Rethinking the project life cycle – how circularity challenges processes, roles and governance
Open accessAbstract
The pressing need for sustainability transitions requires not only new project outcomes, but also new ways of leading and organizing projects. The study aims to examine how circularity, understood as the reuse and recycling of materials, challenges the conventional project life cycle by changing processes, roles, and governance. A case of a nature-based park constructed with circular materials was conducted using interviews, observations, and site visits. The results show that circularity reshapes project leadership in three key ways. First, circular material sourcing requires an iterative and adaptive project process, which extends the front-end and overlaps with delivery. This disrupts linear, stage-gated models and introduces ongoing decision-making and flexible planning throughout the lifecycle. Second, the changing process reconfigures project roles: project managers take on expanded and evolving leadership, including facilitating collaboration, managing uncertainty, and communicating sustainability values across phases. Third, the findings underscore the need for adaptive governance, including engaged clients and flexible contracting, to support circular practices. These insights extend existing research on sustainability in and by projects by showing how circularity is not merely a design principle but an organizing logic that restructures internal processes, leadership roles, and governance arrangements. The study advances theory on how circularity functions not only as a sustainability goal but also as a transformative force in project organizing and leadership. • Circularity reshapes project processes into iterative, adaptive structures • Project roles become fluid, cross-phase, and value-driven • Leadership shifts from coordination to sustainability facilitation • Circularity demands new governance with active clients and flexible contracts • Circularity acts as an organizing principle, not just a project goal
Verified 2026-11-10 · 3 references not checked yet
Overview
AI snapshot
Written from the paper’s full text.
TL;DR
This case study of a Swedish municipal park built with circular materials shows that circularity disrupts conventional linear project life cycles, turning front-end and delivery into overlapping, iterative processes. It argues circularity is not just a sustainability goal but an organizing logic that reshapes project roles and governance.
Key findings
- Circular material sourcing made the project process iterative and adaptive: the front-end extended and overlapped with delivery, with design, material sourcing, and construction running in parallel rather than as stage-gated phases. The project used 30,000 m³ of clay masses for topography, and finalization was pushed from Fall 2024 to Spring 2025 due to delays in surrounding building projects.
- Project roles became fluid and cross-phase. The same person held the Project manager and Site manager roles; the Landscape architect stayed involved during construction, whereas in traditional projects the architect estimated 70% of hours go to design and documentation. The Project manager used on-site hand-drawing and continuous communication to convey the design to contractors.
- Governance required flexibility plus a clear aim. The project ran on a running account, relied on a conceptual sketch and continuous decision-making, and the team described construction standards as inflexible for this iterative way of working. The paper calls for engaged clients, flexible contracting, and value-aligned governance to support circular practices.
Methods
- Abductive single-case study of a public municipal park and recreational area in Örebro, Sweden: 70,000 m² nature-like park with playground, using local material reuse, life cycle planning, and ecological design.
- Data collected June 2023–March 2025 through group interviews, e-mail interviews, observation of project meetings, project documents, and a site visit; participants were the Strategic planner, Project manager/Site manager, and consultant Landscape architect.
- Analysis used iterative coding, sorted into two main categories: conveying circularity and changes in project organizing, with comparison to traditional construction project management.
Limitations
- The paper states it draws on a single case and that further empirical research is needed to confirm and complement the findings in diverse project contexts; future research should assess outcomes of circularity, including environmental benefits and cost implications.
- Evident from the text: the case is deliberately small and “mundane” in budget, length, and number of actors, with a three-person core team, so findings are used for analytical rather than statistical generalization.
- Evident from the text: the study follows processes and roles but does not report quantified environmental or cost outcomes of the circular approach.
Model-written summary. Check it against the paper before relying on it.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
1 of 51 cited sources checked · 1 supported · 0 flagged
- Study design and conductcitation§ 3.1. Case study approach · p. 5
The case was chosen as a deviant case to current literature on sustainability aspects in project organizing.
“The case of following the processes of constructing a park, including a playground and recreational area, in the municipality of ¨ Orebro, Sweden, was chosen as a deviant case (Flyvbjerg, 2006) to the current literature on sustainability aspects in project organizing.”
Quote in the paperSubstantial claim1 of 1 sources checked- cites Flyvbjerg, 2006 source
- Findingown data§ [https://doi.org/10.1016/j.plas.2025.100194](https://doi.org/10.1016/j.plas.2025.100194) · p. 2
The case project embedded circularity principles from the outset, including local material reuse, life cycle planning, and ecological design.
“While modest in scope, the project embedded circularity principles from the outset, including local material reuse, life cycle planning, and ecological design.”
Quote in the paperSubstantial claim - Findingcitation§ 5.2. Redefining project roles · p. 8
Human interaction played a significant role, compared to socialized leadership.
“Human interaction also played a significant role, compared to socialized leadership (Whyte et al., 2022).”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Whyte et al., 2022 source
A check is scheduled.
- Findingown data§ 4.2. Changes of roles from flexible project processes · p. 7
The group interviews and observations clearly indicate changes in the roles following the iterative project processes, especially for the Project manager and the Landscape architect.
“The group interviews and observations clearly indicate changes in the roles following the iterative project processes, especially for the Project manager and the Landscape architect.”
Quote in the paperSubstantial claim - Findingown data§ 5.2. Redefining project roles · p. 8
A main finding from following the iterative project processes was the need to appoint a committed Project manager to convey circularity throughout the project life cycle.
“A main finding from following the iterative project processes was the need to appoint a committed Project manager to convey circularity throughout the project life cycle.”
Quote in the paperSubstantial claim
- Findingnone given§ 5.2. Redefining project roles · p. 8
Circularity, by using available reused material, was adopted as an approach for sustainability in and by the project.
“Circularity, by using available reused material, was adopted as an approach for sustainability in and by the project.”
Quote in the paperSubstantial claim - Findingown data§ 5.1. Iterative project processes · p. 8
Compared to conventional project life cycle phases, which are linear, this project illustrated a process where the phases were more parallel.
“Compared to the conventional project life cycle phases, where the process is linear (Williams et al., 2019), this project illustrated a process where the phases were more parallel.”
Quote in the paperSubstantial claim0 of 1 sources checked- cites Williams et al., 2019 source
- Findingcitation§ 5.1. Iterative project processes · p. 8
The project team could not rely solely on previous experience, adding to the uncertainty often observed at the front end of projects.
“The project team could not rely solely on previous experience, adding to the uncertainty often observed at the front end of projects (Williams et al., 2019).”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Williams et al., 2019 source
- Findingreasoning§ 5.2. Redefining project roles · p. 8
This was a new approach, which put pressure on communicating the project's core values and goals.
“This was a new approach, which put pressure on communicating the project ' s core values and goals.”
Quote in the paperNot a substantial claim - Findingnone given§ 5.1. Iterative project processes · p. 8
Rather than emphasizing early decision-making, decisions are consistently made considering the project's aim.
“Rather than emphasizing early decision-making, decisions are consistently made considering the project ' s aim.”
Quote in the paperSubstantial claim - Findingown data§ 5.2. Redefining project roles · p. 8
When adapting to a circular approach, the balance between project management and site management practices was influenced and facilitated by a committed Project manager, in collaboration with the Landscape architect, whose role was prolonged to include the construction phase.
“It was evident that when adapting to a circular approach, the balance between project management and site management practices was influenced and facilitated by a committed Project manager, in collaboration with the Landscape architect, whose role was prolonged to include the con struction phase.”
Quote in the paperSubstantial claim - Findingreasoning§ 5.1. Iterative project processes · p. 8
In circular projects, an iterative process occurs where the project team works with a conceptual sketch, creates a target vision, and adapts to changing conditions.
“Instead, an iterative process occurs where the project team works with a conceptual sketch of the design, creates a target vision, and adapts depending on the changing conditions.”
Quote in the paperSubstantial claim - Findingnone given§ 5.2. Redefining project roles · p. 8
When interacting with the contractors on site, the idea sketches were not enough as a communication medium.
“When interacting with the contractors on site, the idea sketches were not enough as a communication medium.”
Quote in the paperSubstantial claim - Findingown data§ Table 4 · p. 6
Project planning and project delivery were merged rather than separated in this project.
“it became evident during the initial analysis of the data that these two phases were merged rather than separated in this project.”
Quote in the paperSubstantial claim - Findingown data§ 3.4. Data analysis · p. 6
Changes from traditional construction project management were triggered by the project's strong circularity ambition.
“We focused on changes from traditional construction project manage ment, as an example of stage-gate model management, triggered by the project ' s strong circularity ambition, see Table 4.”
Quote in the paperSubstantial claim- Rests on an assumption: The changes in project processes and roles observed in the case were caused by the circularity ambition rather than other factors such as project size, budget, or individual personalities.
- Findingreasoning§ 5.1. Iterative project processes · p. 8
The planning of the project and the design were still ongoing when the construction started.
“The planning of the project and the design were still ongoing when the construction started.”
Quote in the paperSubstantial claim - Findingown data§ Table 4 · p. 6
The project processes were found to be interdependent with the roles of the key participants.
“The project processes were found to be interdependent with the roles of the key participants in the projects”
Quote in the paperSubstantial claim - Findingown data§ 6. Conclusions · p. 9
Circularity changes project processes from linear, stage-gated sequences into iterative and adaptive structures.
“First, it shows how circularity changes project processes from linear, stage-gated sequences into iterative and adaptive structures.”
Quote in the paperSubstantial claim - Findingown data§ 6. Conclusions · p. 9
Project actor roles, particularly that of the project manager, become more fluid, collaborative, and cross-phase.
“Second, the study demonstrates how project actor roles, particularly that of the project manager, become more fluid, collaborative, and cross-phase.”
Quote in the paperSubstantial claim - Findingcitation§ 5.3. Governance aspects · p. 8
Flexible and iterative processes were adopted to make decisions in the project, which has previously been suggested as a response to challenges created by uncertainty.
“In this way, flexible and iterative processes were adopted to make decisions in the project, which has previously been suggested as a response to challenges created by uncertainty (Enembreck et al., 2024).”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Enembreck et al., 2024
Couldn’t be matched to a paper in Crossref, so it can’t be checked.
- Findingreasoning§ 5.3. Governance aspects · p. 8
With the iterative process, the objective needed to be upheld, conveyed and comprehended by all project participants, as detailed planning and design documents were not available.
“With the iterative process, the objective needed to be upheld, conveyed and comprehended by all project participants, as detailed planning and design documents were not available.”
Quote in the paperSubstantial claim - Interpretationreasoning§ 5.1. Iterative project processes · p. 8
Conventional projects can lock main solutions early because their prerequisites are rather stable.
“This can be done since the prerequisites are rather stable; for example, it is assumed that the materials needed for the project are available within the budget.”
Quote in the paperSubstantial claim- The authors state this as an assumption: In conventional projects, the materials needed for the project are available within the budget.
- Interpretationreasoning§ 5.1. Iterative project processes · p. 8
Circularity necessitates non-linear, adaptive organizing.
“Circularity necessitates non- linear, adaptive organizing”
Quote in the paperSubstantial claim - Premisecitation§ [https://doi.org/10.1016/j.plas.2025.100194](https://doi.org/10.1016/j.plas.2025.100194) · p. 2
The role of circularity in reshaping project practices and redefining actor roles remains underexplored.
“In particular, the role of circularity in reshaping project practices and redefining actor roles remains underexplored.”
Quote in the paperSubstantial claim - Premisecitation§ 5.1. Iterative project processes · p. 8
A more agile approach to project management facilitates decisions for uncertainty and innovation.
“Previous studies show that a more agile approach to project management facili tates decisions for e.g. uncertainty and innovation (Ansari et al., 2024; Enembreck et al., 2024).”
Quote in the paperSubstantial claim0 of 2 sources checked- cites Ansari et al., 2024 source
Checked before — its earlier verdict is held back until a new check runs.
- cites Enembreck et al., 2024
Couldn’t be matched to a paper in Crossref, so it can’t be checked.
- Premisecitation§ 2.2. Circularity in construction · p. 4
Public procurement literature on circular construction projects often focuses on tender criteria and implementation in the client organization, while contracting is a less common focus.
“These studies often focus on tender criteria (Fuentes-Bargues et al., 2017) and implementation in the client organization (Igarashi et al., 2017), while a less common focus is on contracting”
Quote in the paperSubstantial claim0 of 2 sources checked - Interpretationcitation§ 5.1. Iterative project processes · p. 8
The investigated project exemplifies the integration of circularity in the front-end phase, which is still an emerging practice for achieving sustainability by projects.
“This exemplifies the integration of circularity in the front-end phase, which is still an emerging practice for achieving sustainability by projects (Bertozzi, 2022).”
Quote in the paperSubstantial claim0 of 1 sources checked- cites Bertozzi, 2022
Couldn’t be matched to a paper in Crossref, so it can’t be checked.
- Interpretationreasoning§ 5.1. Iterative project processes · p. 8
The front-end phase, or shaping the projects, was prolonged and merged with the construction/delivery phase.
“However, one could argue that the front-end phase, or shaping the projects, was prolonged and merged with the con struction/delivery phase.”
Quote in the paperSubstantial claim - Interpretationreasoning§ [https://doi.org/10.1016/j.plas.2025.100194](https://doi.org/10.1016/j.plas.2025.100194) · p. 2
The case project's ambitions required the project team to adapt roles, processes, and governance practices beyond traditional norms.
“These ambitions required the project team to adapt roles, processes, and governance practices beyond traditional norms.”
Quote in the paperSubstantial claim - Premisecitation§ 5.1. Iterative project processes · p. 8
Conventional projects tend to lock the main solutions and options early in the front-end.
“Conventional projects tend to lock the main solutions and options early on, already in the front-end (Winch, 1998; Rokio et al., 2024).”
Quote in the paperSubstantial claim0 of 2 sources checked - Interpretationreasoning§ 4.2. Changes of roles from flexible project processes · p. 7
The risk of losing this volume of hours may incentivize landscape architects to promote the traditional way of working.
“Thus, the risk of losing this volume of hours may incentivize landscape architects to promote the traditional way of working.”
Quote in the paperSubstantial claim - Premisecitation§ 2.2. Circularity in construction · p. 4
The integration of circular solutions in the design phase is not a common practice.
“The integration of circular solutions in the design phase is, however, not a common practice (Bertozzi, 2022).”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Bertozzi, 2022
Couldn’t be matched to a paper in Crossref, so it can’t be checked.
- Premisecitation§ [https://doi.org/10.1016/j.plas.2025.100194](https://doi.org/10.1016/j.plas.2025.100194) · p. 2
Incorporating circular solutions during front-end phases remains rare.
“However, incorporating circular solutions during front-end phases remains rare (Bertozzi, 2022).”
Quote in the paperSubstantial claim0 of 1 sources checked- cites Bertozzi, 2022
Couldn’t be matched to a paper in Crossref, so it can’t be checked.
- Premisecitation§ [https://doi.org/10.1016/j.plas.2025.100194](https://doi.org/10.1016/j.plas.2025.100194) · p. 2
The front-end phases of the project life cycle are where significant strategic decisions are made.
“The front-end phases of the project life cycle are where significant strategic decisions are made (Miller and Hobbs, 2005; Williams et al., 2019).”
Quote in the paperSubstantial claim0 of 2 sources checked - Interpretationown data§ 1. Introduction · p. 1
Circular material sourcing requires an iterative and adaptive project process, which extends the front-end and overlaps with delivery.
“First, circular material sourcing requires an iterative and adaptive project process, which extends the front-end and overlaps with delivery.”
Quote in the paperSubstantial claim- Rests on an assumption: The case project is representative enough that findings about circularity's challenges can be generalized to other construction projects.
- Premisecitation§ 1. Introduction · p. 1
There is a gap in understanding how projects can contribute to the necessary sustainable transition in society, specifically through leadership, focusing on both sustainability practices in a project and sustainability by projects.
“Overall, there is a gap in understanding how projects can contribute to the necessary sustainable transition in society (Winch, 2022), specifically through leadership, focusing on both the sustainability practices in a project and sustainability by projects (Huemann and Silvius, 2017).”
Quote in the paperSubstantial claim0 of 2 sources checked- cites Winch, 2022
Couldn’t be matched to a paper in Crossref, so it can’t be checked.
- cites Huemann and Silvius, 2017 source
A check is scheduled.
- Interpretationreasoning§ 5.1. Iterative project processes · p. 8
When unknowns such as reused materials are introduced, upfront early decision-making is no longer possible.
“However, when unknowns, such as reused materials, are introduced into the equation, this upfront early-on decision-making is no longer possible.”
Quote in the paperSubstantial claim - Interpretationreasoning§ 1. Introduction · p. 1
The changing process reconfigures project roles: project managers take on expanded and evolving leadership, including facilitating collaboration, managing uncertainty, and communicating sustainability values across phases.
“Second, the changing process reconfigures project roles: project managers take on expanded and evolving leadership, including facilitating collaboration, managing uncertainty, and communicating sustainability values across phases.”
Quote in the paperSubstantial claim- Rests on an assumption: The case project is representative enough that findings about circularity's challenges can be generalized to other construction projects.
- Interpretationcitation§ 5.3. Governance aspects · p. 8
Control mechanisms take on a distinct configuration when aligned with a project's sustainability goals, suggesting that these in sustainable project management may differ significantly from those used in conventional projects.
“This confirms previous research stating that control mechanisms take on a distinct configuration when aligned with a project ' s sustainability goals, suggesting that these in S. Lingegård and S. Hedborg sustainable project management may differ significantly from those used in conventional projects (Kivil ¨ a et al., 2017).”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Kivilä et al., 2017 source
A check is scheduled.
- Interpretationreasoning§ 6. Conclusions · p. 9
Circularity is not merely a sustainability goal, but an organizing principle that reshapes how projects are structured, led, and delivered.
“Together, these insights position circularity not merely as a sus tainability goal, but as an organizing principle that reshapes how pro jects are structured, led, and delivered.”
Quote in the paperSubstantial claim
- Probably not a substantial claim. 54
- It may state two separate claims as one. 46
Probably not a substantial claim. The paper’s conclusions may not depend on it. It may state two separate claims as one.
Findingown data§ 4.2. Changes of roles from flexible project processes · p. 7The importance of motivation among involved individuals is not often discussed; people are often seen as resources in projects.
“The Strategic planner says the impor tance of motivation among the involved individuals is not often dis cussed. Instead, people are often seen as resources in projects.”
Quote in the paperNot a substantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it.
Findingnone given§ 5.1. Iterative project processes · p. 8Decisions affect the next line of divisions, such as what plants to use.
“These decisions also affect the next line of divisions, e.g., what plants to use.”
Quote in the paperNot a substantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it. It may state two separate claims as one.
Findingown data§ 3.2. Case description · p. 5The project budget does not allow for classical material for plant beds, so other circular materials are in focus.
“The project budget does not allow for classical material for plant beds, such as planting soil instead, other circular materials are in focus.”
Quote in the paperNot a substantial claimProbably not a substantial claim.
Findingnone given§ 4.2. Changes of roles from flexible project processes · p. 7The Landscape architect estimated that 70% of the hours a Landscape architect puts into a traditional project are associated with the design and documentation process.
“In fact, the Landscape architect estimated that 70 % of the hours a Landscape architect puts into a traditional project are associated with the design and documentation process.”
Quote in the paperSubstantial claimProbably not a substantial claim. The authors may not put it forward as true. The paper’s conclusions may not depend on it. It may state two separate claims as one.
Findingown data§ 4.2. Changes of roles from flexible project processes · p. 7The Project manager owns the vision and must be mandated to continuously make decisions on the construction site.
“The Strategic planner noted that the Project manager owns the vision, and this person must be mandated to continuously make decisions on the construction site.”
Quote in the paperNot a substantial claimProbably not a substantial claim. It may state two separate claims as one.
Findingown data§ 4.1. Circularity challenging project processes · p. 7The process does not have to be linear; different tracks run in parallel.
“The Strategic planner emphasized that the process does not have to be linear. Instead, different tracks run in parallel.”
Quote in the paperSubstantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it.
Findingnone given§ 4.2. Changes of roles from flexible project processes · p. 7In this project, the Landscape architect works more collaboratively with the Project manager than in traditional projects.
“In this project, the Landscape architect works more collaboratively with the Project manager than in traditional projects”
Quote in the paperNot a substantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it.
Findingreasoning§ 4.1. Circularity challenging project processes · p. 7With less experience, more control is needed.
“However, they argue that with less experience, more control is needed.”
Quote in the paperNot a substantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it.
Findingown data§ 4.1. Circularity challenging project processes · p. 7The use of standards is related to the Project manager's experience.
“The use of standards is related to the Project manager ' s experience, according to the project group.”
Quote in the paperNot a substantial claimIt may state two separate claims as one.
Findingreasoning§ 3.2. Case description · p. 5The trajectory toward the desired outcome necessitated a new strategy for material sourcing, and the municipality, the Landscape architect, and the contractor all needed to modify their planning and construction procedures.
“The trajectory toward the desired outcome also necessitated a new strategy for material sourcing, and the municipality, the Landscape architect, and the contractor all needed to modify their planning and construction procedures.”
Quote in the paperNot a substantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it.
Findingown data§ 4.1. Circularity challenging project processes · p. 7A high level of communication is necessary for their new way of working.
“According to the Strategic planner, a high level of communication is necessary for their new way of working.”
Quote in the paperNot a substantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it.
Findingown data§ 3.3. Data collection · p. 5The data from observations and interviews revealed the intricate and interconnected changes required to incorporate circularity into the project.
“While the data from observations and interviews revealed the intri cate and interconnected changes required to incorporate circularity into the project”
Quote in the paperNot a substantial claimProbably not a substantial claim. The authors may not put it forward as true. The paper’s conclusions may not depend on it. It may state two separate claims as one.
Findingown data§ 4.1. Circularity challenging project processes · p. 7Standards are good for minimizing cheating and providing quality, but they are difficult to adapt.
“Standards are good for minimizing cheating and providing quality, but they are difficult to adapt according to the Strategic planner.”
Quote in the paperNot a substantial claimIt may state two separate claims as one.
Findingown data§ 5. Discussion · p. 7Cost was essential but not the project's only target; social and ecological sustainability values were also crucial.
“Although cost was essential, it was not the project ' s only target. Social and ecological sustainability values were also crucial in the targets.”
Quote in the paperSubstantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it.
Findingown data§ 4.2. Changes of roles from flexible project processes · p. 7Using less detailed documentation creates the need for new ways for the Project manager to communicate the design to the contractor.
“Using less detailed documentation creates the need for new ways for the Project manager to communicate the design to the contractor”
Quote in the paperNot a substantial claimProbably not a substantial claim. The authors may not put it forward as true. The paper’s conclusions may not depend on it.
Findingown data§ 4.1. Circularity challenging project processes · p. 7Having a flexible process and making decisions along the way would have been impossible unless there was clarity on the final result.
“According to the project group, having this flexible process and making decisions along the way would have been impossible unless there was clarity on the final result.”
Quote in the paperNot a substantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it.
Findingown data§ 4.2. Changes of roles from flexible project processes · p. 7Landscape architects traditionally evaluate the design process but not the results.
“The Landscape architect adds that they traditionally evaluate the design process but not the results”
Quote in the paperNot a substantial claimIt may state two separate claims as one.
Findingnone given§ 5.1. Iterative project processes · p. 8Not all the circular materials were sourced, and therefore the design was not set.
“Not all the circular materials were sourced, and therefore, the design was not set.”
Quote in the paperNot a substantial claimIt may state two separate claims as one.
Findingcitation§ 5. Discussion · p. 7Circular material use was at the forefront of the design to reduce impact on nature and keep costs down.
“To reduce the impact on nature and to keep costs down, circular material use was at the forefront of the design, as seen by Huemann and Silvius (2017).”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Huemann and Silvius, 2017 source
A check is scheduled.
It may state two separate claims as one.
Findingnone given§ 5.1. Iterative project processes · p. 8In the investigated project, new approaches were combined with an unknown availability of circular materials.
“For the investigated project, new approaches were combined with an unknown availability of circular materials.”
Quote in the paperSubstantial claimIt may state two separate claims as one.
Findingown data§ 4.1. Circularity challenging project processes · p. 7Decisions were consistently made with the target vision into consideration, continuously communicated by the Strategic planner and Project manager.
“Rather than placing emphasis on early decision-making in the project, decisions were consistently made with the target vision into consideration, continuously communicated by the Strategic planner and Project manager.”
Quote in the paperNot a substantial claimIt may state two separate claims as one.
Findingown data§ 3.4. Data analysis · p. 6The Project manager's conviction and dedication to circularity stood out as important in guiding the organizing, including how the Project manager took on the role as Site manager.
“In this initial analysis, the Project manager ' s conviction and dedication to circularity stood out as important in guiding the organizing, including how the Project manager took on the role as Site manager”
Quote in the paperNot a substantial claimIt may state two separate claims as one.
Findingreasoning§ 4.1. Circularity challenging project processes · p. 7The design phase, including the conceptual sketch, the material sourcing, and the construction phase, were running in parallel and iterated when needed.
“In this way, the design phase, including the conceptual sketch, the material sourcing, and the construction phase, were running in parallel and iterated when needed.”
Quote in the paperSubstantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it. It may state two separate claims as one.
Findingreasoning§ 3.2. Case description · p. 5Extensive testing was needed because some substances are released when crushed materials are used.
“However, extensive testing was needed, especially since some substances are released when crushed materials are used.”
Quote in the paperNot a substantial claimIt may state two separate claims as one.
Findingown data§ 4.2. Changes of roles from flexible project processes · p. 7In this project, one person holds both the role of the Project manager and the Site manager, while traditionally these roles are divided between two people.
“In this project, one person holds both the role of the Project manager and the Site manager, while traditionally, these roles are divided be tween two people for construction projects.”
Quote in the paperNot a substantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it.
Findingown data§ 4.1. Circularity challenging project processes · p. 7The project team considers current standards inflexible.
“The project team considers current standards inflexible.”
Quote in the paperNot a substantial claimProbably not a substantial claim. It may state two separate claims as one.
Findingown data§ 4.2. Changes of roles from flexible project processes · p. 7The flexibility in the process requires increased availability of the Project manager on-site to answer questions continuously, changing the leadership style.
“The Project manager explained that the flexibility in the process they want requires increased availability of the Project manager on-site to answer questions continuously, changing the leadership style.”
Quote in the paperSubstantial claimIt may state two separate claims as one.
Findingnone given§ 3.1. Case study approach · p. 5The project context is mundane in terms of budget, length and number of actors, rather than a large, complex project, but circularity is at the forefront of the project aim and circular materials are used at a large scale.
“The project context is mundane (in terms of budget, length and number of actors), rather than a large, complex project, but circularity is still at the forefront of the project aim and circular materials are used at a large scale.”
Quote in the paperSubstantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it. It may state two separate claims as one.
Findingreasoning§ 5.2. Redefining project roles · p. 8The project group emphasized the need to see project participants as humans with emotions and not 'resources', as involvement can benefit the project's outcome.
“This is imperative, as the project group emphasized the need to see project participants as humans with emo tions and not 'resources ' , as involvement can benefit the project ' s outcome.”
Quote in the paperNot a substantial claimIt may state two separate claims as one.
Findingown data§ 6. Conclusions · p. 9Leadership shifts from a focus on coordination and control to facilitation and the interpretation of sustainability values, with expanded responsibilities taken on by roles such as the landscape architect and strategic planner.
“Leadership shifts from a focus on coordination and control to facilitation and the interpretation of sustainability values, with expanded responsibilities taken on by roles such as the landscape architect and strategic planner.”
Quote in the paperSubstantial claimProbably not a substantial claim. It may state two separate claims as one.
Findingown data§ 5.3. Governance aspects · p. 8The respondents argue that the standards used in the construction industry to control quality are not adapted to this iterative way of working, especially not in combination with the aim of creating a park integrated with nature, which conflicts with the conventional notion of beauty.
“However, in general, they argue that the standards used in the construction industry to control quality are not adapted to this iterative way of working, especially not in combination with the aim of creating a park integrated with nature, which conflicts with the conventional notion of”
Quote in the paperSubstantial claimIt may state two separate claims as one.
Findingown data§ 5.2. Redefining project roles · p. 8The Project manager stopped referring to changes and treated them as merely part of the process, illustrating a shift from seeing change as undesirable to becoming a natural piece of the puzzle, and presumably also shifted the contractors' mindset.
“In fact, the Project manager stopped referring to them as changes and merely part of the process, illustrating a shift from seeing change as undesirable to becoming a natural piece of the puzzle, and presumably, also shifted the contractors ' mindset.”
Quote in the paperNot a substantial claimIt may state two separate claims as one.
Findingown data§ 6. Conclusions · p. 9The front-end becomes extended and overlaps with delivery, reflecting the uncertain and dynamic availability of reused materials and requiring ongoing decision-making throughout the project lifecycle.
“The frontend becomes extended and overlaps with delivery, reflecting the un certain and dynamic availability of reused materials and requiring ongoing decision-making throughout the project lifecycle.”
Quote in the paperSubstantial claimProbably not a substantial claim.
Findingown data§ 5.3. Governance aspects · p. 8The respondents argue for adapted documentation, with different types and levels of specificity depending on where they are in the process.
“The respondents argue for adapted documentation, with different types and levels of specificity depending on where they are in the process.”
Quote in the paperSubstantial claimIt may state two separate claims as one.
Findingown data§ 5.2. Redefining project roles · p. 8The project manager frequently used the mandate to make decisions as they occurred continuously, and changes were frequent as the idea sketches had to be adapted not only to the circular materials but also to the conditions on-site.
“The project manager frequently used the mandate to make decisions as they occurred continuously, and changes were frequent as the idea sketches had to be adapted not only to the circular materials but also to the conditions on-site.”
Quote in the paperSubstantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it.
Findingown data§ 5.3. Governance aspects · p. 8The findings show that a clear distinction between control and flexibility can be detected in the discussion in the group interviews.
“Adding to the ongoing discussion on how to balance flexibility and control in projects (Bygballe et al., 2021; Sydow and Windeler, 2020), the findings show that a clear distinction between control and flexibility can be detected in the dis cussion in the group interviews.”
Quote in the paperNot a substantial claim0 of 2 sources checkedIt may state two separate claims as one.
Findingreasoning§ 5.3. Governance aspects · p. 8While flexibility is needed for the project actors to create opportunities to work with circular materials, control in terms of a clear aim and a conceptual sketch for the project was essential.
“While flexibility is needed for the project actors to create opportunities to work with circular materials, control in terms of a clear aim and a conceptual sketch for the project was essential.”
Quote in the paperSubstantial claimIt may state two separate claims as one.
Findingnone given§ 5.3. Governance aspects · p. 9While the Project manager's involvement and capacity to be present in different parts of the project contributed to its success, it also underscored a vulnerability regarding scalability.
“Furthermore, while the Project manager ' s involvement and capacity to be present in different parts of the project contributed to its success, it also underscored a vulnerability regarding scalability.”
Quote in the paperSubstantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it.
Premisecitation§ 2.2. Circularity in construction · p. 4Waste recycling, such as crushing materials for road construction, is the most common circular practice in the construction industry.
“Waste recycling, e.g., crushing materials for road construction, is the most common circular practice in the construction industry”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Fo ˇ rt and ˇ Cerný, 2020
Couldn’t be matched to a paper in Crossref, so it can’t be checked.
Probably not a substantial claim.
Premisecitation§ 2.2. Circularity in construction · p. 4The construction industry is not sustainable and circular enough due to organizational patterns such as lack of long-term relationships and increasing complexity of multi-partner project organizations.
“Havinga et al. (2023) call for new approaches in the construction industry, suggesting that the reason the construction industry is not sustainable and circular enough is due to organizational patterns such as the lack of long-term relationships and the increasing complexity of multi-partner project organizations.”
Quote in the paperSubstantial claim0 of 1 sources checked- cites Havinga et al., 2023 source
Probably not a substantial claim.
Premisecitation§ 3.1. Case study approach · p. 5A case study methodology is appropriate for comprehensive examination of complex matters involving numerous variables.
“When conducting a comprehensive examination of complex matters involving numerous variables, a case study methodology is appropriate (Merriam, 1998; Yin, 2014).”
Quote in the paperSubstantial claim0 of 2 sources checked- cites Merriam, 1998
Couldn’t be matched to a paper in Crossref, so it can’t be checked.
- cites Yin, 2014
Couldn’t be matched to a paper in Crossref, so it can’t be checked.
Probably not a substantial claim. It may state two separate claims as one.
Interpretationreasoning§ 5.1. Iterative project processes · p. 8Circularity introduces role fluidity and leadership in uncertainty.
“Introduces role fluidity and leadership in uncertainty”
Quote in the paperSubstantial claimIt may state two separate claims as one.
Interpretationown data§ 5. Discussion · p. 7Adopting circular approaches in a project created iterative processes, redefined project roles, and challenged governance structures.
“With these widened targets, the current study illustrates how adopting circular approaches in a project created iterative processes, redefined project roles, and challenged governance structures.”
Quote in the paperSubstantial claim- Rests on an assumption: The changes in project processes and roles observed in the case were caused by the circularity ambition rather than other factors such as project size, budget, or individual personalities.
- Rests on an assumption: The case is sufficiently similar to other construction projects to allow analytical generalization to broader project organizing and leadership for sustainability and circularity.
Probably not a substantial claim.
Premisecitation§ 2.2. Circularity in construction · p. 4Interdependencies among actors need to be understood to benefit from circularity.
“the interdependencies among actors need to be understood to benefit from circularity (Lingegård et al., 2021)”
Quote in the paperSubstantial claim0 of 1 sources checked- cites Lingegård et al., 2021 source
Probably not a substantial claim. It may state two separate claims as one.
Study design and conductcitation§ 3.1. Case study approach · p. 5The case was selected based on the project actors' commitment to circular material usage and that it was small enough to analyze how changes followed from actions and decisions.
“The case was selected based on the project actors ' commitment to circular ma terial usage and that it was small enough to analyze how changes fol lowed from actions and decisions”
Quote in the paperSubstantial claimProbably not a substantial claim. It may be too vague to check against evidence.
Interpretationreasoning§ [https://doi.org/10.1016/j.plas.2025.100194](https://doi.org/10.1016/j.plas.2025.100194) · p. 2The case provides a grounded empirical basis for advancing theory on how circularity functions not only as a sustainability goal but also as a transformative force in project organizing.
“As such, the case provides a grounded empirical basis for advancing theory on how circularity functions not only as a sustainability goal but also as a transformative force in project organizing.”
Quote in the paperNot a substantial claim- Rests on an assumption: The case project is representative enough that findings about circularity's challenges can be generalized to other construction projects.
Probably not a substantial claim. The paper’s conclusions may not depend on it.
Study design and conductcitation§ 3.3. Data collection · p. 5The data were triangulated for validation.
“In this way, the data were further triangulated for validation (Eisenhardt, 1989).”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Eisenhardt, 1989 source
It may state two separate claims as one.
Interpretationreasoning§ 5. Discussion · p. 7The project altered the project organizing and the management's leadership.
“This study examined a project with sustainability values aiming to create a low-maintenance park integrated into nature, thereby not just challenging the traditional project outcome of constructing a park and playground but altering the project organizing and the managements ' leadership.”
Quote in the paperSubstantial claim- Rests on an assumption: The changes in project processes and roles observed in the case were caused by the circularity ambition rather than other factors such as project size, budget, or individual personalities.
- Rests on an assumption: The case is sufficiently similar to other construction projects to allow analytical generalization to broader project organizing and leadership for sustainability and circularity.
Probably not a substantial claim. The paper’s conclusions may not depend on it. It may state two separate claims as one.
Interpretationreasoning§ 4.1. Circularity challenging project processes · p. 7The project's aim and vision needed to be clear and communicated, using the conceptual sketch as one tool.
“That means the project ' s aim and vision needed to be clear and communicated, using the conceptual sketch as one tool.”
Quote in the paperNot a substantial claimProbably not a substantial claim. It may state two separate claims as one.
Interpretationreasoning§ 4.2. Changes of roles from flexible project processes · p. 7If the architect participated in the construction phase, the process would be more effective and learning would increase.
“Then, the process would be more effective, and the learning would increase since the architect would learn the consequences of the choices.”
Quote in the paperSubstantial claimProbably not a substantial claim. The authors may not put it forward as true. It may state two separate claims as one.
Interpretationown data§ 4.2. Changes of roles from flexible project processes · p. 7Landscape architects must find a new role to fit into this changed project process, where the role is also needed in the construction phase.
“According to the Strategic planner, the Landscape architects must find a new role to fit into this changed project process, where the role is also needed in the construc tion phase.”
Quote in the paperNot a substantial claimProbably not a substantial claim. It may be too vague to check against evidence.
Interpretationown data§ 3.1. Case study approach · p. 5The case offers an empirical foundation for advancing theory on circularity as not only a sustainability objective but also a driver of transformation in project organizing.
“The case offers an empirical foundation for advancing theory on circularity as not only a sustain ability objective but also a driver of transformation in project organizing.”
Quote in the paperNot a substantial claim- Rests on an assumption: The case is sufficiently similar to other construction projects to allow analytical generalization to broader project organizing and leadership for sustainability and circularity.
Probably not a substantial claim. The paper’s conclusions may not depend on it.
Study design and conductnone given§ 3.3. Data collection · p. 5The first author's notes were shared and discussed with the second author as a step for validation.
“These were shared and discussed with the second author as a step for validation.”
Quote in the paperNot a substantial claimIt may state two separate claims as one.
Premisecitation§ 5.1. Iterative project processes · p. 8Creating sustainability value is a co-creative process that is iterative and adaptive.
“This aligns with Keeys and Huemann (2017), describing a co-creative process of creating sustainability value that is iterative and adaptive.”
Quote in the paperSubstantial claim0 of 1 sources checked- cites Keeys and Huemann (2017) source
Probably not a substantial claim. The paper’s conclusions may not depend on it.
Interpretationcitation§ 5. Discussion · p. 7This confirms previous research on sustainability in project results, where a broader perspective than traditional cost, time, and quality is called for.
“This confirms previous research on sustain ability in project results, where a broader perspective than the tradi tional cost, time, and quality is called for”
Quote in the paperNot a substantial claim0 of 3 sources checkedIt may state two separate claims as one.
Interpretationown data§ 1. Introduction · p. 1Circular material sourcing disrupts linear, stage-gated models and introduces ongoing decision-making and flexible planning throughout the lifecycle.
“This disrupts linear, stage-gated models and introduces ongoing decision-making and flexible planning throughout the lifecycle.”
Quote in the paperSubstantial claim- Rests on an assumption: The case project is representative enough that findings about circularity's challenges can be generalized to other construction projects.
Probably not a substantial claim. The paper’s conclusions may not depend on it. It may state two separate claims as one.
Study design and conductnone given§ 3.3. Data collection · p. 5The data was compiled and written in detailed case descriptions, which the participants have approved, for added validity.
“Furthermore, the data was compiled and written in detailed case descriptions, which the participants have approved, for added validity.”
Quote in the paperNot a substantial claimProbably not a substantial claim.
Premisecitation§ [https://doi.org/10.1016/j.plas.2025.100194](https://doi.org/10.1016/j.plas.2025.100194) · p. 2Project-based organizing hinders sustainability, such as circularity.
“Havinga et al. (2023) suggest that project-based organizing hinders sustainability, such as circularity and call for updated project processes.”
Quote in the paperSubstantial claim0 of 1 sources checked- cites Havinga et al. (2023) source
Probably not a substantial claim. The paper’s conclusions may not depend on it. It may state two separate claims as one.
Premisecitation§ 2.2. Circularity in construction · p. 4In small-scale projects, new approaches are tested but experiences rarely spread to the whole construction sector and a critical mass of engaged actors.
“In small-scale projects, including fewer technical challenges, reduced risks, and fewer actors, new approaches are tested, the experiences rarely spread to the whole construction sector and a critical mass of engaged actors (Bertozzi, 2022).”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Bertozzi, 2022
Couldn’t be matched to a paper in Crossref, so it can’t be checked.
Probably not a substantial claim. The paper’s conclusions may not depend on it.
Premisecitation§ 5.1. Iterative project processes · p. 8Project shaping is the part of the front-end where ideas are formulated, tested, challenged, and reformulated in an iterative process.
“Miller and Hobbs (2005) describe project shaping as the part of the front-end where the ideas are formulated, tested, challenged, and reformulated in an iterative process.”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Miller and Hobbs (2005) source
Checked before — its earlier verdict is held back until a new check runs.
Probably not a substantial claim. The paper’s conclusions may not depend on it.
Premisecitation§ 5.1. Iterative project processes · p. 8The front-end phase is critical for committing to the sustainability value of the project.
“Furthermore, Rokio et al., 2024 state the front-end phase as critical for committing to the sustainability value of the project.”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Rokio et al., 2024 source
Probably not a substantial claim.
Study design and conductcitation§ 3.1. Case study approach · p. 5The findings are used for analytical generalization, extrapolating the results to a broader context of project organizing and leadership for sustainability and circularity.
“The findings are used for analytical generalization (Yin, 2014), extrapolating the results to a broader context of project organizing and leadership for sustainability and circularity.”
Quote in the paperSubstantial claim0 of 1 sources checked- cites Yin, 2014
Couldn’t be matched to a paper in Crossref, so it can’t be checked.
- Rests on an assumption: The case is sufficiently similar to other construction projects to allow analytical generalization to broader project organizing and leadership for sustainability and circularity.
It may state two separate claims as one.
Interpretationreasoning§ 1. Introduction · p. 1Circularity functions not only as a sustainability goal but also as a transformative force in project organizing and leadership.
“The study advances theory on how circularity functions not only as a sustainability goal but also as a transformative force in project organizing and leadership.”
Quote in the paperSubstantial claim- Rests on an assumption: The case project is representative enough that findings about circularity's challenges can be generalized to other construction projects.
Probably not a substantial claim. It may be too vague to check against evidence.
Interpretationown data§ 1. Introduction · p. 1Adaptive governance, including engaged clients and flexible contracting, is needed to support circular practices.
“Third, the findings underscore the need for adaptive governance, including engaged clients and flexible contracting, to support circular practices.”
Quote in the paperNot a substantial claim- Rests on an assumption: The case project is representative enough that findings about circularity's challenges can be generalized to other construction projects.
It may state two separate claims as one.
Premisecitation§ 5.1. Iterative project processes · p. 8There is a significant opportunity to create value in the front end, but also risks because uncertainty is high.
“Not only is there a significant opportunity to create value for the project in the front end, but also risks as uncertainty is high, see, e.g., Edkins et al. (2013).”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Edkins et al. (2013)
Couldn’t be matched to a paper in Crossref, so it can’t be checked.
Probably not a substantial claim. The paper’s conclusions may not depend on it. It may state two separate claims as one.
Premisecitation§ 5.2. Redefining project roles · p. 8The effectiveness and efficiency of project management are key for more sustainable processes and results, and the development of the Project manager's leadership and the suitability of the team are essential.
“The effectiveness and efficiency of project management are key for more sustainable processes and results, and for this, the development of the Project manager ' s leadership and the suitability of the team are essential (Magano et al., 2021).”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Magano et al., 2021 source
Probably not a substantial claim. The paper’s conclusions may not depend on it.
Premisecitation§ 5.2. Redefining project roles · p. 8Changing organizational values concerning sustainability is important.
“Previous research has stated the importance of changing organiza tional values concerning sustainability (de Almeida Vittori Ferreira et al., 2024)”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites de Almeida Vittori Ferreira et al., 2024 source
Probably not a substantial claim.
Study design and conductnone given§ 6. Conclusions · p. 9The study draws on a single case.
“As this study draws on a single case, further empirical research is needed to confirm and complement the findings in diverse project contexts.”
Quote in the paperSubstantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it. It may state two separate claims as one.
Premisecitation§ 5.2. Redefining project roles · p. 8Lack of communication and a uniform understanding of the sustainability strategy hinders implementation.
“and that the lack of communication and a uniform under standing of the sustainability strategy hinders implementation (Barendsen et al., 2021).”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Barendsen et al., 2021 source
Probably not a substantial claim. It may be too vague to check against evidence.
Interpretationcitation§ 6. Conclusions · p. 9Circularity is a valuable approach for projects aiming to combine sustainability of the projects and sustainability by the projects.
“The findings contribute by suggesting circularity as a valuable approach for projects aiming to combine sustainability of the projects and sustainability by the projects, see Huemann and Silvius (2017) and Magano et al. (2021).”
Quote in the paperNot a substantial claim0 of 2 sources checked- Rests on an assumption: Circular materials sourcing aims to increase resource efficiency during the project.
- Rests on an assumption: The project outcome can become ecologically sustainable.
It may state two separate claims as one.
Interpretationreasoning§ 6. Conclusions · p. 9Sustainability ambitions become operationalized through changes in processes, roles, and governance within everyday project contexts, and sustainability cannot be achieved without reconfiguring core project structures.
“In doing so, the study advances theory on sustainability-oriented project management (e.g., Silvius, 2017) by showing how sustainability ambitions become operationalized through changes in processes, roles, and governance within everyday project contexts, and debunks the assumption that sustainability can be achieved without reconfiguring core project structures.”
Quote in the paperSubstantial claim0 of 1 sources checked- cites Silvius, 2017 source
Checked before — its earlier verdict is held back until a new check runs.
It may state two separate claims as one.
Interpretationreasoning§ 5.3. Governance aspects · p. 9These challenges show the rationale for why circularity programs remain fragmented and have failed to achieve standardization.
“These challenges show the rationale for why circu larity programs remain fragmented and have failed to achieve standardization.”
Quote in the paperNot a substantial claimProbably not a substantial claim. It may be too vague to check against evidence. It may state two separate claims as one.
Interpretationreasoning§ 6. Conclusions · p. 9The findings highlight the need for new governance models that can support circular practices, including active client engagement, flexible contracting arrangements, and value-aligned procurement strategies.
“Third, the findings highlight the need for new governance models that can support circular practices, including active client engagement, flexible con tracting arrangements, and value-aligned procurement strategies.”
Quote in the paperNot a substantial claimProbably not a substantial claim. It may be too vague to check against evidence. The paper’s conclusions may not depend on it.
Interpretationreasoning§ 5.3. Governance aspects · p. 8The notion of re-evaluating beauty, as an example of targeted value, is essential for both circular ambitions and a sustainable outcome.
“As such, the notion of re-evaluating beauty, as an example of targeted value, is essential for both circular ambitions and a sustainable outcome.”
Quote in the paperNot a substantial claimProbably not a substantial claim. It may be too vague to check against evidence.
Interpretationreasoning§ 5.3. Governance aspects · p. 9There is a necessity for a framework that facilitates the expansion of circularity efforts within projects.
“This marks the necessity for a framework that facilitates the expansion of circularity efforts within projects.”
Quote in the paperNot a substantial claimProbably not a substantial claim. It may be too vague to check against evidence. It may state two separate claims as one.
Premisecitation§ 5.3. Governance aspects · p. 9An understanding of how short-term projects can foster long-term strategic change and increased cross-project knowledge transfer is needed.
“An understanding of how short-term projects can foster long-term strategic change (Lehtim ¨ aki et al., 2023) and increased cross-project knowledge transfer (Eikelenboom and van Marrewijk, 2024) are needed.”
Quote in the paperNot a substantial claim0 of 2 sources checked- cites Lehtimäki et al., 2023 source
Checked before — its earlier verdict is held back until a new check runs.
- cites Eikelenboom and van Marrewijk, 2024
Couldn’t be matched to a paper in Crossref, so it can’t be checked.
Probably not a substantial claim. The paper’s conclusions may not depend on it.
Premisecitation§ 5.3. Governance aspects · p. 8Decision support is needed to handle sustainability and circularity challenges that involve uncertainty.
“Previous research points to the need for decision support to handle sustainability and circularity challenges that involve uncertainty (Gibbin et al., 2023).”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Gibbin et al., 2023 source
Checked before — its earlier verdict is held back until a new check runs.
It may state two separate claims as one.
Premisecitation§ 5.2. Redefining project roles · p. 8Engagement is a key factor in aligning motivations between actors and objectives, and this becomes even more prominent for a project where the goals and conceptual sketch are essential in guiding the project processes.
“Engagement is a key factor in aligning motivations between actors and objectives (Bertozzi, 2022), and this becomes even more prominent for a project where the goals and conceptual sketch are essential in guiding the project processes.”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Bertozzi, 2022
Couldn’t be matched to a paper in Crossref, so it can’t be checked.
It may state two separate claims as one.
Premisecitation§ 5.2. Redefining project roles · p. 8Sustainability competence and awareness creates a change in the mindset of the project manager, which is essential for the sustainability outcome of the project.
“This type of sustainability competence and awareness creates a change in the mindset of the project manager, which is essential for the sustainability outcome of the project (Magano et al., 2021; Tabassi et al., 2016).”
Quote in the paperNot a substantial claim0 of 2 sources checkedProbably not a substantial claim. The paper’s conclusions may not depend on it.
Premisecitation§ 5.3. Governance aspects · p. 8The resilience of a designed landscape can be included in the evaluation of its beauty rather than a predetermined set of forms or types.
“For instance, the resilience of a designed landscape can be included in the evaluation of its beauty rather than a predetermined set of forms or types (Meyer, 2008).”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Meyer, 2008 source
Checked before — its earlier verdict is held back until a new check runs.
The paper relies on this without support.
The case project is representative enough that findings about circularity's challenges can be generalized to other construction projects.
“It allowed for the observation of how circular principles, when introduced early and pursued throughout, disrupt established project organizing and leadership logics”
The paper relies on this without support.
The changes in project processes and roles observed in the case were caused by the circularity ambition rather than other factors such as project size, budget, or individual personalities.
“We focused on changes from traditional construction project manage ment, as an example of stage-gate model management, triggered by the project ' s strong circularity ambition, see Table 4.”
The paper relies on this without support.
The case is sufficiently similar to other construction projects to allow analytical generalization to broader project organizing and leadership for sustainability and circularity.
“The findings are used for analytical generalization (Yin, 2014), extrapolating the results to a broader context of project organizing and leadership for sustainability and circularity.”
The authors state this as an assumption.
In conventional projects, the materials needed for the project are available within the budget.
“for example, it is assumed that the materials needed for the project are available within the budget.”
The paper relies on this without support.
Circular materials sourcing aims to increase resource efficiency during the project.
“This since circular materials sourcing aims to increase resource efficiency during the project, and the project outcome can become ecologically sustainable.”
The paper relies on this without support.
The project outcome can become ecologically sustainable.
“and the project outcome can become ecologically sustainable.”
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
Each contradiction between two passages listed here was confirmed by an independent check.
Data-collection period excludes the first listed interview
MinorThe stated data-collection period begins in June 2023, but the data-collection table lists a group interview on May 31, 2023.
“The data collection, conducted from June 2023 to March 2025”
“May 31st , 2023, 1,5 h”
Role comparison is attributed to the wrong table
MinorThe text directs readers to Table 2 for changes in the two roles, but Table 2 lists data-collection activities; the role comparison is Table 4.
“which presents the changes in the two roles in Table 2.”
“Table 4 Comparison of roles between traditional construction project management and circular construction projects.”
Collected data are attributed to the wrong table
MinorThe text says Table 1 details the collected data, whereas Table 1 reviews prior studies and Table 2 lists the data-collection activities.
“Table 1 presents the collected data in detail.”
“Table 2 Table with the data collection activities.”
Citations
Cites
Building Theories from Case Study Research
Eisenhardt, K. M. (1989) · The Academy of Management Review · doi:10.2307/258557 · Cited by 17,455
Five misunderstandings about case-study research
Flyvbjerg, B. (2006) · Qualitative Inquiry · doi:10.1177/1077800405284363 · Cited by 14,266
Systematic combining: an abductive approach to case research
Dubois, A., & Gadde, L.-E. (2002) · Journal of Business Research · doi:10.1016/s0148-2963(00)00195-8 · Cited by 4,941
Renaissance of case research as a scientific method
Ketokivi, M. A., & Choi, T. Y. (2014) · Journal of Operations Management · doi:10.1016/j.jom.2014.03.004 · Cited by 1,468
Taking Stock of Temporary Organizational Forms: A Systematic Review and Research Agenda
Bakker, R. M. (2010) · International Journal of Management Reviews · doi:10.1111/j.1468-2370.2010.00281.x · Cited by 687
Project sustainability strategies: A systematic literature review
Aarseth, W. K., Ahola, T., Aaltonen, K., Økland, A., & Andersen, B. S. (2016) · International Journal of Project Management · doi:10.1016/j.ijproman.2016.11.006 · Cited by 465
Temporary Organizing: Promises, Processes, Problems
Bakker, R. M., DeFillippi, R., Schwab, A., & Sydow, J. (2016) · Organization Studies · doi:10.1177/0170840616655982 · Cited by 398
Zephyrs of creative destruction: understanding the management of innovation in construction
Winch, G. (1998) · Building Research & Information · doi:10.1080/096132198369751 · Cited by 339
Sustainable project management through project control in infrastructure projects
Kivilä, J., Martinsuo, M., & Vuorinen, L. (2017) · International Journal of Project Management · doi:10.1016/j.ijproman.2017.02.009 · Cited by 301
Munaro, M. R., & Tavares, S. F. (2023) · Cleaner and Responsible Consumption · doi:10.1016/j.clrc.2023.100107 · Cited by 280
Lenferink, S., Tillema, T., & Arts, J. (2012) · International Journal of Project Management · doi:10.1016/j.ijproman.2012.09.014 · Cited by 201
Sustainability as a new school of thought in project management
Silvius, G. (2017) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2017.08.121 · Cited by 196
Governance regimes for large complex projects
Miller, R., & Hobbs, B. (2005) · Project Management Journal · doi:10.1177/875697280503600305 · Cited by 174
Projects to create the future: managing projects meets sustainable development
Huemann, M., & Silvius, G. (2017) · International Journal of Project Management · doi:10.1016/j.ijproman.2017.04.014 · Cited by 155
Project benefits co-creation: shaping sustainable development benefits
Keeys, L. A., & Huemann, M. (2017) · International Journal of Project Management · doi:10.1016/j.ijproman.2017.02.008 · Cited by 148
Gil, N. A., & Fu, Y. (2021) · Academy of Management Discoveries · doi:10.5465/amd.2020.0029 · Cited by 146
The front-end of projects: a systematic literature review and structuring
Williams, T., Vo, H., Samset, K., & Edkins, A. (2019) · Production Planning & Control · doi:10.1080/09537287.2019.1594429 · Cited by 145
Illankoon, I. M. C. S., & Vithanage, S. C. (2023) · Journal of Building Engineering · doi:10.1016/j.jobe.2023.107362 · Cited by 140
Fořt, J., & Černý, R. (2020) · Waste Management · doi:10.1016/j.wasman.2020.09.004 · Cited by 137
Factor dynamics to facilitate circular economy adoption in construction
Charef, R., & Lu, W. (2021) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2021.128639 · Cited by 130
Leadership competences of sustainable construction project managers
Tabassi, A. A., Roufechaei, K. M., Ramli, M., Bakar, A. H. A., Ismail, R., & Pakir, A. H. K. (2016) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2016.02.076 · Cited by 123
Sustaining beauty. The performance of appearance: A manifesto in three parts
Meyer, E. K. (2008) · Journal of Landscape Architecture · doi:10.1080/18626033.2008.9723392 · Cited by 118
The co-creation of values-in-use at the front end of infrastructure development programs
Liu, Y., van Marrewijk, A. H., Houwing, E.-J., & Hertogh, M. J. C. M. (2019) · International Journal of Project Management · doi:10.1016/j.ijproman.2019.01.013 · Cited by 101
Invernizzi, D. C., Locatelli, G., Velenturf, A. P. M., Love, P. E. D., Purnell, P., & Brookes, N. J. (2020) · Energy Policy · doi:10.1016/j.enpol.2020.111677 · Cited by 96
Email Interviews: A Guide to Research Design and Implementation
Dahlin, E. (2021) · International Journal of Qualitative Methods · doi:10.1177/16094069211025453 · Cited by 91
Industrial renewal within the construction network
Håkansson, H., & Havenvid, M. I. (2012) · Construction Management and Economics · doi:10.1080/01446193.2012.737470 · Cited by 84
Temporary organizing and permanent contexts
Sydow, J., & Windeler, A. (2020) · Current Sociology · doi:10.1177/0011392120907629 · Cited by 75
Sabini, L., & Alderman, N. (2021) · Project Management Journal · doi:10.1177/87569728211007660 · Cited by 67
The Effects of Megaproject Social Responsibility on Participating Organizations
Ma, H., Sun, D., Zeng, S., Lin, H., & Jonathan Jingsheng, S. H. I. (2021) · Project Management Journal · doi:10.1177/87569728211015868 · Cited by 60
Dewagoda, K. G., Ng, S. T., & Chen, J. (2022) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2022.135197 · Cited by 56
Whyte, J., & Mottee, L. (2022) · International Journal of Project Management · doi:10.1016/j.ijproman.2022.10.007 · Cited by 55
Environmental criteria in the Spanish public works procurement process
Fuentes-Bargues, J., González-Cruz, M., & González-Gaya, C. (2017) · International Journal of Environmental Research and Public Health · doi:10.3390/ijerph14020204 · Cited by 48
The human factor in agility: Exploring employee dedication in agile project organizations
Meier, A., & Kock, A. (2023) · International Journal of Project Management · doi:10.1016/j.ijproman.2023.102527 · Cited by 42
Magano, J., Silvius, G., Silva, C. S. E., & Leite, Â. (2021) · Project Leadership and Society · doi:10.1016/j.plas.2021.100020 · Cited by 40
Implementation of circular economy in construction projects: a procurement strategy approach
Ahmed, S., Majava, J., & Aaltonen, K. (2023) · Construction Innovation · doi:10.1108/ci-12-2022-0327 · Cited by 40
Gibbin, R. V., Sigahi, T. F. A. C., Pinto, J. D. S., Rampasso, I. S., & Anholon, R. (2023) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2023.137753 · Cited by 38
Barendsen, W., Muß, A. C., & Silvius, G. (2021) · Project Leadership and Society · doi:10.1016/j.plas.2021.100015 · Cited by 36
Sankaran, S., Müller, R., & Drouin, N. (2020) · Systems Research and Behavioral Science · doi:10.1002/sres.2744 · Cited by 35
Analyzing buyer behavior when selecting green criteria in public procurement
Igarashi, M., Boer, L. D., & Pfuhl, G. (2017) · Journal of Public Procurement · doi:10.1108/jopp-17-02-2017-b001 · Cited by 34
Strategic responses to external stakeholder influences
Nguyen, T. H. D., Chileshe, N., Rameezdeen, R., & Wood, A. (2022) · International Journal of Project Management · doi:10.1016/j.ijproman.2022.102434 · Cited by 33
Lingegård, S., & Lindahl, M. (2014) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2014.06.039 · Cited by 31
Self-citationGustavsson, T. K. (2018) · Construction Management and Economics · doi:10.1080/01446193.2018.1464197 · Cited by 29
Bertozzi, C. (2022) · City Culture and Society · doi:10.1016/j.ccs.2022.100446 · Cited by 29
Influence of transformational and transactional leadership on agile project success
Ansari, M. S. A., Abouraia, M., El Morsy, R., & Thumiki, V. R. R. (2024) · Project Leadership and Society · doi:10.1016/j.plas.2024.100136 · Cited by 28
Havinga, F., Mahdad, M., & Dolfsma, W. (2023) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2023.137455 · Cited by 25
The Temporality of Project Success: Vindeby, the World’s First Offshore Wind Farm
Feddersen, J., Koll, H., & Geraldi, J. G. (2023) · Project Management Journal · doi:10.1177/87569728231217231 · Cited by 25
de Almeida Vittori Ferreira, M., Morgado, C. D. R. V., & Estellita Lins, M. P. (2024) · Heliyon · doi:10.1016/j.heliyon.2023.e23762 · Cited by 25
Tied islands: The role of organizational members in knowledge transfer across strategic projects
Eikelenboom, M., & van Marrewijk, A. H. (2024) · International Journal of Project Management · doi:10.1016/j.ijproman.2024.102590 · Cited by 25
Lehtimäki, H., Jokinen, A., & Pitkänen, J. (2023) · International Journal of Project Management · doi:10.1016/j.ijproman.2023.102516 · Cited by 22
Rokio, M., Ahola, T., Alkki, L., & Ståhle, M. (2024) · International Journal of Project Management · doi:10.1016/j.ijproman.2024.102647 · Cited by 21
A routine dynamics lens on the stability-change dilemma in project-based organizations
Bygballe, L. E., Swärd, A., & Vaagaasar, A. L. (2021) · Project Management Journal · doi:10.1177/8756972820986660 · Cited by 20
Circular public procurement through integrated contracts in the infrastructure sector
Lingegård, S., Havenvid, M. I., & Eriksson, P.-E. (2021) · Sustainability · doi:10.3390/su132111983 · Cited by 20
Self-citationDemolishers or ‘material experts’? Project actors negotiating changing roles in sustainable projects
Eikelenboom, M., Oosterlee, M., & van Marrewijk, A. H. (2024) · International Journal of Project Management · doi:10.1016/j.ijproman.2024.102605 · Cited by 15
Han, Y., Yang, Q., & Tian, P. (2024) · Project Leadership and Society · doi:10.1016/j.plas.2024.100140 · Cited by 14
Barbero (2014) · doi:10.1016/j · Cited by 1
Flagged first, then by citations
Research works printed but not linked: 5
- Berg, 2019, Managing circular building projects. University of Tweente, Bertozzi, C. (2022). How is the construction sector perceiving and integrating the circular economy paradigm? Insights from the Brussels experience, City Cult. Soc., 29
- Edkins, 2013, Exploring the front-end of project management, Eng. Proj. Organ. J., 3, 71
- Terenzi, 2024, Projects as vectors of change: a transition toward net-zero sociotechnical systems, Proj. Manag. J., 0
- Whyte, 2022, Call for papers special collection: project leadership in a changing world, Project Leadership Soc., 3
- Winch, 2022, Projecting for sustainability transitions: advancing the contribution of peter morris, Eng. Proj. Organ. J., 11
Cited by
Sorted by citations
Editorial: Project leadership in a changing world
Whyte, J. K., Asadabadi, M. R., & Naderpajouh, N. (2025) · Project Leadership and Society · doi:10.1016/j.plas.2025.100200 · Cited by 1
Call for papers: Leading projects through time
Kortantamer, D., Delisle, J., & Alvehus, J. (2025) · Project Leadership and Society · doi:10.1016/j.plas.2025.100195
Call for papers: Circular economy in project management
(2025) · International Journal of Project Management · doi:10.1016/j.ijproman.2025.102797
Rokio, M., Ahola, T., & Ståhle, M. (2026) · Project Leadership and Society · doi:10.1016/j.plas.2026.100220
From waste to worth: Stakeholders’ sensemaking of value in circular projects
Khadim, N., Brouwer, C., & van Marrewijk, A. H. (2026) · International Journal of Project Management · doi:10.1016/j.ijproman.2026.102890
Graiff, M., & Cassalini, G. (2026) · Lund University Publications Student Papers (Lund University)
Al-Thanya, S. M., Gündüz, M., & Naji, K. K. (2026) · Buildings · doi:10.3390/buildings16183662
Tumpa, R. J., Amponsah-Asante, L. N. A., Botchway, B., Eduam, E. J., & Gyimah, S. (2026) · Engineering Construction & Architectural Management · doi:10.1108/ecam-04-2026-0721
Homeostatic governance: A grounded theory study of board engagement with projects
Lawler, C., Killen, C. P., & Sankaran, S. (2026) · Project Leadership and Society · doi:10.1016/j.plas.2026.100247
From vision to reality: How ‘sustainability’ is accomplished in projects
Sabini, L., Muzio, D., & Clegg, S. R. (2026) · European Management Review · doi:10.1111/emre.70119
Metadata
- Authors
- Lingegård, S., & Hedborg, S.
- Affiliations
- KTH Royal Institute of Technology (SE)
- Uppsala University (SE)
- Corresponding author
- Lingegård, Sofia
- Venue
- Project Leadership and Society
- Publisher
- Elsevier BV
- Published
- 2025-12
- Volume
- 6
- Pages
- 100194
- ISSN
- 2666-7215 (ISSN-L)
- OpenAlex
- W7083295476
- Cited by
- 10
- References
- 52
- Citations by year
- 2026: 7 · 2025: 3
- FWCI
- 5.27
- Type
- journal article
- Language
- en
- Open access
- gold
- doi.org
- Licence
- Locations
- Project Leadership and Society (publishedVersion, cc-by)
- Diva portal (Dalarna University Library) (submittedVersion, other-oa)
- DOAJ (DOAJ: Directory of Open Access Journals) (submittedVersion)
- Funders
- Sweden's Innovation Agency
- Svenska Forskningsrådet Formas
- Topics
- Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
- Physical Sciences › Engineering › Building and Construction › Sustainable Building Design and Assessment
- Physical Sciences › Engineering › Building and Construction › Construction Management and Sustainability
- Keywords
- circularity, project life cycle, circular materials, project leadership, project roles, project governance, adaptive governance, sustainability transitions, project organization, customer engagement
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
A language model drew the claims from the paper on 2026-11-10, under version 3 of the claim definition (model deepseek-v4.1-flash, prompt extract-v3).
A second model labelled each claim on 2026-11-10 (model jev-1.13-20260917, definition revision gold-guideline-v0.2).
Cited sources are checked with a language model’s help (gpt-6-sol).
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.