The construction industry as a loosely coupled system: implications for productivity and innovation
The DOI matches its Crossref record; 37 of the 37 references it cites were found in a registry or an index.
Abstract
Previous research suggests that the construction industry is characterized by (1) particular complexity factors owing to industry specific uncertainties and interdependences, and (2) inefficiency of operations. The aim of this study was to analyse the operations and behaviour of firms as a means of dealing with complexity. The observations made indicate that the industry as a whole is featured as a loosely coupled system. Taking this as a starting point, the couplings among activities, resources and actors were analysed in different dimensions. The pattern of couplings builds on two interdependent layers: tight couplings in individual projects and loose couplings based on collective adaptations in the permanent network. It is concluded that the pattern of couplings seems to favour short term productivity while hampering innovation and learning.
Overview
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
Claims other papers make about this one
Each is checked against this paper’s own text: does it say what the citing paper says it does?
In the citing paper
“but also on the fact that the construction industry is characterized by slow adaptation to new technologies (Dubois and Gadde 2002 )”
From A review of LLMs and their applications in the architecture, engineering and construction industry (2025) · cites this paper as Dubois and Gadde 2002
Citations
Cites
Educational Organizations as Loosely Coupled Systems
Weick, K. E. (1976) · Administrative Science Quarterly · doi:10.2307/2391875 · Cited by 5,142
Organizations and Environments
Hougland, J. G., Shepard, J. M., & Aldrich, H. E. (1980) · The Academy of Management Review · doi:10.2307/257814 · Cited by 2,862
Capturing Value from Knowledge Assets: The New Economy, Markets for Know-How, and Intangible Assets
Teece, D. J. (1998) · California Management Review · doi:10.2307/41165943 · Cited by 2,617 · cited 1×
“According to Teece (1998) the opportunities for learning are closely related to previous activities and experiences: if many aspects of a rm’s learning environment change simultaneously the ability to form cognitive structures favouring learning becomes severely restricted.”
BackgroundLoosely Coupled Systems: A Reconceptualization
Orton, J. D., & Weick, K. E. (1990) · The Academy of Management Review · doi:10.2307/258154 · Cited by 2,431 · cited 5×
“Researchers should not simplify the concept but invoke it: ‘what elements are loosely coupled, what domains are they coupled on, and what are the characteristics of the couplings and decouplings?’ (Orton and Weick, 1990).”
BackgroundInfluentialIf Only We Knew What We Know: Identification and Transfer of Internal Best Practices
O'Dell, C., & Grayson, C. J. (1998) · California Management Review · doi:10.2307/41165948 · Cited by 1,543
von Krogh, G. (1998) · California Management Review · doi:10.2307/41165947 · Cited by 1,453
Managing Business Relationships
(2017) · Project Management · doi:10.1201/9780203710739-11 · Cited by 1,307
Powell, W. W. (1998) · California Management Review · doi:10.2307/41165952 · Cited by 1,096 · cited 3×
“These conditions differ from the situation in many other industries (Powell, 1998).”
BackgroundInfluentialBrown, J. S., & Duguid, P. (1998) · California Management Review · doi:10.2307/41165945 · Cited by 911
The four roles of supply chain management in construction
Vrijhoef, R., & Koskela, L. (2000) · European Journal of Purchasing & Supply Management · doi:10.1016/s0969-7012(00)00013-7 · Cited by 862 · cited 6×
“They are loose in terms of the coupling between the production of building materials and what is done on site; see e.g. Vrijhoef and Koskela (2000) and Akintoye et al. (2000).”
BackgroundInfluentialHybrid Organizational Arrangements: New Form or Transitional Development?
Powell, W. W. (1987) · California Management Review · doi:10.2307/41165267 · Cited by 630 · cited 1×
“This is a problem when learning is concerned because ‘heterogeneity and interdependence are greater spurs to collaborative action than homogeneity and discipline’ (Powell 1998: 231). In construction the resources of different suppliers are quite homogeneous and a contractor could not expect to learn more from one of t…”
BackgroundGadde, L., Håkansson, H., & Persson, G. (2010) · Cited by 563
Self-citationOrganizations and Environments.
de Ven, A. H. V., & Aldrich, H. E. (1979) · Administrative Science Quarterly · doi:10.2307/2392504 · Cited by 551 · cited 2×
“These collective adaptations are formed in what can be identified as ‘a community of practice’ (Brown and Duguid 1998). These authors discuss the preconditions for learning and argue that ‘a great deal of knowledge is both preserved and held collectively’ (p. 91). Collective knowledge is generated when people work tog…”
BackgroundA survey of supply chain collaboration and management in the UK construction industry
Akintoye, A., McIntosh, G., & Fitzgerald, E. (2000) · European Journal of Purchasing & Supply Management · doi:10.1016/s0969-7012(00)00012-5 · Cited by 549 · cited 2×
“Vrijhoef and Koskela (2000) and Akintoye et al. (2000). The loose couplings result from the rather long lead times and the ‘slack’ provided by distributors.”
BackgroundManaging Business Relationships
Watson, D., & Jones, A. (2013) · Digital Forensics Processing and Procedures · doi:10.1016/b978-1-59749-742-8.00014-5 · Cited by 435 · cited 1×
“On the other hand, interaction in close relationships can be used as means for reducing other types of uncertainty, for example need uncertainty and transaction uncertainty (Ford et al., 1998).”
Persistence and loose coupling in living systems
Glassman, R. B. (1973) · Behavioral Science · doi:10.1002/bs.3830180202 · Cited by 387 · cited 4×
“For example, Loasby (1976) argues that learning cannot take place through anonymous contracting but requires continuous interaction through which individuals and companies increasingly 'commits to the group and thus becomes one within the group'.”
BackgroundInfluentialGann, D. M. (1996) · Construction Management and Economics · doi:10.1080/014461996373304 · Cited by 385 · cited 8×
“Gidado (1996) further emphasized this view by stating that there is a continuous increase in the complexity of construction projects.”
BackgroundInfluentialChoice, Complexity and Ignorance.
Jones-Lee, M. W., & Loasby, B. J. (1977) · Economica · doi:10.2307/2553725 · Cited by 368
Bureaucratic and Craft Administration of Production: A Comparative Study
Stinchcombe, A. L. (1959) · Administrative Science Quarterly · doi:10.2307/2390676 · Cited by 368
Supply strategy and network effects — purchasing behaviour in the construction industry
Dubois, A., & Gadde, L.-E. (2000) · European Journal of Purchasing & Supply Management · doi:10.1016/s0969-7012(00)00016-2 · Cited by 313
Self-citationRelational competence and strategic procurement management
Cox, A. (1996) · European Journal of Purchasing & Supply Management · doi:10.1016/0969-7012(95)00019-4 · Cited by 294 · cited 2×
“A number of authors argue that construction has failed in adopting techniques that have improved performance in other industries, such as just-in-time (Low and Mok 1999), total quality management (Shammas-Thoma et al 1998), partnering with suppliers ( Cox 1996 ), the supply chain principle and ‘industrialization’ of m…”
BackgroundProject complexity: The focal point of construction production planning
Gidado, K. I. (1996) · Construction Management and Economics · doi:10.1080/014461996373476 · Cited by 294 · cited 8×
“Gidado (1996) further emphasized this view by stating that there is a continuous increase in the complexity of construction projects.”
BackgroundInfluentialIn search of relevance: Project management in drifting environments
Kreiner, K. (1995) · Scandinavian Journal of Management · doi:10.1016/0956-5221(95)00029-u · Cited by 266 · cited 1×
“Kreiner (1995) pointed out the danger of the short term based project focus, arguing that the fact that projects occupy only a bracket in time, and thus have neither history nor future, allows evolutionary processes little scope for improving performance’.”
BackgroundCox, A., & Thompson, I. (1997) · European Journal of Purchasing & Supply Management · doi:10.1016/s0969-7012(97)00005-1 · Cited by 207 · cited 7×
“Cox and Thompson (1997) argued that because the constellation of actors is continually changing it is dif cult to make use of experience gained in previous projects.”
BackgroundInfluentialInstitutions in building projects: Implications for flexibility and change
Kadefors, A. (1995) · Scandinavian Journal of Management · doi:10.1016/0956-5221(95)00017-p · Cited by 182 · cited 5×
“According to Kadefors (1995) the existence of joint industry standards simplifies work considerably.”
BackgroundInfluentialEccles, R. G. (1981) · Administrative Science Quarterly · doi:10.2307/2392517 · Cited by 165
Shields, M. W. (1997) · Springer eBooks · doi:10.1007/978-1-4471-0933-4_18 · Cited by 122
Organizational structures in the construction industry
Shirazi, B., Langford, D. A., & Rowlinson, S. (1996) · Construction Management and Economics · doi:10.1080/014461996373467 · Cited by 97 · cited 2×
“Received 7 March 2002; accepted 13 June 2002 Previous research suggests that the construction industry is characterized by (1) particular complexity factors owing to industry speci c uncertainties and interdependences, and (2) inef ciency of operations.”
BackgroundThe application of JIT philosophy to construction: a case study in site layout
Pheng, L. S., & Hui, M. S. (1999) · Construction Management and Economics · doi:10.1080/014461999371268 · Cited by 96
Interdependence and Uncertainty
Crichton, C. (2013) · Routledge eBooks · doi:10.4324/9781315013688 · Cited by 90
Contracting strategies for the project environment
Thompson, I., Cox, A. M., & Anderson, L. J. (1998) · European Journal of Purchasing & Supply Management · doi:10.1016/s0969-7012(98)00005-7 · Cited by 78 · cited 3×
“The outcome of this procedure is that the constellation of rms involved in the temporary network does not have joint plans beyond the project (Thompson et al., 1998).”
BackgroundInfluentialObstacles to implementing total quality management in the UK construction industry
Shammas‐Toma, M., Seymour, D., & Clark, L. (1998) · Construction Management and Economics · doi:10.1080/014461998372475 · Cited by 72 · cited 1×
“Shammas-Toma et al. (1998) argued that the tendering system and the short term perspective are to blame for many shortcomings in construction, for example the problems of adopting concurrent engineering practices and the dif culties in integrating design and building activities.”
BackgroundUnderstanding construction supply chains: an alternative interpretation
Vrijhoef, R., Koskela, L., & Howell, G. A. (2001) · University of Salford Institutional Repository (University of Salford) · Cited by 69
The virtual corporation: learning from construction
Kornelius, L. L., & Wamelink, H. (1998) · Supply Chain Management An International Journal · doi:10.1108/13598549810244278 · Cited by 61 · cited 2×
“We agree with Kornelius and Warmelink (1998), who argued that coordination through bilateral relationships is problematic in construction.”
BackgroundSupply Network Strategies, Wiley, Chichester.
Gadde, L., & Håkansson, H. (2001) · Chalmers Publication Library (Chalmers University of Technology) · Cited by 48
Self-citationMarketing of Housebuilding Materials
Cox, R., & Goodman, C. S. (1956) · Journal of Marketing · doi:10.1177/002224295602100105 · Cited by 48 · cited 2×
“The consequences were discussed by Crichton (1966, p. 22): ‘. . . there is no input of commonly shared experience of other building processes. Each member of the building team brings little more than his own accumulated experiences (and prejudices) to bear on current problems. Learning, in the sense of adaptations bro…”
BackgroundMarketing of Housebuilding Materials
Cox, R., & Goodman, C. S. (1956) · Journal of Marketing · doi:10.2307/1247698 · Cited by 21
Research works printed but not linked: 6
- Björkegren, C. Learning for the next project. Proceedings of the 3rd Conference on Organisational Learning. Edited by: Easterby-Smith, M., Araujo, I. and Burgoyne, J. pp.107–123. Lancaster University.
- Crichtori C., 1966, Interdependence and Uncertainly: A Study of the Building Industry
- Gadde L. E., 2001, Supply Newwork Strategies
- Meyer J., 1975, Notes on a structure of educational organizations; quoted in Weick (1976)
- Powell W., 1991, Markets, Hierarchies & Networks, 265
- Winch G., 1987, Managing Construction Worldwide, Vol. 2, Productivity and Human factors
Cited by
Environmental impacts and decarbonization strategies in the cement and concrete industries
Habert, G., Miller, S. A., John, V. M., Provis, J. L., Favier, A., Horvath, A., & Scrivener, K. L. (2020) · Nature Reviews Earth & Environment · doi:10.1038/s43017-020-0093-3 · Cited by 1,572
Oesterreich, T. D., & Teuteberg, F. (2016) · Computers in Industry · doi:10.1016/j.compind.2016.09.006 · Cited by 1,526
“Uncertainty: As each construction project is a time-limited, sitebased unique undertaking, there exists a lack of complete specification for processes and sub-processes and uniformity of materials, work and teams at construction site, resulting in an unpredictable environment [10].”
BackgroundUsing the Gioia Methodology in international business and entrepreneurship research
Magnani, G., & Gioia, D. (2023) · International Business Review · doi:10.1016/j.ibusrev.2022.102097 · Cited by 484
Key influences on construction innovation
Blayse, A. M., & Manley, K. (2004) · Construction Innovation · doi:10.1108/14714170410815060 · Cited by 527
“Industry relationships have an extremely significant influence on construction innovation (Anderson and Manseau, 1999; Miozzo and Dewick, 2002; Dubois and Gadde, 2002).”
BackgroundInfluentialDallasega, P., Rauch, E., & Linder, C. (2018) · Computers in Industry · doi:10.1016/j.compind.2018.03.039 · Cited by 468
Metadata
- Authors
- Dubois, A., & Gadde, L.-E.
- Affiliations
- Chalmers University of Technology (SE)
- ORCID
- Dubois, Anna
- Venue
- Construction Management and Economics
- Publisher
- Informa UK Limited
- Published
- 2002-10
- Volume
- 20
- Issue
- 7
- Pages
- 621-631
- ISSN
- 0144-6193 (ISSN-L)
- 1466-433X
- OpenAlex
- W2162531320
- Cited by
- 1,041
- References
- 36
- Citations by year
- 2026: 48 · 2025: 47 · 2024: 32 · 2023: 41 · 2022: 66 · 2021: 66 · 2020: 71 · 2019: 73 · 2018: 72 · 2017: 56 · 2016: 61 · 2015: 53 · 2014: 59 · 2013: 59 · 2012: 47
- FWCI
- 12.62
- Type
- journal article
- Language
- en
- Open access
- closed
- Locations
- Construction Management and Economics (publishedVersion)
- RePEc: Research Papers in Economics (submittedVersion)
- Topics
- Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
- Social Sciences › Business, Management and Accounting › Management of Technology and Innovation › Product Development and Customization
- Physical Sciences › Engineering › Building and Construction › BIM and Construction Integration
- Keywords
- construction industry, loosely coupled systems, tight coupling, project networks, interorganizational networks, complexity, uncertainty, productivity, innovation, organizational learning
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.