge gap by: (1) reviewing and synthesising existing literature on project change causes and effects; (2) developing two taxonomies for change causes and change effects; and (3) illustrating how the taxonomies can be used during the project change management process.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Causes of delay in large construction projects
Assaf, S. A., & Al-Hejji, S. (2006) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.11.010 · Cited by 1,705
A comparative study of causes of time overruns in Hong Kong construction projects
Chan, D. W., & Kumaraswamy, M. M. (1997) · International Journal of Project Management · doi:10.1016/s0263-7863(96)00039-7 · Cited by 831
Causes of construction delay: traditional contracts
Odeh, A. M., & Battaineh, H. T. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00037-5 · Cited by 810
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00055-8 · Cited by 796
Factors influencing construction time and cost overruns on high-rise projects in Indonesia
Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997) · Construction Management and Economics · doi:10.1080/014461997373132 · Cited by 698
The effects of construction delays on project delivery in Nigerian construction industry
Aibinu, A. A., & Jagboro, G. O. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00028-5 · Cited by 597
Construction delay: a quantitative analysis
Al-Momani, A. H. (2000) · International Journal of Project Management · doi:10.1016/s0263-7863(98)00060-x · Cited by 553
Quantifying the causes and costs of rework in construction
Love, P. E. D., & Li, H. (2000) · Construction Management and Economics · doi:10.1080/01446190050024897 · Cited by 486
Influence of Project Type and Procurement Method on Rework Costs in Building Construction Projects
Love, P. E. D. (2002) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2002)128:1(18 · Cited by 463
Construction delays in a fast-growing economy: Comparing Thailand with other economies
Ogunlana, S. O., Promkuntong, K., & Jearkjirm, V. (1996) · International Journal of Project Management · doi:10.1016/0263-7863(95)00052-6 · Cited by 390
Love, P. E. D., Holt, G. D., Shen, L. Y., Li, H., & Irani, Z. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(01)00039-4 · Cited by 316
Illustrative Benchmarking Rework and Rework Costs in Swedish Construction Industry
Josephson, P.-E., Larsson, B., & Li, H. (2002) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(2002)18:2(76 · Cited by 214
Determining the causal structure of rework influences in construction
LOVE, P. E. D., MANDAL, P., & LI, H. (1999) · Construction Management and Economics · doi:10.1080/014461999371420 · Cited by 211
An evaluation of construction time performance in the building industry
Chan, D. W. M., & Kumaraswamy, M. M. (1996) · Building and Environment · doi:10.1016/0360-1323(96)00031-5 · Cited by 205
Impact of Change Orders on Labor Efficiency for Electrical Construction
Hanna, A. S., Russell, J. S., Nordheim, E. V., & Bruggink, M. J. (1999) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(1999)125:4(224 · Cited by 175
Factors Affecting Contractors' Risk of Cost Overburden
Akinci, B., & Fischer, M. A. (1998) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(1998)14:1(67 · Cited by 155
Statistical analysis of causes for change orders in metropolitan public works
Hsieh, T.-Y., Lu, S.-T., & Wu, C.-H. (2004) · International Journal of Project Management · doi:10.1016/j.ijproman.2004.03.005 · Cited by 146
Reasons for Cost and Schedule Increase for Engineering Design Projects
Chang, A. S.-T. (2002) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(2002)18:1(29 · Cited by 133
Quantitative Definition of Projects Impacted by Change Orders
Hanna, A. S., Camlic, R., Peterson, P. A., & Nordheim, E. V. (2002) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2002)128:1(57 · Cited by 131
Cost overruns in public projects
Arditi, D., Akan, G. T., & Gurdamar, S. (1985) · International Journal of Project Management · doi:10.1016/0263-7863(85)90053-5 · Cited by 121
Reasons for overrun in public sector construction projects in Nigeria
Dlakwa, M. M., & Culpin, M. F. (1990) · International Journal of Project Management · doi:10.1016/0263-7863(90)90032-7 · Cited by 109
Statistical analysis of causes for design change in highway construction on Taiwan
Wu, C.-H., Hsieh, T.-Y., & Cheng, W. (2005) · International Journal of Project Management · doi:10.1016/j.ijproman.2004.07.010 · Cited by 105
Identification and evaluation of factors influencing variations on building projects
Akinsola, A., Potts, K., Ndekugri, I., & Fc, H. (1997) · International Journal of Project Management · doi:10.1016/s0263-7863(96)00081-6 · Cited by 96
Claims for extensions of time in civil engineering projects
Yogeswaran, K., Kumaraswamy, M. M., & Miller, D. R. (1998) · Construction Management and Economics · doi:10.1080/014461998372312 · Cited by 91
Effects of overtime work and additional resources on project cost and quality
Li, H., Love, P. E. D., & Drew, D. S. (2000) · Engineering Construction & Architectural Management · doi:10.1046/j.1365-232x.2000.00151.x · Cited by 45
Williams, T. M. (2000) · International Journal of Project Management · doi:10.1016/s0263-7863(98)00063-5 · Cited by 40
Navigational Measures for Managing Defective Designs
Andi, A. (2004) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(2005)21:1(10 · Cited by 8
Cited by
Analysis of cost and schedule performance of international development projects
Ahsan, K., & Gunawan, I. (2010) · International Journal of Project Management · doi:10.1016/j.ijproman.2009.03.005 · Cited by 375
Manager emotional intelligence and project success: The mediating role of job satisfaction and trust
Rezvani, A., Chang, A., Wiewiora, A., Ashkanasy, N. M., Jordan, P. J., & Zolin, R. (2016) · International Journal of Project Management · doi:10.1016/j.ijproman.2016.05.012 · Cited by 301
Eybpoosh, M., Dikmen, I., & Talat Birgonul, M. (2011) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000382 · Cited by 217
Risk paths in international construction projects: Case study from Chinese contractors
Liu, J., Zhao, X., & Yan, P. (2016) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001116 · Cited by 203
Park, Y., & Papadopoulou, T. C. (2012) · Built Environment Project and Asset Management · doi:10.1108/20441241211280873 · Cited by 91
Metadata
- Authors
- Sun, M., & Meng, X.
- Venue
- International Journal of Project Management
- Publisher
- Elsevier BV
- Published
- 2009-08
- Volume
- 27
- Issue
- 6
- Pages
- 560-572
- ISSN
- 0263-7863 (ISSN-L)
- OpenAlex
- W2083674894
- Cited by
- 331
- References
- 27
- FWCI
- 8.20
- Type
- journal article
- Language
- en
- Open access
- green
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.