Approaches for Making Risk-Based Go/No-Go Decision for International Projects
The DOI matches its Crossref record; 14 of the 14 references it cites were found in a registry or an index.
Abstract
The world economy is becoming more global due to agreements such as the “Uruguay Round” in the General Agreement on Tariffs and Trade. The globalization of the construction industry provides tremendous opportunities for contractors to expand into new foreign markets. However, international construction involves all of the uncertainties common to domestic construction projects as well as risks specific to international transactions. Consequently, in opposition to the worldwide globalization trend, only 19% of the U.S. top 400 contractors actively seek international contracts. This paper discusses current approaches related to entry decisions into international construction markets. It then develops a comprehensive approach for making stable and systematic go/no-go decisions for international projects. Finally, a pilot study is used to demonstrate and validate the approach.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Theory of games and economic behavior
(2019) · 100 Years of Math Milestones · doi:10.1090/mbk/121/32 · Cited by 16,632
Judgment under Uncertainty: Heuristics and Biases
(1982) · doi:10.1017/cbo9780511809477 · Cited by 8,240
Judgment under uncertainty: List of contributors
Kahneman, D. J., Slovic, P., & Tversky, A. (1982) · Cited by 4,670
Judgment under uncertainty: Causality and attribution
Kahneman, D. J., Slovic, P., & Tversky, A. (1982) · Cited by 4,670
BOUNDED RATIONALITY, AMBIGUITY, AND THE ENGINEERING OF CHOICE
March, J. G. (1988) · Decision Making · doi:10.1017/cbo9780511598951.004 · Cited by 1,688
Rational choice in an uncertain world
Dawes, R. M., & Kagan, J. (1988) · Medical Entomology and Zoology · Cited by 1,291
Risk Management and Construction
Flanagan, R. (1993) · Medical Entomology and Zoology · Cited by 910
Judgment in Managerial Decision Making
Bazerman, M. H. (1986) · Digital Commons - USU (Utah State University) · Cited by 448
Initial experiments with the cross impact matrix method of forecasting
Gordon, T. J., & Hayward, H. (1968) · Futures · doi:10.1016/s0016-3287(68)80003-5 · Cited by 405
Decision Research: A Field Guide
Mayne, A. J. (1992) · Journal of the Operational Research Society · doi:10.1057/jors.1992.8 · Cited by 226
Cited by
Using fuzzy risk assessment to rate cost overrun risk in international construction projects
Dikmen, I., Birgonul, M. T., & Han, S. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.12.002 · Cited by 374
Self-citationFactors Affecting International Construction
Gunhan, S., & Arditi, D. (2005) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2005)131:3(273 · Cited by 239
Key project management practices affecting Singaporean firms’ project performance in China
Ling, F. Y. Y., Low, S. P., Wang, S. Q., & Lim, H. H. (2009) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.10.004 · Cited by 224
“transactions [3]. Besides the typical risks of a domestic project, international projects have a complex and subtle web of political, economic and cultural risks [ 4 ].”
BackgroundEybpoosh, M., Dikmen, I., & Talat Birgonul, M. (2011) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000382 · Cited by 217
Risk paths in international construction projects: Case study from Chinese contractors
Liu, J., Zhao, X., & Yan, P. (2016) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001116 · Cited by 203
Modelling and assessment of critical risks in BOT road projects
Thomas, A. V., Kalidindi, S. N., & Ganesh, L. S. (2006) · Construction Management and Economics · doi:10.1080/01446190500435275 · Cited by 163
“Keywords: BOT projects, risk modelling, risk assessment, fuzzy sets, possibility distribution”
BackgroundTowards a Strategic Model of Global Franchise Expansion
Aliouche, E. H., & Schlentrich, U. A. (2011) · Journal of Retailing · doi:10.1016/j.jretai.2011.01.004 · Cited by 90
Impact of aleatoric, stochastic and epistemic uncertainties on project cost contingency reserves
Curto, D., Acebes, F., González-Varona, J. M., & Poza, D. (2022) · International Journal of Production Economics · doi:10.1016/j.ijpe.2022.108626 · Cited by 47
Metadata
- Authors
- Han, S. H., & Diekmann, J. E.
- Venue
- Journal of Construction Engineering and Management
- Published
- 2001-08
- Volume
- 127
- Issue
- 4
- Pages
- 300-308
- ISSN
- 0733-9364 (ISSN-L)
- 1943-7862
- DOI
- 10.1061/(asce)0733-9364(2001)127:4(300
- OpenAlex
- W2037833831
- Cited by
- 203
- References
- 14
- FWCI
- 3.32
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.