Risk Management in the Chinese Construction Industry
The DOI matches its Crossref record; 38 of the 38 references it cites were found in a registry or an index.
Abstract
There has been an increase in research on risk management practice in the construction industry. However, little research has been conducted to systematically investigate the overall aspects of risk management on the perspectives of various project participants. This paper reports the findings of an empirical Chinese industry survey on the importance of project risks, application of risk management techniques, status of the risk management system, and the barriers to risk management, which were perceived by the main project participants. The risk management strategies adopted in the Three Gorges Project were also studied. The study reveals that: Most project risks are commonly of concern to project participants; the industry has shifted from risk transfer to risk reduction; current risk management systems are inadequate to manage project risks; and lack of joint risk management mechanisms is the key barrier to adequate risk management. Future studies should be conducted to systematically improve the risk management in construction by different approaches that facilitate equitable sharing of rewards through effective risk management among participants. Such studies should also consider the establishment of an open communication risk management process to permit the corporate experience of all participants, as well as their personal knowledge and judgment, to be effectively utilized.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Evaluating the risks of public private partnerships for infrastructure projects
Grimsey, D., & Lewis, M. K. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00040-5 · Cited by 964 · cited 1×
“…introduced in the literature COSO 2004; Lyons 2003; Walker and Johannes 2003; Cano and Cruz 2002; Elkington and Smallman 2002; Velde and Donk 2002; Grimsey and Lewis 2002; Duffield 2001; Jaafari 2001; Raz and Michael 2001; Floricel and Miller 2001; Turner and Simister 2001; Berends 2000; Dey…”
BackgroundThe allocation of risk in PPP/PFI construction projects in the UK
Bing, L., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005) · International Journal of Project Management · doi:10.1016/j.ijproman.2004.04.006 · Cited by 901 · cited 2×
“…industry of mainland China and Hong Kong Rahman and Kumaraswamy 2002a ; 9 allocation of risk in PPP/PFI construction projects in the United Kingdom Bing et al. 2005 ; 10 contractual risk and liability sharing in hydropower construction Charoenngam and Yeh 1999 ; 11 practices of using risk…”
BackgroundEnterprise Risk Management—Integrated Framework
Anand, S. (2012) · Wiley eBooks · doi:10.1002/9781119201939.app4 · Cited by 884
Risk analysis and management in construction
Akintoye, A. S., & MacLeod, M. J. (1997) · International Journal of Project Management · doi:10.1016/s0263-7863(96)00035-x · Cited by 755 · cited 3×
“Akintoye and Macleod 1997 argued that postal surveys can be biased if the return rate is lower than 30–40%.”
BackgroundTrust in project relationships—inside the black box
Kadefors, A. (2004) · International Journal of Project Management · doi:10.1016/s0263-7863(03)00031-0 · Cited by 584
Management of risks, uncertainties and opportunities on projects: time for a fundamental shift
Jaafari, A. (2001) · International Journal of Project Management · doi:10.1016/s0263-7863(99)00047-2 · Cited by 466 · cited 2×
“…Lyons 2003; Walker and Johannes 2003; Cano and Cruz 2002; Elkington and Smallman 2002; Velde and Donk 2002; Grimsey and Lewis 2002; Duffield 2001; Jaafari 2001; Raz and Michael 2001; Floricel and Miller 2001; Turner and Simister 2001; Berends 2000; Dey 1999; Barber et al. 1999; Standards…”
BackgroundManaging Risk in Construction Projects
Smith, N. J. T., Merna, T., & Jobling, P. E. (1998) · Cited by 425
Use and benefits of tools for project risk management
Raz, T., & Michael, E. (2001) · International Journal of Project Management · doi:10.1016/s0263-7863(99)00036-8 · Cited by 402 · cited 2×
“…Walker and Johannes 2003; Cano and Cruz 2002; Elkington and Smallman 2002; Velde and Donk 2002; Grimsey and Lewis 2002; Duffield 2001; Jaafari 2001; Raz and Michael 2001; Floricel and Miller 2001; Turner and Simister 2001; Berends 2000; Dey 1999; Barber et al. 1999; Standards Association of…”
BackgroundProject risk management in the Queensland engineering construction industry: a survey
Lyons, T., & Skitmore, M. (2004) · International Journal of Project Management · doi:10.1016/s0263-7863(03)00005-x · Cited by 340
Innovation and learning in complex offshore construction projects
Barlow, J. (2000) · Research Policy · doi:10.1016/s0048-7333(00)00115-3 · Cited by 329 · cited 1×
“…2003; Bower et al. 2002; Gallagher 2002; Hoisie 2001; Scott 2001; NAO 2001; Bresnen and Marshall 2000; Association of Consultant Architects 2000; Barlow 2000; Carr et al. 1999; ACA 1999; Bennett and Jayes 1998; Baldry 1998; Egan 1998; Pietroforte 1997; Li and Green 1996; Crowley and Karim 1995;…”
BackgroundMotivation, commitment and the use of incentives in partnerships and alliances
Bresnen, M., & Marshall, N. (2000) · Construction Management and Economics · doi:10.1080/014461900407392 · Cited by 266 · cited 1×
“…Rahman and Kumaraswamy 2004, 2002b; Kadefors 2004; Walker and Hampson 2003; Bower et al. 2002; Gallagher 2002; Hoisie 2001; Scott 2001; NAO 2001; Bresnen and Marshall 2000; Association of Consultant Architects 2000; Barlow 2000; Carr et al. 1999; ACA 1999; Bennett and Jayes 1998; Baldry 1998;…”
BackgroundJoint risk management through transactionally efficient relational contracting
Rahman, M. M., & Kumaraswamy, M. M. (2002) · Construction Management and Economics · doi:10.1080/01446190110089682 · Cited by 251
Procurement strategies : a relationship-based approach
Walker, D. H. T., & Hampson, K. D. (2003) · QUT ePrints (Queensland University of Technology) · Cited by 250
Risk and its management in the Kuwaiti construction industry: a contractors’ perspective
Kartam, N. A., & Kartam, S. A. (2001) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00014-4 · Cited by 249 · cited 1×
“…management in the © ASCE / DECEMBER 2007 conceptual phase of a project Uher and Toakley 1999 ; 14 risks perceived by the BOT road project participants in India Thomas et al. 2003 ; and 15 Kuwaiti contractors’ perspectives on construction risks and the mitigation strategies Kartam and Kartam 2001 .”
BackgroundStrategizing for anticipated risks and turbulence in large-scale engineering projects
Floricel, S., & Miller, R. (2001) · International Journal of Project Management · doi:10.1016/s0263-7863(01)00047-3 · Cited by 228
Project contract management and a theory of organization
Turner, J. R., & Simister, S. (2001) · International Journal of Project Management · doi:10.1016/s0263-7863(01)00051-5 · Cited by 226
Contracting Relationship Trends and Transitions
Rahman, M. M., & Kumaraswamy, M. M. (2004) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(2004)20:4(147 · Cited by 215 · cited 4×
“Rahman and Kumaraswamy 2004, 2002a, b concluded that the construction industry is moving towards joint risk management by the application of partnering principles.”
BackgroundInfluential(2017) · Project Management for Engineering, Business and Technology · doi:10.4324/9781315676319-22 · Cited by 212
Project risk analysis and management—PRAM the generic process
Chapman, C. (1997) · International Journal of Project Management · doi:10.1016/s0263-7863(96)00079-8 · Cited by 205 · cited 4×
“Clients and contractors need to establish constructive dialogue involving input to each other’s risk management process Chapman 1997 , in which participants are able to disseminate project experiences such that planning, design, and management procedures may benefit from a continual learning…”
BackgroundInfluentialRisk Management Perceptions and Trends of U.S. Construction
Kangari, R. (1995) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(1995)121:4(422 · Cited by 203 · cited 2×
“Risk management is an important part of the decision-making process in construction Kangari 1995 , and now widely accepted as a vital tool in the management of projects Wood and Ellis 2003 .”
BackgroundMethodRisk management in the conceptual phase of a project
Uher, T. E., & Toakley, A. R. (1999) · International Journal of Project Management · doi:10.1016/s0263-7863(98)00024-6 · Cited by 175 · cited 1×
“…tools, and techniques currently used by consultants Wood and Ellis 2003 ; 13 risk management in the © ASCE / DECEMBER 2007 conceptual phase of a project Uher and Toakley 1999 ; 14 risks perceived by the BOT road project participants in India Thomas et al. 2003 ; and 15 Kuwaiti contractors’…”
MethodManaging project risks: a case study from the utilities sector
Elkington, P., & Smallman, C. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00034-x · Cited by 167 · cited 2×
“…of risk management techniques has been studied and introduced in the literature COSO 2004; Lyons 2003; Walker and Johannes 2003; Cano and Cruz 2002; Elkington and Smallman 2002; Velde and Donk 2002; Grimsey and Lewis 2002; Duffield 2001; Jaafari 2001; Raz and Michael 2001; Floricel and Miller…”
BackgroundTriangulation in construction management research*
Love, P. E. D., Holt, G. D., & Li, H. (2002) · Engineering Construction and Architectural Management · doi:10.1046/j.1365-232x.2002.00226.x · Cited by 164
Conceptual Model of Partnering
Crowley, L. G., & Karim, M. A. (1995) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(1995)11:5(33 · Cited by 162
Project risk management in Hong Kong
Shen, L. (1997) · International Journal of Project Management · doi:10.1016/s0263-7863(96)00045-2 · Cited by 160 · cited 2×
“Previous empirical studies on risk management practice are mainly regarding: 1 perceptions of the typical large United States contractors towards construction risk allocation, and the importance of different risk categories Kangari 1995 ; 2 usage of techniques at different risk management stages of major United Kingdo…”
Communication and governance in the building process
Pietroforte, R. (1997) · Construction Management and Economics · doi:10.1080/014461997373123 · Cited by 159 · cited 2×
“... alliancing, and relationship contracting that adopt cooperative philosophy to seek congruence in objectives Tang et al. 2006, 2004; Rahman and Kumaraswamy 2004, 2002b; Kadefors 2004; Walker and Hampson 2003; Bower et al. 2002; Gallagher 2002; Hoisie 2001; Scott 2001; NAO 2001; Bresnen and Marshall 2000; Associatio…”
BackgroundFactors Affecting Contractors' Risk of Cost Overburden
Akinci, B., & Fischer, M. A. (1998) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(1998)14:1(67 · Cited by 155
Risks in Chinese Construction Market—Contractors’ Perspective
Fang, D., Li, M., Fong, P. S. W., & Shen, L. (2004) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2004)130:6(853 · Cited by 134 · cited 1×
“…various analytical techniques for risk assessment in Hong Kong Shen 1997 ; 6 various risks perceived by the contractors in Chinese construction market Fang et al. 2004 ; 7 critical risks associated with China’s build-operate-transfer BOT projects and the effectiveness of mitigation measures Wang…”
MethodRisk management trends in the construction industry: moving towards joint risk management
Rahman, M. M., & Kumaraswamy, M. M. (2002) · Engineering Construction & Architectural Management · doi:10.1108/eb021210 · Cited by 121
Value management practices of leading UK cost consultants
Ellis, R. C. T., Wood, G. D., & Keel, D. A. (2005) · Construction Management and Economics · doi:10.1080/01446190500040711 · Cited by 116
Risk response techniques employed currently for major projects
Baker, S., Ponniah, D. A., & Smith, S. D. (1999) · Construction Management and Economics · doi:10.1080/014461999371709 · Cited by 116 · cited 1×
“…importance of different risk categories Kangari 1995 ; 2 usage of techniques at different risk management stages of major United Kingdom companies Baker 1999; Baker et al. 1999 ; 3 usage of risk management techniques and barriers to risk management in the Queensland engineering construction…”
BackgroundCase study of government initiatives for PRC's BOT power plant project
Wang, S. Q., & Tiong, L. K. (2000) · International Journal of Project Management · doi:10.1016/s0263-7863(98)00072-6 · Cited by 98 · cited 1×
“The World Bank has estimated that China’s expenditure in infrastructure will soon be the highest among all East Asian countries and is expected to account for $750 billion United States over the period 1995‐2004 Wang and Tiong 2000 .”
BackgroundRisk management practices of leading UK cost consultants
Wood, G. D., & Ellis, R. C. T. (2003) · Engineering Construction & Architectural Management · doi:10.1108/09699980310489960 · Cited by 93 · cited 3×
“Thus there has been an increase in research aimed at investigating risk management practice in the construction industry Wood and Ellis 2003 .”
BackgroundMethodThe evaluation of risk management in public sector capital projects
Baldry, D. (1998) · International Journal of Project Management · doi:10.1016/s0263-7863(97)00015-x · Cited by 89 · cited 5×
“…2001; Scott 2001; NAO 2001; Bresnen and Marshall 2000; Association of Consultant Architects 2000; Barlow 2000; Carr et al. 1999; ACA 1999; Bennett and Jayes 1998; Baldry 1998; Egan 1998; Pietroforte 1997; Li and Green 1996; Crowley and Karim 1995; Hanly and Valence 1993; Cowan 1992; CII 1991 .”
BackgroundInfluentialProcess re-engineering for effective implementation of projects
Dey, P. K. (1999) · International Journal of Project Management · doi:10.1016/s0263-7863(98)00023-4 · Cited by 64
Construction industry joint venture behaviour in Hong Kong—designed for collaborative results?
Walker, D. H. T., & Johannes, D. S. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(01)00064-3 · Cited by 53 · cited 1×
“A variety of risk management techniques has been studied and introduced in the literature COSO 2004; Lyons 2003; Walker and Johannes 2003; Cano and Cruz 2002; Elkington and Smallman 2002; Velde and Donk 2002; Grimsey and Lewis 2002; Duffield 2001; Jaafari 2001; Raz and Michael 2001; Floricel and…”
BackgroundSurvey of Risk Management in Major U.K. Companies
Baker, S., Ponniah, D. A., & Smith, S. D. (1999) · Journal of Professional Issues in Engineering Education and Practice · doi:10.1061/(asce)1052-3928(1999)125:3(94 · Cited by 52
Reducing user-related risks during and prior to system development
Jiang, J. J., Klein, G. L., Chen, H.-G., & Lin, L. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(01)00049-7 · Cited by 43 · cited 1×
“Thus, organizations should spend more effort up front to put a foundation for improving communication, resolving conflicts, and making process improvements among participants Jiang et al. 2002 .”
Background
Cited by
A critical review of 3D printing in construction: benefits, challenges, and risks
El-Sayegh, S., Romdhane, L., & Manjikian, S. (2020) · Archives of Civil and Mechanical Engineering · doi:10.1007/s43452-020-00038-w · Cited by 387
Identifying and assessing critical risk factors for BIM projects: Empirical study
Chien, K.-F., Wu, Z.-H., & Huang, S.-C. (2014) · Automation in Construction · doi:10.1016/j.autcon.2014.04.012 · Cited by 317
Risk Assessment and Allocation in Highway Construction Projects in the UAE
El-Sayegh, S. M., & Mansour, M. H. (2015) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000365 · Cited by 236
Xia, N., Zou, P. X. W., Griffin, M. A., Wang, X., & Zhong, R. (2018) · International Journal of Project Management · doi:10.1016/j.ijproman.2018.03.006 · Cited by 229
“Among the included literature, empirical surveys in various countries or regions also reveal that although practitioners desire joint RM, in reality, the mechanism for such a joint effort is lacking (Choudhry and Iqbal, 2013; Nguyen and Chileshe, 2015; Tang et al., 2007).”
BackgroundFactors affecting contractors’ risk attitudes in construction projects: Case study from China
Wang, J., & Yuan, H. (2011) · International Journal of Project Management · doi:10.1016/j.ijproman.2010.02.006 · Cited by 216
“According to Teo and Loosemore (2001), the attitude is based on individual’s positive or negative evaluation on consequences of a particular type of behavior, as well as personal beliefs or knowledge about the consequences.”
BackgroundInfluential
Metadata
- Authors
- Tang, W., Qiang, M., Duffield, C. F., Young, D. M., & Lu, Y.
- Venue
- Journal of Construction Engineering and Management
- Published
- 2007-12
- Volume
- 133
- Issue
- 12
- Pages
- 944-956
- ISSN
- 0733-9364 (ISSN-L)
- 1943-7862
- DOI
- 10.1061/(asce)0733-9364(2007)133:12(944
- OpenAlex
- W2158619472
- Cited by
- 198
- References
- 38
- FWCI
- 3.81
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.